North Jeddah Bulk Plant Restoration


27 Executive Summary
HSE:
Stop work initiated due to high winds on the 26th September. Normal work resumed today 27th September.

Progress:
Manpower
WBS Planned Actual
601
Engineering 90.63% 98.38%
Procurement 68.54% 86.53%
PMT 41,910 Construction 44.96% 56.10%
MHs GES+ 33,740
Cont 1,458020
Procurement:
o 2 off Gauge Hatch
LTI 0 o 1 Lot Cathodic Protection
RDI 0
No. Description Unit QTY Total # PO POs Placed Delivered ETA
MTC 0
1 Pipes M 900 4 4 900 Delivered
FAI 1 2 Pipe fittings Each 383 11 11 383 Delivered
3 Valves Each 165 9 9 165 Delivered
NM 27 4 ENI Cables M 88,000 5 5 88,000 Delivered
COVID-19 0 Electrical (CP,glands,
5 Each 9,117 15 15 8,641 Sep 30th, 2022
etc.)
6 Instruments Each 95 15 15 65 Nov 15th, 2022
7 Structure Steel Ton 13.7 8 8 13.7 Delivered
8 Tanks Ton 1000 4 4 1000 Delivered
9 FW equipment Each 10 3 3 6 Oct 15th, 2022

Demolition:

Description Planned Actual


Demolition 67.68% 74.58%

o No major highlight.

Restoration

Description Planned Actual


Restoration 29.64% 44.75%

o Completed 32% of tank T-103 shells and base plate fabrication.


o Completed 96% of HDPE liner installation for T-103 foundation.
o Completed 95% of CP grid installation T-103
o Completed 1,750 out of 1,760 termination for electrical connections.
o Completed 6,580 out of 6,600 termination for Instrumentation connections.
o Completed 95.55% of Shell #7 welding for T-103.

Challenges:

o Tank 102 remains with product preventing restoration team from executing the conversion of tank to Diesel/ Jet.
o Tank 109 remains with product preventing restoration team from completing internal tank assessment.