CONSULTANTS DAY:_Thursday___

FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA


Ethiopian Roads Administration DATE:_09/03/23__
HITCON Engineering Plc. Weather: Sunny/Cloudy/Rainy/Windy/Dusty
Supervision of Alaba – Alemgebeya – Hulbareg Routine
Maintenance of Road Projects under Shashemene District
Temperature: at 8:00 am __28___oC
Min.:_______oCMax.:_______oC

DAILY SITE DIARY & PROGRESS REPORT(Alaba-A/Gebeya- Hulbareg Routine


Maintenance)
NUMBER OF SITE STAFF AND LABOUR RECORD
S.nr. Trade Nr. Hrs. S.nr. Trade Nr. Hrs.
1 Forman 2 8
2 Driver 3 8
3 Operator 3 8
4 Labourer 8 8
5
6
7

ON SITE PLANT AND EQUIPMENT


Hours Hours Hours Hours
S/nr. Category number Idle S/nr. Category number Idle
worked worked

1 Spray truck 1 8 13
2 Roller 1 8 14
3 Chip spreader truck 2 8 15
4 Grader 1 8 16
5 Service truck 1 8 17
6 18
7 19
8 20
9 21
10 22

DELIVERY OF MATERIALS ON SITE


S/nr. Material Unit Quantity Remark
1 Asphalt (double bituminous surface treatment) m 2
2800
2 Crushed aggregate m3 50
DESCRIPTION OF WORKS DONE
Sr/nr. Brief description of works Quantity produced Remark
[km, no.] % completed
1 Asphalt sprayed over a road section length of 400m having a width of 7.5m but 2800m2 100
the correction of the curb side was left.

2 Damaged asphalt surface of 35m length with full lane width was excavated and
levelled.
3 Crushed aggregates were spreaded by a chip spreader for a road section of 50m3 100
Length 400m and width 7.5m.
STATUS OF APPROVAL
RF no. Location of work Activity Remark
From To At
1
2
3
ACCIDENT RECORD VISITORS ON SITE
1. No Accident occurred during the reporting date 1.
2. 2.
COMMENTS OR REMARKS ON SITE ACTIVITIES/ SPECIAL PROBLEMS / ATTENTION