You are on page 1of 7

KINE

TANK CONSTRUCTION DAILY REPORT PROJECT JO

Project : LINE PROJECT Date: 2023-10-22


Client : LOTTE CHEMICAL INDONESIA Weather: 30° C
1. Construction Status

No. Discipline Area Today 10/22/2023 Tomorrow 10/23/2023 Remark


1) Grinding of 3H (Inside) for 90-TK-407 1) Installation of Air Foam Pipe for 90-TK-401 A
2) Installation of Scaffolding (Outside)for 90-TK-409 B 2) Smooth Grinding for IFR for 90-TK-401 B
3) Welding of Accessories (Nozzle, Rafter, etc) for 90-TK-404 A/B
4) Installation of Accessories (Drain Sump, Nozzle, Etc) for 90-TK-406
5) Welding of Wind Girder for 90-TK-407
WP 5
6) Smooth Grinding for 90-TK-408
7) Welding of Top Angle for 90-TK-409 A
8) Fit-up / Welding of Roof Plate for 90-TK-409 B

1) Water Filling 75% - 100% for 80-TK-121 1) Water Filling 75% - 100% for 80-TK-121
4 ATM 2) Holding time of Hydro test for 80-TK-131 2) Holding time of Hydro test for 80-TK-131
3) Dismantling of Scaffolding for 80-TK-601 3) Erection of Roof Plate for 80-TK-211
4) Dismantling of Scaffolding for 80-TK-512 4) Welding of 10H (Outside) for 80-TK-221
5) Installation of Center Platform for 80-TK-601
6) Prepare Erection of Stairway for 80-TK-412
WP 4 7) Welding of Top Angle for 80-TK-421
8) Welding of Top Angle for 80-TK-511 A/B
9) Prepare of Hydrotest for 80-TK-512
10) Erection of Stairway for 80-TK-541

Page 1 of 7
2. MANPOWER / EQUIPMENT STATUS 2023-10-22 30° C
0) PT. DAEAH E&C INDONESIA
MANPOWER
No. Description Unit Previous Today Cumulative
1) Korean staff MD 1,853 - 1,853
2) Local staff MD 50,761 64 50,825
Sub-Total MD 52,614 64 52,678

4) ATM (WP 4 & 5)


MANPOWER (WP 4) EQUIPMENT (WP 4)
No. Description Unit Previous Today Cumulative No. Equipment Spec. Previous Today Cumulative Previous
1) Site Manager MD 215 - 215 1) Hydro crane 60 ton 206 - 206 Site Man
2) Administration Manager MD 163 - 163 2) Crawler crane 150 ton 50 - 50 Administ
3) Construction Manager MD 370 - 370 3) Forklift 7 ton 223 1 ###
224
4) QC Manager MD 173 - 173 4) Boom truck - - QC Mana
5) Safety Staff (Supervisor,officer,P/Holder) MD 1,065 - 1,065 5) Trailer 202 - 202 Safety St
6) Tank Engineer MD 224 - 224 6) Scissors lift - - Tank Eng
7) QC MD 1,093 - 1,093 7) Man lift 211 2 213 QC
8) Welder (Auto) MD 239 - 239 8) Pick Up Truck 1 ton 376 1 377 Welder (
9) Welder (Manual) MD 6,229 3 6,232 9) Hydro crane 70 ton 198 - 198 Welder (
10) Fitter MD 4,013 - 4,013 10) Mini Bus 168 - 168 Fitter
11) Grinder MD - - - 11) Bus 131 1 132 Grinder
12) Rigger MD 1,230 - 1,230 12) Hydro crane 80 ton 79 - 79 Rigger
13) Electrician MD 427 3 430 13) Hydro crane 50 ton 22 - 22 Electricia
14) Others MD 158 - 158 Others
15) Supervisor MD 206 - 206 Supervis
16) Staff (Accountant,Admin,D/controller) MD 750 - 750 Staff (Ac
17) Driver MD 501 1 502 Driver
18) Foreman MD 896 - 896 Foreman
19) Operator(Crane,Trailer,F/Lift) MD 390 - 390 Operator
20) Scaffold MD 1,892 17 1,909 Scaffold
21) Material Control Engineer MD 129 - 129 Sub-Total 1,867 5 1,872 Material
22) Tool Keeper MD 429 - 429 Tool Kee
23) Flagman MD 503 - 503 Flagman
24) Helper MD 4,089 3 4,092 Helper
25) House Keeper MD 82 - 82 House K
26) Watch Man MD - - - Watch M
27) Fire Watcer MD 280 - 280
28) Hole Watcher MD 187 - 187
Sub-Total MD 25,934 27 25,961 ###

