1) Water Filling 75% - 100% for 80-TK-121 1) Water Filling 75% - 100% for 80-TK-121
4 ATM 2) Holding time of Hydro test for 80-TK-131 2) Holding time of Hydro test for 80-TK-131
3) Dismantling of Scaffolding for 80-TK-601 3) Erection of Roof Plate for 80-TK-211
4) Dismantling of Scaffolding for 80-TK-512 4) Welding of 10H (Outside) for 80-TK-221
5) Installation of Center Platform for 80-TK-601
6) Prepare Erection of Stairway for 80-TK-412
WP 4 7) Welding of Top Angle for 80-TK-421
8) Welding of Top Angle for 80-TK-511 A/B
9) Prepare of Hydrotest for 80-TK-512
10) Erection of Stairway for 80-TK-541
Page 1 of 7
2. MANPOWER / EQUIPMENT STATUS 2023-10-22 30° C
0) PT. DAEAH E&C INDONESIA
MANPOWER
No. Description Unit Previous Today Cumulative
1) Korean staff MD 1,853 - 1,853
2) Local staff MD 50,761 64 50,825
Sub-Total MD 52,614 64 52,678
Page 2 of 7
Page 3 of 7
3. SITE PHOTO 2023-10-22 30° C
4) ATM WP 4 & 5
Page 5 of 7
WP 4 Sub Total 1,873 1,771 - 1,771 95%
80-TK-221 ton 292 237 - 237 81%
Install Annular/Bottom ton 31 31 - 31 100%
Install Shell Plate ton 169 169 - 169 100%
Install Misc. ton 93 37 - 37 40%
80-TK-211 ton 133 124 - 124 93%
Install Annular/Bottom ton 21 21 - 21 100%
Install Shell Plate ton 64 64 - 64 100%
Install Misc. ton 48 39 - 39 80%
80-TK-241 ton 17 16 - 16 100%
Install Annular/Bottom ton 3 3 - 3 100%
Install Shell Plate ton 8 8 - 8 100%
Install Misc. ton 6 6 - 6 100%
80-TK-601 ton 425 425 - 425 100%
Install Annular/Bottom ton 76 76 - 76 100%
Install Shell Plate ton 218 218 - 218 100%
Install Misc. ton 130 130 - 130 100%
80-TK-512 ton 51 49 - 49 97%
Install Annular/Bottom ton 8 8 - 8 100%
Install Shell Plate ton 26 26 - 26 100%
Install Misc. ton 17 15 - 15 90%
80-TK-541 ton 76 70 - 70 93%
Install Annular/Bottom ton 15 15 - 15 100%
Install Shell Plate ton 32 32 - 32 100%
Install Misc. ton 29 24 - 24 82%
80-TK-511A ton 99 89 - 89 90%
A W
T Install Annular/Bottom ton 16 16 - 16 100%
M P
Install Shell Plate ton 50 50 - 50 100%
4
Install Misc. ton 33 23 - 23 70%
80-TK-511B ton 99 89 - 89 90%
Install Annular/Bottom ton 16 16 - 16 100%
Install Shell Plate ton 50 50 - 50 100%
Install Misc. ton 33 23 - 23 70%
80-TK-411 ton 82 80 - 80 98%
Install Annular/Bottom ton 12 12 - 12 100%
Install Shell Plate ton 46 46 - 46 100%
Install Misc. ton 24 23 - 23 93%
80-TK-412 ton 49 46 - 46 94%
Install Annular/Bottom ton 7 7 - 7 100%
Install Shell Plate ton 25 25 - 25 100%
Install Misc. ton 17 14 - 14 82%
80-TK-421 ton 36 32 - 32 87%
Install Annular/Bottom ton 4 4 - 4 100%
Install Shell Plate ton 20 20 - 20 100%
Install Misc. ton 12 7 - 7 61%
80-TK-121 ton 485 485 - 485 100%
Install Annular/Bottom ton 76 76 - 76 100%
Install Shell Plate ton 243 243 - 243 100%
Install Misc. ton 166 166 - 166 100%
80-TK-131 ton 30 30 - 30 100%
Install Annular/Bottom ton 5 5 - 5 100%
Install Shell Plate ton 13 13 - 13 100%
Install Misc. ton 12 12 - 12 100%
Page 6 of 7
1. STEEL STRUCTURE 단위 : TON
Pre 운송 준비 완료
구분 계약 Shop 도착 현장 도착
Fabrication (To 현장)