You are on page 1of 1

Qatar Meta Coats W.L.

L DAILY REPORT REPORT


,: P. O. BOX 12006, DOHA, QATAR No Date
(: (+974) 44114672 / 44114851 Al Bayt Stadium façade works at Sector G Level 103 328 31-Mar-19

7 : (+974) 44114673 | ):
ü: www.qatarmetacoats.com
1. Contract Details
Client Aspire Zone Foundation Consultant KEO
Main Contractor GSIC-JV Façade Contractor Qatar Meta Coats
.
2. Manpower 3. Other Details

Management Labour Total

QMC 12 68 80
GA 23 23
DL 22 22
TOTAL 12 113 125

4. Description of work being planned for the Day 5. Any Special Events / Delay & Downtime - on activities

1 Sector B,D & A Silicon (cont).


2 Sector B,D,F&H Tube installation (CW9&10)
3 Sector E Sandwich panel installation (CW8E1 & E2) cont.
4 Sector B Aluminum installation(CW3)cont.
5 Sector F Glass installation(CW3).cont.
6 Sector E Flashing installation (CW8) cont.
7 Sector E frame installation (CW17) cont
8 Sector G Door alignment (CW18) cont.
9 Sector E glass shifting (104 skybox) cont.
10 All sectors Material shifting,acp,doors+survey works.(lvl 103-106).cont.
11 Sector E Sandwich panel installation skybox (104) cont.
12 Sector B Bracket preparation & welding (CW3) ACP
13 Sector D transom installation & fastening (CW4) ACP cont.
14 Sector F Fastening & alignment of transom (CW2) ACP
15 Sector B Material preparation & shifting (CW3) ACP
16 Sector B & F transom alignment and modification for glass installation (CW4)
6. Description of work being performed on the previous day 7. Any Special Events / Delay & Downtime - on activities

1 Sector B,D & A Silicon (cont).


2 Sector B,D,F&H Tube installation (CW9&10)
3 Sector E Sandwich panel installation (CW8E1 & E2) cont.
4 Sector B Aluminum installation(CW3)cont.
5 Sector F Glass installation(CW3).cont.
6 Sector E Flashing installation (CW8)
7 Sector E frame installation (CW17) cont
8 Sector G Door alignment (CW18)
9 Sector E glass shifting (104 skybox)
10 All sectors Material shifting,acp,doors+survey works.(lvl 103-106).cont.
11 Sector E Sandwich panel installation skybox (104)
12 Sector G Bracket full welding (CW1) ACP
13 Sector D Frame & transom installation (CW4) ACP cont.
14 Sector F Fastening & alignment of transom (CW2) ACP
15 Sector B Material preparation (CW2) ACP
16 Sector C Expansion joint mullion lugplate preparation & installation (CW1) cont.

Equipment Description Active Idle Total Equipment Description Active Idle Total

1 Electrical Operated heavy duty Hilti Drills 5 5 6 Laser leveling equipment 1 1


2 Total Station & survey equipments 2 2 7
3 Magnet drill machine 3 3 8
4 Mobile crane 18 tonnes 1 1 9
5 Slide Compound Saw 1 1 10
5 Vacuum based glass lifting device 1 2 3 Total 14 2 16

9. Manpower Report
Management ONSITE No of Hours Labour No. of People Hrs Total Hours

1 Project Enginner 3 8 1 Lead hand/ foreman 6 10 60


2 Site Supervisor 2 8 2 Technician 45 10 450
3 Safety Officer / Asst. S.O 3 8 3 Welder 4 10 40

4 Land surveyor 3 8 4 Rigger 1 10 10

5 Store keeper 1 8 5 Helper 27 10 270

6 QC engineer 1 8 6 Crane operator 1 10 10


7 Manager 1 8 7 Electrician 1 8 8

8 Drvier 1 10 10

Total Manhours 914


10. Material deliveries (on Previous day)

1
2
3

Note; Please mention material name, type, spec., quantity & manufacturer / supplier details.
11. Remarks

Report Prepared by: Jeran

Contractor: QMC

Date: 3/3/2019

4/1/2019 Page 1 of 1