4 Pier Nos 68 - 68
B VIADUCT
1 Pile Nos 395 4 22 373
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
T
2/22/2023
Remarks
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
CT
2/23/2023
Remarks
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday
1
expected from tonight .
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 2/24/2023
Balance Remarks
201
208
03 nos. pile cap Steel cutting & Bending
68 & 08 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 50
2 PIT/Sonic Test 619 - 16
3 Pile cap Nos 173 - -
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
1
expected from tonight .
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
Date: 2/25/2023
Balance Remarks
IECCL Executed
S.N. Description of Work Unit Today
SCOPE upto Prev.
A STATIONS + VIADUCT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
OJECT
ORT
Date: 2/26/2023
Cumul-
Balance Remarks
ative
16 603
03 nos. pile cap Steel cutting & Bending
- 173 & 12 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 51
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 2/27/2023
Balance Remarks
603
03 nos. pile cap Steel cutting & Bending
173 & 12 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 53
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 3/1/2023
Balance Remarks
566
603
03 nos. pile cap Steel cutting & Bending
173 & 12 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 55
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 3/2/2023
Balance Remarks
564
603
03 nos. pile cap Steel cutting & Bending
173 & 17 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 57
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT -done Total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25mm
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Batching Plant- CP-30 tested OK - but due to non availability of Machinery i.e. Loader & Transit Mixer unable to produce
Due to Non availability of Back Hoe Loader (JCB) & Hydra/Farana Casting yard development work suffered. Needs to be
3
hire from external agencies.
ECT
T
Date: 3/3/2023
Balance Remarks
562
603
03 nos. pile cap Steel cutting & Bending
173 & 17 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 59
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT -done Total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25mm-16.07-
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Batching Plant- CP-30 tested OK - but due to non availability of Machinery i.e. Loader & Transit Mixer unable to produce
Due to Non availability of Back Hoe Loader (JCB) & Hydra/Farana Casting yard development work suffered. Needs to be
3
from external agencies.
OJECT
ORT
Date: 3/4/2023
Balance Remarks
560
599
03 nos. pile cap Steel cutting & Bending & 17
173 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 59
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT -done Total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25mm-16.07-
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Batching Plant- CP-30 tested OK - but due to non availability of Machinery i.e. Loader & Transit Mixer unable to produce
Due to Non availability of Back Hoe Loader (JCB) & Hydra/Farana Casting yard development work suffered. Needs to be
3
from external agencies.
OJECT
ORT
Date: 3/5/2023
Balance Remarks
560
743
03 nos. pile cap Steel cutting & Bending & 17
173 nos. PCC Completed.
IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 61
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Recievedd total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25
5 TMT Bars - PO for 665-MT -done Critical dia - 20mm Dia only 1.2-MT available at site
Bulk Material i.e. Cement, Sand, Aggregate,
6 36-MT Coarse Sand received 06-03-2023
Plasticizer - Purchase Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works. (Day time both plants denied to c
Due to Non availability of Back Hoe Loader (JCB) at Casting yard development work suffered. Needs to be internal site tr
2
agencies.
OJECT
ORT
Date: 3/6/2023
Balance Remarks
558
702
03 nos. pile cap Steel cutting & Bending & 17
173 nos. PCC Completed.
IECCL Executed
S.N. Description of Work Unit Today
SCOPE upto Prev.
A STATIONS + VIADUCT
1 Pile Nos 619 61 5
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 128-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - Stock in critical - NIL at site IECCL yard.
Bulk Material i.e. Cement, Sand, Aggregate,
6 36-MT Coarse Sand received 06-03-2023
Plasticizer - Purchase Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Due to Non availability of Back Hoe Loader (JCB) at Casting yard development work suffered. Needs to be internal site tr
PROJECT
EPORT
Date: 3/9/2023
Cumul-
Balance Remarks
ative
72 702
03 nos. pile cap Steel cutting & Bending & 17
- 173 nos. PCC Completed.
eeds to be internal site transfer from AMRP or hire from external agencies.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
IECCL Cumul-
S.N. Description of Work Unit Today Balance
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 3 69 550
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 128-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - Stock in critical - NIL at site IECCL yard.