MANPOWER (WP 5) EQUIPMENT (WP 5)


No. Description Unit Previous Today Cumulative No. Equipment Spec. Previous Today Cumulative
1) Site Manager MD 144 - 144 1) Hydro crane 60 ton 77 1 ###
78
2) Administration Manager MD 208 - 208 2) Hydro crane 100 ton 145 - 145
3) Construction Manager MD 354 - 354 3) Forklift 7 ton 98 - 98
4) QC Manager MD 226 - 226 4) Boom truck 61 - 61
5) Safety Staff (Supervisor,officer,P/Holder) MD 1,067 - 1,067 5) Trailer 281 - 281
6) Tank Engineer MD 245 - 245 6) Scissors lift - - -
7) QC MD 1,135 - 1,135 7) Man lift 81 1 82
8) Welder (Auto) MD 239 - 239 8) Pick Up Truck 1 ton 274 2 276
9) Welder (Manual) MD 6,473 12 6,485 9) Hydro crane 50 ton 128 - 128
10) Fitter MD 4,140 - 4,140 10) Mini Bus 210 1 211
11) Grinder MD - - - 11) Hydro crane 160 ton 72 - 72
12) Rigger MD 1,268 - 1,268
13) Electrician MD 441 3 444
14) Others MD 187 - 187
15) Supervisor MD 222 - 222
16) Staff (Accountant,Admin,D/controller) MD 763 - 763
17) Driver MD 530 1 531
18) Foreman MD 889 - 889
19) Operator(Crane,Trailer,F/Lift) MD 387 - 387
20) Scaffold MD 1,925 18 1,943
21) Material Control Engineer MD 66 - 66 Sub-Total 1,426 5 1,431
22) Tool Keeper MD 449 - 449
23) Flagman MD 483 - 483
24) Helper MD 4,227 3 4,230
25) House Keeper MD 146 - 146
26) Watch Man MD - - -
27) Fire Watcer MD 280 - 280
28) Hole Watcher MD 187 - 187
Sub-Total MD 26,680 37 26,717

Page 2 of 7
Page 3 of 7
3. SITE PHOTO 2023-10-22 30° C

4) ATM WP 4 & 5

Installation of Scaffolding (Outside)for 90-TK-409 B Grinding of 3H (Inside) for 90-TK-407

Dismantling of Scaffolding for 80-TK-601


1. Progress of Work 2023-10-22 Weather : 30° C
Work Quantity
Item Unit Remark
Total (A) Up to Last Today Accum.(B) (B/A) %
ATM Total 4,122 3,765 - 3,765 91%
WP 5 Sub Total 2,249 1,994 - 1,994 89%
90-TK-401A ton 344 344 - 344 100%
Install Annular/Bottom ton 69 69 - 69 100%
Install Shell Plate ton 129 129 - 129 100%
Install Misc. ton 146 146 - 146 100%
90-TK-401B ton 344 344 - 344 100%
Install Annular/Bottom ton 69 69 - 69 100%
Install Shell Plate ton 129 129 - 129 100%
Install Misc. ton 146 146 - 146 100%
90-TK-403 ton 96 96 - 96 100%
Install Annular/Bottom ton 19 19 - 19 100%
Install Shell Plate ton 44 44 - 44 100%
Install Misc. ton 33 33 - 33 100%
90-TK-404A ton 222 173 - 173 78%
Install Annular/Bottom ton 43 43 - 43 100%
Install Shell Plate ton 82 82 - 82 100%
Install Misc. ton 97 48 - 48 49%
90-TK-404B ton 222 187 - 187 84%
Install Annular/Bottom ton 43 43 - 43 100%
Install Shell Plate ton 82 82 - 82 100%
Install Misc. ton 97 62 - 62 63%
90-TK-405 ton 235 184 - 184 78%
A W
T Install Annular/Bottom ton 45 45 - 45 100%
M P
Install Shell Plate ton 95 95 - 95 100%
5
Install Misc. ton 96 45 - 45 47%
90-TK-406 ton 235 177 - 177 75%
Install Annular/Bottom ton 45 45 - 45 100%
Install Shell Plate ton 95 95 - 95 100%
Install Misc. ton 96 38 - 38 40%
90-TK-407 ton 235 204 - 204 87%
Install Annular/Bottom ton 45 45 - 45 100%
Install Shell Plate ton 95 95 - 95 100%
Install Misc. ton 96 65 - 65 68%
90-TK-408 ton 99 83 - 83 84%
Install Annular/Bottom ton 19 19 - 19 100%
Install Shell Plate ton 47 47 - 47 100%
Install Misc. ton 33 17 - 17 52%
90-TK-409A ton 108 100 - 100 93%
Install Annular/Bottom ton 19 19 - 19 100%
Install Shell Plate ton 54 54 - 54 100%
Install Misc. ton 35 27 - 27 77%
90-TK-409B ton 108 102 - 102 95%
Install Annular/Bottom ton 19 19 - 19 100%
Install Shell Plate ton 54 54 - 54 100%
Install Misc. ton 35 29 - 29 85%

