Sunkoshi Marin Diversion Multipurpose Project Date : 5-Dec-22

SMEC-EMAY-JADE-CMS JV in
association with ECoCoDE Shift : Day & Night (24hrs)
DAILY REPORT
7 AM to 7 AM
Contract No.: Civil-01/HRT/SMDMP/2077-78 Construction of Headrace Tunnel and Associated Structures
Weather (am) : Sunny Temperature (oC min) : 16
WEATHER

Weather (pm) : Clear Temperature (oC max) : 27


Flooding : Rainfall (mm) : 0
1 5 4 9 8 7
ACTIVITY DESCRIPTION
SEGMENT PLANT:

Production of segmentts completed from ID No. 11915-12034) =120


Segments Produced (no.)
Cumulative Cumulative
Segment Type Repair Reqd. Rejected Remarks
Day Shift Night Shift Daily Total previous day till date

TYPE I 47 50 97 5299 5396 Segment ID No.


11961 (I-B)
TYPE II 13 10 23 5850 5873
TYPE III 0 0 0 765 765
Total 60 60 120 11914 12034

LABORATORY:
Moisture contenet measurement and correction
Regular pH of curing tank, measured PH 9
Compressive strength test of SCM 652-657 (7days) SCM 536 to 542 (28 Days)
Compressive strength test of Concrete CSM 189 (7 Days), CSM -154,155 (28 days)

Compressive strength test CT 113 (7Days), 101 (28 days)


Compressive strength test of MSM 196 (7 days), MSM 177(28 Days)
Cement Test Hongshi OPC 53 grade (fineness, soundness)
Sand and Coarse Aggregate Test: Sieve analysis, clay content, water absorption, specific gravity.
Casting Sampleof Concrete CSM 196
ACTIVITY REPORT FOR SITE

Casting Sample Segment Concrete SCM 691-697


Casting Sampleof Mortar MSM 202
Cement Test Hongshi OPC 53 (Mfd.29,11,2022)
CRUSHING PLANT:
Construction materials (Sand & Aggrigate) Production
TBM PLATFORM:
Transportation of Segment and onloading is going on
Loading of segment, peagravels and cement for TBM tunneling.
ENGINEER CAMP:
Painting of the wall of the house (Type 2-1) with putting. Construction of floor of house (Type 1-1).
Construction of retaining wall (30m3) around the camp area for supporting staffs (Area 1 & Area 2), 26m3.

MADAN BHANDARI HIGHWAY DIVERSION:


Pouring of 23m3 for concreting of retaining wall from Ch. 0+495.00 to 0+500.00m.
Earth filling on the left bank of the river.
Demolding of formwork Ch. 0+305.0 to 0+345.0m retaining wall of express highway.
The collection well of No.3 culvert and the drainage ditch outside the road laid. 7m3.
Scafolding for concreting at highway from ch. 0+335.00 to 0+355.00m
Installation of concrete block on left bank of river.
TUNNEL
Day Shift Night Shift
Activity Description Total Remarks
From To From To
Excavation Length Chainage (m) 1+066.903 1+084.518 1+084.518 1+105.827 38.924 m
Segment Installation Ring no. 723 734 735 750 28 Nos. Type - I
Pea Gravel Injection m3 42 56.00 98 m3
Mortar Injection m3 4.9 5.88 10.78 m3
Cement Grouting m3 30.2 27.6 57.8 m3
HEALTH, SAFETY, ENVIRONMENTAL, SOCIAL :

DELAYS, STANDING TIME & STOPPAGES :

GENERAL COMMENTS
edge of the Segment ring no, 743-E, 747-F, 749-E was cracked/broken during installation at tail skin of the TBM

Prepared by : Ugrasen Chaudhary Pursottam Shilpakar Received by:


Signature: Date Signature: Date: Stamp & signature: Date:
5-Dec-22 5-Dec-22

Tunnel face by manhole Pea gravel injection/backfilling from 1 o'clock hole

Grout mixing for cement grouting Muck in the muck car.

Construction of stone masonry retaining wall at Engineer's camp area Installation of Top Segment type - D.