Bulk Material i.e. Cement, Sand, Aggregate,
6 36-MT Coarse Sand received 06-03-2023
Plasticizer - Purchase Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
ROJECT
PORT
3/10/2023
Remarks
03 nos. pile cap Steel cutting & Bending & 17 nos. PCC
Completed.
CCL yard.
.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 160-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand,
6 Aggregate, Plasticizer - Purchase 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & a
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
O RAIL PROJECT
GRESS REPORT
Date: 3/11/2023
Working Days (Sunday Half day working) 18
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
03 nos. pile cap Steel cutting & Bending & 20 nos. PCC
- 173 Completed & for Convention Centre pile cap & pier labour
reached at site.
- - 178
from 06-03-23
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJE
DAILY PROGRESS REPORT
Working Days (S
PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT
1 Pile Nos 619 179 21 158 9.3
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 160-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand,
6 Aggregate, Plasticizer - Purchase 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & a
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/12/2023
Working Days (Sunday Half day working) 17
ACHIEVED
72 72 702
03 nos. pile cap Steel cutting & Bending & 20 nos. PCC
- - 173 Completed & for Convention Centre pile cap & pier labour
reached at site.
- - - 178
from 06-03-23
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase 01 Bulker Cement - 39.01 MT Received on 13.03.2023
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
O RAIL PROJECT
GRESS REPORT
Date: 3/13/2023
Working Days (Sunday Half day working) 16
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
03 nos. pile cap Steel cutting & Bending & 20 nos. PCC
- 173 Completed & for Convention Centre.Pile Cap Steel Cutting,
Bending started at Casting yard.
- - 178
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023
23
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJE
DAILY PROGRESS REPORT
Working Days (S
PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase 01 Bulker Cement - 39.01 MT Received on 13.03.2023
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/14/2023
Working Days (Sunday Half day working) 15
ACHIEVED
72 72 702
02 nos. pile cap Steel cutting & Bending & 21 nos. PCC
- - 173 Completed & for Convention Centre.Pile Cap Steel Cutting,
Bending started at Casting yard.
- - - 178
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023
23
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical Only @ 3.9-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delive
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/15/2023
Working Days (Sunday Half day working) 14
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178
from 06-03-23
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.9-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/16/2023
Working Days (Sunday Half day working) 13
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 1-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/17/2023
Working Days (Sunday Half day working) 12
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.5-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/18/2023
Working Days (Sunday Half day working) 11
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.5-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/19/2023
Working Days (Sunday Half day working) 11
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 484-MT recieved IECCL procurement out of 650-Mt received 215-MT + (fro
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.5-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/20/2023
Working Days (Sunday Half day working) 10
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
from 06-03-23
0-Mt received 215-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 484-MT recieved IECCL procurement out of 650-Mt received 215-MT + (fro
5 TMT Bars - PO for 665-MT -done 20mm 2.1 MT & 25mm 1.2 MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/21/2023
Working Days (Sunday Half day working) 9
ACHIEVED
Cumul- Remarks
Today Balance
ative
01 Pile Bore Collapse during the cage lowering at Women ITI STNS
Another 04nos. Hydraulic Rig machine yet to operational due to
3 101 518 their Tools & Accessries arrangement expected 01 nos start by 23-
03-23 , 02nos. By 25-03-23 & 01nos. 27-03-23.