Page 5 of 7
WP 4 Sub Total 1,873 1,771 - 1,771 95%
80-TK-221 ton 292 237 - 237 81%
Install Annular/Bottom ton 31 31 - 31 100%
Install Shell Plate ton 169 169 - 169 100%
Install Misc. ton 93 37 - 37 40%
80-TK-211 ton 133 124 - 124 93%
Install Annular/Bottom ton 21 21 - 21 100%
Install Shell Plate ton 64 64 - 64 100%
Install Misc. ton 48 39 - 39 80%
80-TK-241 ton 17 16 - 16 100%
Install Annular/Bottom ton 3 3 - 3 100%
Install Shell Plate ton 8 8 - 8 100%
Install Misc. ton 6 6 - 6 100%
80-TK-601 ton 425 425 - 425 100%
Install Annular/Bottom ton 76 76 - 76 100%
Install Shell Plate ton 218 218 - 218 100%
Install Misc. ton 130 130 - 130 100%
80-TK-512 ton 51 49 - 49 97%
Install Annular/Bottom ton 8 8 - 8 100%
Install Shell Plate ton 26 26 - 26 100%
Install Misc. ton 17 15 - 15 90%
80-TK-541 ton 76 70 - 70 93%
Install Annular/Bottom ton 15 15 - 15 100%
Install Shell Plate ton 32 32 - 32 100%
Install Misc. ton 29 24 - 24 82%
80-TK-511A ton 99 89 - 89 90%
A W
T Install Annular/Bottom ton 16 16 - 16 100%
M P
Install Shell Plate ton 50 50 - 50 100%
4
Install Misc. ton 33 23 - 23 70%
80-TK-511B ton 99 89 - 89 90%
Install Annular/Bottom ton 16 16 - 16 100%
Install Shell Plate ton 50 50 - 50 100%
Install Misc. ton 33 23 - 23 70%
80-TK-411 ton 82 80 - 80 98%
Install Annular/Bottom ton 12 12 - 12 100%
Install Shell Plate ton 46 46 - 46 100%
Install Misc. ton 24 23 - 23 93%
80-TK-412 ton 49 46 - 46 94%
Install Annular/Bottom ton 7 7 - 7 100%
Install Shell Plate ton 25 25 - 25 100%
Install Misc. ton 17 14 - 14 82%
80-TK-421 ton 36 32 - 32 87%
Install Annular/Bottom ton 4 4 - 4 100%
Install Shell Plate ton 20 20 - 20 100%
Install Misc. ton 12 7 - 7 61%
80-TK-121 ton 485 485 - 485 100%
Install Annular/Bottom ton 76 76 - 76 100%
Install Shell Plate ton 243 243 - 243 100%
Install Misc. ton 166 166 - 166 100%
80-TK-131 ton 30 30 - 30 100%
Install Annular/Bottom ton 5 5 - 5 100%
Install Shell Plate ton 13 13 - 13 100%
Install Misc. ton 12 12 - 12 100%

Page 6 of 7
1. STEEL STRUCTURE 단위 : TON

2. ATM TANK 단위 : TON

Pre 운송 준비 완료
구분 계약 Shop 도착 현장 도착
Fabrication (To 현장)

WP4 1,874 10 50 1,814

WP5 2,248 10 270 1,968

Total 4,122 20 320 - 3,782

You might also like