01 Rig Machine Sany-185 display theft from P8-4 Vaiduct.
72 702
from 06-03-23
0-Mt received 215-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 484-MT recieved IECCL procurement out of 650-Mt received 215-MT + (fro
5 TMT Bars - PO for 665-MT -done 20mm 0.5 MT & 25mm 0.2 MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/22/2023
Working Days (Sunday Half day working) 8
ACHIEVED
Cumul- Remarks
Today Balance
ative
01 Pile Bore Collapse during the cage lowering at Women ITI STNS
Another 04nos. Hydraulic Rig machine yet to operational due to
3 104 515 their Tools & Accessries arrangement expected 01 nos start by 23-
03-23 , 02nos. By 25-03-23 & 01nos. 27-03-23.
01 Rig Machine Sany-185 display theft from P8-4 Vaiduct.
72 702
from 06-03-23
0-Mt received 215-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL & 20mm -3.9-MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/23/2023
Working Days (Sunday Half day working) 7
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL & 20mm -3.9-MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/24/2023
Working Days (Sunday Half day working) 6
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL & 20mm -3.9-MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/25/2023
Working Days (Sunday Half day working) 5
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 702
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/27/2023
Working Days (Sunday Half day working) 4
ACHIEVED
112 4 116 503 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 28-
03-23 , 01nos. By 31-03-23 & 01nos. 01-04-23.
72 72 702
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/28/2023
Working Days (Sunday Half day working) 3
ACHIEVED
Cumul- Remarks
Today Balance
ative
4 120 499 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 28-
03-23 , 01nos. By 31-03-23 & 01nos. 01-04-23.
72 702
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/29/2023
Working Days (Sunday Half day working) 2
ACHIEVED
120 3 123 545 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 30-
03-23 , 01nos. By 31-03-23 & 01nos. 01-04-23.
72 72 763
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/30/2023
Working Days (Sunday Half day working) 1
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 763
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/31/2023
Working Days (Sunday Half day working) 0
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 763
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 4/1/2023
Working Days (Sunday Half day working) 29
ACHIEVED
Cumul- Remarks
Today Balance
ative
72 763
from 06-03-23
0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 297-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/2/2023
Working Days (Sunday Half day working) 28
ACHIEVED
72 72 763
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 297-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/3/2023
Working Days (Sunday Half day working) 27
ACHIEVED
72 72 763
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-3 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/4/2023
Working Days (Sunday Half day working) 26
ACHIEVED
145 9 154 514 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 03-
03-23 & 01nos. 04-04-23.
72 72 763
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-3 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/5/2023
Working Days (Sunday Half day working) 25
ACHIEVED
154 5 159 509 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
03-23 & 01nos by 10-04-23.
72 72 763
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 02 erected 03 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-2 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/6/2023
Working Days (Sunday Half day working) 24
ACHIEVED
159 5 164 504 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.
72 72 763
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 02 erected 03 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-2 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/7/2023
Working Days (Sunday Half day working) 23
ACHIEVED
72 72 763
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 02 erected 03 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/8/2023
Working Days (Sunday Half day working) 22
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 04 erected 01 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/9/2023
Working Days (Sunday Half day working) 21
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/10/2023
Working Days (Sunday Half day working) 20
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/11/2023
Working Days (Sunday Half day working) 19
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/12/2023
Working Days (Sunday Half day working) 18
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/13/2023
Working Days (Sunday Half day working) 17
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/14/2023
Working Days (Sunday Half day working) 16
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/15/2023
Working Days (Sunday Half day working) 15
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/16/2023
Working Days (Sunday Half day working) 14
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/17/2023
Working Days (Sunday Half day working) 13
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/18/2023
Working Days (Sunday Half day working) 12
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/19/2023
Working Days (Sunday Half day working) 11
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 405-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/20/2023
Working Days (Sunday Half day working) 10
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 405-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/21/2023
Working Days (Sunday Half day working) 9
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 405-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/22/2023
Working Days (Sunday Half day working) 8
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 488-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/23/2023
Working Days (Sunday Half day working) 7
ACHIEVED
72 72 763
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-9.82 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/24/2023
Working Days (Sunday Half day working) 6
ACHIEVED
72 8 80 755
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-9.82 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/25/2023
Working Days (Sunday Half day working) 5
ACHIEVED
72 8 80 755
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-8 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/26/2023
Working Days (Sunday Half day working) 4
ACHIEVED
72 8 80 755
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/27/2023
Working Days (Sunday Half day working) 3
ACHIEVED
72 8 80 755
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/28/2023
Working Days (Sunday Half day working) 2
ACHIEVED
72 8 80 755
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/29/2023
Working Days (Sunday Half day working) 1
ACHIEVED
72 8 80 755
from 06-03-23
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/30/2023
Working Days (Sunday Half day working) 0
ACHIEVED
72 8 80 755
from 06-03-23
PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the May- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 5/1/2023
ACHIEVED
80 80 755
from 06-03-23
PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the May- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/2/2023
ACHIEVED
80 80 755
from 06-03-23
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/3/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
1 1 2.0 176 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress
from 06-03-23
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/4/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
2 2.0 176 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress
from 06-03-23
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & Sonic Pipe
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/5/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
2 2.0 176 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & Sonic Pipe
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/6/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
2 1 3.0 175 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & Sonic Pipe
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/8/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
3 3.0 175 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/9/2023
ACHIEVED
80 80 755
07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
3 1 4.0 174 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & 8mm dia TMT
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/10/2023
ACHIEVED
80 80 755
07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
4 4.0 174 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group
Pile Head Chipping in progress
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/11/2023
ACHIEVED
80 80 755
07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
4 1 5.0 173 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/13/2023
ACHIEVED
80 80 755
07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
5 1 6.0 172 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/14/2023
ACHIEVED
80 80 755
07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
6 6.0 172 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/16/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
6 1 7.0 171 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/17/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
7 7.0 171 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/18/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
7 1 8.0 170 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/19/2023
ACHIEVED
80 80 755
06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
8 1 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/20/2023
ACHIEVED
80 80 755
05 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/21/2023
ACHIEVED
80 80 755
05 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/22/2023
ACHIEVED
80 80 758
05 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
80 80 758
04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 1 10 168 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
80 80 758
04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
10 1 11 167 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
80 80 758
04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
11 11 167 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
80 80 758
04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
11 1 12 166 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
80 80 758
04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
12 12 166 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
80 80 758
04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
12 12 166 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
80 15 95 743
04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
12 1 13 165 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
95 10 105 733
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
13 1 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 1 15 163 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/9/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 1 15 163 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/10/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
16 1 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/11/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
16 1 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/12/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 - 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/13/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 - 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 96% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/14/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/15/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/16/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/17/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/18/2023
ACHIEVED
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
18 1 19 159 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988
from 06-03-23
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.
PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED
Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate
4.7 19 1 20 158
1.8 - - 183
- - 104
- - 938
- - 1,988
Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.
Remarks
02 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct
mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO
PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED
Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate
5.3 20 - 20 158
2.0 - - 183
- - 104
- - 938
- - 1,988
Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.
Remarks
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct
mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO
PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED
Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate
6.0 20 - 20 158
2.3 - - 183
- - 104
- - 938
- - 1,988
Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.
Remarks
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct
mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO
PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED
Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate
7.0 20 - 20 158
2.7 - - 183
- - 104
- - 938
- - 1,988
Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.
Remarks
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct
mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO
PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED
Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate
8.4 20 - 20 158
3.2 - - 183
- - 104
- - 938
- - 1,988
Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.
Remarks
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct
PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED
Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate
10.5 20 - 20 158
3.8 - 1 1 182
- - 104
- - 938
- - 1,988
Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.
Remarks
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct
PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23
A STATIONS + VIADUCT
OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED
Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate
13.7 20 1 21 157
5.0 1 - 1 182
- - 104
- - 938
- - 1,988
Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.
Remarks
03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct