SURAT METRO RAIL PROJECT

DAILY PROGRESS REPORT


Date
IECCL Cumul-
S.N. Description of Work Unit Today Balance
SCOPE ative
A STATIONS
1 Pile Nos 224 23 201
2 PIT/Sonic Test 224 16 16 208

3 Pile cap Nos 68 - 68

4 Pier Nos 68 - 68
B VIADUCT
1 Pile Nos 395 4 22 373

2 PIT/Sonic Test Nos 395 - 395


3 Pile Cap Nos 105 - 105
4 Pier Nos 110 - 110

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
T

2/22/2023
Remarks

03 nos. pile cap Steel cutting &


Bending & 08 nos. PCC Completed.

Further 09 nos. pile group Utility


checking completed.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date
IECCL Cumul-
S.N. Description of Work Unit Today Balance
SCOPE ative
A STATIONS
1 Pile Nos 224 23 201
2 PIT/Sonic Test 224 0 16 208
3 Pile cap Nos 68 - 68
B VIADUCT
1 Pile Nos 395 0 22 373

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
CT

2/23/2023
Remarks

03 nos. pile cap Steel cutting & Bending


& 08 nos. PCC Completed.

01 Pile Boring in progress & 10 nos.


pile group Utility checking completed.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Executed Cumul-


S.N. Description of Work Unit Today
SCOPE upto Prev. ative
A STATIONS
1 Pile Nos 224 23 23

2 PIT/Sonic Test 224 16 - 16

3 Pile cap Nos 68 - -


B VIADUCT
1 Pile Nos 395 22 3 25

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday
1
expected from tonight .
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 2/24/2023
Balance Remarks

201

208
03 nos. pile cap Steel cutting & Bending
68 & 08 nos. PCC Completed.

11 nos. pile group Utility checking


370 completed.

nd Payment done yesterday material delievery schedule


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 50
2 PIT/Sonic Test 619 - 16
3 Pile cap Nos 173 - -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
1
expected from tonight .
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT

Date: 2/25/2023
Balance Remarks

12 nos. pile group Utility checking


569 completed.
603
03 nos. pile cap Steel cutting &
173 Bending & 08 nos. PCC Completed.

Payment done yesterday material delievery schedule


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Executed
S.N. Description of Work Unit Today
SCOPE upto Prev.
A STATIONS + VIADUCT

1 Pile Nos 619 50 1

2 PIT/Sonic Test 619 16 -

3 Pile cap Nos 173 - -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
OJECT
ORT
Date: 2/26/2023
Cumul-
Balance Remarks
ative

Utility Checking Completed between


51 568 Convention Centre to Bhimrad Station.

16 603
03 nos. pile cap Steel cutting & Bending
- 173 & 12 nos. PCC Completed.

ayment done yesterday material delievery awaited.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 51

2 PIT/Sonic Test 619 16

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 2/27/2023
Balance Remarks

Work stopeed due to non availability of


568 20mm & 25mm dia TMT Bar .

603
03 nos. pile cap Steel cutting & Bending
173 & 12 nos. PCC Completed.

Payment done yesterday material delievery awaited.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 53

2 PIT/Sonic Test 619 16

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 3/1/2023
Balance Remarks

566

603
03 nos. pile cap Steel cutting & Bending
173 & 12 nos. PCC Completed.

Payment done yesterday material delievery awaited.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 55

2 PIT/Sonic Test 619 16

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT Done
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)
Constraints -
1 Non availability of 20mm & 25mm dia TMT Bar cause Pile & Pile Cap work suffered. PO and Payment done yesterday m
2 Short Supply of RMC from outside approved batching plants with restricted piling works.
ECT
T
Date: 3/2/2023
Balance Remarks

564

603
03 nos. pile cap Steel cutting & Bending
173 & 17 nos. PCC Completed.

Payment done yesterday material delievery awaited.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 57

2 PIT/Sonic Test 619 16

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT -done Total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25mm
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)

Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Batching Plant- CP-30 tested OK - but due to non availability of Machinery i.e. Loader & Transit Mixer unable to produce
Due to Non availability of Back Hoe Loader (JCB) & Hydra/Farana Casting yard development work suffered. Needs to be
3
hire from external agencies.
ECT
T
Date: 3/3/2023
Balance Remarks

562

603
03 nos. pile cap Steel cutting & Bending
173 & 17 nos. PCC Completed.

03-T, 16mm-15.99-T & 25mm-16.07-T) received at site.

sit Mixer unable to produce concrete.


work suffered. Needs to be internal site transfer from AMRP or
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 59

2 PIT/Sonic Test 619 4 20

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT -done Total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25mm-16.07-
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)

Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Batching Plant- CP-30 tested OK - but due to non availability of Machinery i.e. Loader & Transit Mixer unable to produce
Due to Non availability of Back Hoe Loader (JCB) & Hydra/Farana Casting yard development work suffered. Needs to be
3
from external agencies.
OJECT
ORT
Date: 3/4/2023
Balance Remarks

560

599
03 nos. pile cap Steel cutting & Bending & 17
173 nos. PCC Completed.

16mm-15.99-T & 25mm-16.07-T) received at site on dtd. 03.03.22.

sit Mixer unable to produce concrete.


work suffered. Needs to be internal site transfer from AMRP or hire
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 59

2 PIT/Sonic Test 774 11 31

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 Completed
4 Cement Silo Erection 01 erected 04 to be erect
5 TMT Bars - PO for 665-MT -done Total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25mm-16.07-
Bulk Material i.e. Cement, Sand, Aggregate,
6 Done
Plasticizer - Purchase Requisition (PR)

Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
2 Batching Plant- CP-30 tested OK - but due to non availability of Machinery i.e. Loader & Transit Mixer unable to produce
Due to Non availability of Back Hoe Loader (JCB) & Hydra/Farana Casting yard development work suffered. Needs to be
3
from external agencies.
OJECT
ORT
Date: 3/5/2023
Balance Remarks

560

743
03 nos. pile cap Steel cutting & Bending & 17
173 nos. PCC Completed.

16mm-15.99-T & 25mm-16.07-T) received at site on dtd. 03.03.22.

sit Mixer unable to produce concrete.


work suffered. Needs to be internal site transfer from AMRP or hire
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Cumul-
S.N. Description of Work Unit Today
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 2 61

2 PIT & Sonic Test(CHSL) Nos 774 41 72

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Recievedd total 64.08-MT (12mm- 15.99-T, 20mm-16.03-T, 16mm-15.99-T & 25
5 TMT Bars - PO for 665-MT -done Critical dia - 20mm Dia only 1.2-MT available at site
Bulk Material i.e. Cement, Sand, Aggregate,
6 36-MT Coarse Sand received 06-03-2023
Plasticizer - Purchase Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works. (Day time both plants denied to c

Due to Non availability of Back Hoe Loader (JCB) at Casting yard development work suffered. Needs to be internal site tr
2
agencies.
OJECT
ORT
Date: 3/6/2023
Balance Remarks

558

702
03 nos. pile cap Steel cutting & Bending & 17
173 nos. PCC Completed.

elopment from 06-03-23

m-16.03-T, 16mm-15.99-T & 25mm-16.07-T) at site on dtd. 03.03.22.


site

time both plants denied to concrete supply)

. Needs to be internal site transfer from AMRP or hire from external


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

IECCL Executed
S.N. Description of Work Unit Today
SCOPE upto Prev.
A STATIONS + VIADUCT
1 Pile Nos 619 61 5

2 PIT & Sonic Test(CHSL) Nos 774 72 -

3 Pile cap Nos 173 -

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 128-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - Stock in critical - NIL at site IECCL yard.
Bulk Material i.e. Cement, Sand, Aggregate,
6 36-MT Coarse Sand received 06-03-2023
Plasticizer - Purchase Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.

2 Due to Non availability of Back Hoe Loader (JCB) at Casting yard development work suffered. Needs to be internal site tr
PROJECT
EPORT
Date: 3/9/2023
Cumul-
Balance Remarks
ative

66 553 5 Piles completed & 6th Boring in progress

72 702
03 nos. pile cap Steel cutting & Bending & 17
- 173 nos. PCC Completed.

pment from 06-03-23

eeds to be internal site transfer from AMRP or hire from external agencies.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
IECCL Cumul-
S.N. Description of Work Unit Today Balance
SCOPE ative
A STATIONS + VIADUCT
1 Pile Nos 619 3 69 550

2 PIT & Sonic Test(CHSL) Nos 774 - 72 702

3 Pile cap Nos 173 - 173

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 128-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - Stock in critical - NIL at site IECCL yard.
Bulk Material i.e. Cement, Sand, Aggregate,
6 36-MT Coarse Sand received 06-03-2023
Plasticizer - Purchase Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.
ROJECT
PORT
3/10/2023
Remarks

01 Pile collapse near Conv Cen Viaduct &


01 Pile Casing punching done - WMN ITI STNS

03 nos. pile cap Steel cutting & Bending & 17 nos. PCC
Completed.

d development from 06-03-23

CCL yard.

.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT
1 Pile Nos 619 179 20 159 8.8

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.2

3 Pile cap Nos 173 15 - 15 0.8

4 Pier Nos 178 6 - 6 0.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 160-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand,
6 Aggregate, Plasticizer - Purchase 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & a
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.

2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
O RAIL PROJECT
GRESS REPORT
Date: 3/11/2023
Working Days (Sunday Half day working) 18
ACHIEVED

Cumul- Remarks
Today Balance
ative

02 Pile in progress (01 VDCT P8 & 01 WMN ITI STNS)


3 72 547 Shortage of Labours, Rig machine Tools & consumables.

72 702
03 nos. pile cap Steel cutting & Bending & 20 nos. PCC
- 173 Completed & for Convention Centre pile cap & pier labour
reached at site.
- - 178

from 06-03-23

received 11-03-2023 & aggegate yet to received

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJE
DAILY PROGRESS REPORT

Working Days (S
PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT
1 Pile Nos 619 179 21 158 9.3

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.2

3 Pile cap Nos 173 15 - 15 0.9

4 Pier Nos 178 6 - 6 0.4

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total recieved 160-MT
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand,
6 Aggregate, Plasticizer - Purchase 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & a
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.

2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/12/2023
Working Days (Sunday Half day working) 17
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

01 Pile is ready for boring at WMN ITI STN


72 1 73 546 Shortage of Labours, Rig machine Tools & consumables.

72 72 702
03 nos. pile cap Steel cutting & Bending & 20 nos. PCC
- - 173 Completed & for Convention Centre pile cap & pier labour
reached at site.
- - - 178

from 06-03-23

received 11-03-2023 & aggegate yet to received

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 22 157 9.8

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.3

3 Pile cap Nos 173 15 - 15 0.9

4 Pier Nos 178 6 - 6 0.4

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase 01 Bulker Cement - 39.01 MT Received on 13.03.2023
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.

2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
O RAIL PROJECT
GRESS REPORT
Date: 3/13/2023
Working Days (Sunday Half day working) 16
ACHIEVED

Cumul- Remarks
Today Balance
ative

03 Pile boring ready for Concrete pouring (02 VDCT + 01 STN)


delayed due to heavy rain during night.
1 74 545 03nos. Hydraulic Rig machine yet to operational due to their
Tools & Accessries arrangement.

72 702
03 nos. pile cap Steel cutting & Bending & 20 nos. PCC
- 173 Completed & for Convention Centre.Pile Cap Steel Cutting,
Bending started at Casting yard.
- - 178

from 06-03-23

om 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023
23

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJE
DAILY PROGRESS REPORT

Working Days (S
PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 27 152 10.1

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.3

3 Pile cap Nos 173 15 - 15 1.0

4 Pier Nos 178 6 - 6 0.4

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia - reached at site -11-03-23
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase 01 Bulker Cement - 39.01 MT Received on 13.03.2023
Requisition (PR)
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023
Constraints -
1 Short Supply of RMC from outside approved batching plants with restricted piling works.

2 Shortage of Labours, 3nos. Rig machine Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumables
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/14/2023
Working Days (Sunday Half day working) 15
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

01 boring in progress delayed due to shortage Cement in Silo.


Another 03nos. Hydraulic Rig machine yet to operational due to
74 5 79 540 their Tools & Accessries arrangement expected 02 nos start by 16-
03-23

72 72 702
02 nos. pile cap Steel cutting & Bending & 21 nos. PCC
- - 173 Completed & for Convention Centre.Pile Cap Steel Cutting,
Bending started at Casting yard.
- - - 178

from 06-03-23

om 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023
23

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 31 148 10.6

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.3

3 Pile cap Nos 173 15 - 15 1.1

4 Pier Nos 178 6 - 6 0.4

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical Only @ 3.9-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delive
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/15/2023
Working Days (Sunday Half day working) 14
ACHIEVED

Cumul- Remarks
Today Balance
ative

01 Pile boring in progress.

4 83 536 Another 04nos. Hydraulic Rig machine yet to operational due to


their Tools & Accessries arrangement expected 02 nos start by 16-
03-23

72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178

from 06-03-23

om 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT


.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 35 144 11.1

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.3

3 Pile cap Nos 173 15 - 15 1.2

4 Pier Nos 178 6 - 6 0.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.9-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/16/2023
Working Days (Sunday Half day working) 13
ACHIEVED

Cumul- Remarks
Today Balance
ative

01 Pile bore casing punching done bore in progress.

4 87 532 Another 04nos. Hydraulic Rig machine yet to operational due to


their Tools & Accessries arrangement expected 02 nos start by 18-
03-23 , 01nos. By 20-03-23 & 23-03-23.

72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178

from 06-03-23

om 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 39 140 11.7

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.3

3 Pile cap Nos 173 15 - 15 1.3

4 Pier Nos 178 6 - 6 0.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 1-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/17/2023
Working Days (Sunday Half day working) 12
ACHIEVED

Cumul- Remarks
Today Balance
ative

02 Pile in progress (01 bore completed & 01nos. bore 15 depth)


work in progress.
4 91 528 Another 04nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 02 nos start by 18-
03-23 , 01nos. By 20-03-23 & 23-03-23.

72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178

from 06-03-23

om 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 42 137 12.5

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.4

3 Pile cap Nos 173 15 - 15 1.4

4 Pier Nos 178 6 - 6 0.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.5-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/18/2023
Working Days (Sunday Half day working) 11
ACHIEVED

Cumul- Remarks
Today Balance
ative

01 Pile bore completed cage lowering in work in progress.


01- Rig Maching Polymer Mixing Pump Breakdown at WMN ITI
3 94 525 Another 04nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 02 nos start by 20-
03-23 , 01nos. By 22-03-23 & 25-03-23.

72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178

from 06-03-23

om 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 43 136 12.4

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.4

3 Pile cap Nos 173 15 - 15 1.4

4 Pier Nos 178 6 - 6 0.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 429-MT recieved IECCL procured -160-MT + (from 64-MT Shiva Infra+ Sadb
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.5-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/19/2023
Working Days (Sunday Half day working) 11
ACHIEVED

Cumul- Remarks
Today Balance
ative

2 Rig + 1 Crawler Crane was on schedule Meintanance.


01- Rig Maching Polymer Mixing Pump Breakdown at WMN ITI
1 95 524 Another 04nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 02 nos start by 20-
03-23 , 01nos. By 22-03-23 & 25-03-23.

72 702
01 Pile Cap Steel Reinf. fixing work in progress
Another 02 nos. pile cap Steel cutting & Bending done at
- 173 Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178

from 06-03-23

om 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 46 133 13.3

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.4

3 Pile cap Nos 173 15 - 15 1.5

4 Pier Nos 178 6 - 6 0.6

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 484-MT recieved IECCL procurement out of 650-Mt received 215-MT + (fro
5 TMT Bars - PO for 665-MT -done 20mm dia stock in Critical only @ 3.5-MT available at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/20/2023
Working Days (Sunday Half day working) 10
ACHIEVED

Cumul- Remarks
Today Balance
ative

Another 04nos. Hydraulic Rig machine yet to operational due to


3 98 521 their Tools & Accessries arrangement expected 01 nos start by 23-
03-23 , 02nos. By 25-03-23 & 01nos. 27-03-23.

72 702

01 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel Lvl yet decided by GEC another 01 pile cage steel
fixing work in progress
- 173 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178 Shortage of Labour Manpower at P-7 Viaduct

from 06-03-23

0-Mt received 215-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 49 130 14.4

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.4

3 Pile cap Nos 173 15 - 15 1.7

4 Pier Nos 178 6 - 6 0.7

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 484-MT recieved IECCL procurement out of 650-Mt received 215-MT + (fro
5 TMT Bars - PO for 665-MT -done 20mm 2.1 MT & 25mm 1.2 MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/21/2023
Working Days (Sunday Half day working) 9
ACHIEVED

Cumul- Remarks
Today Balance
ative

01 Pile Bore Collapse during the cage lowering at Women ITI STNS
Another 04nos. Hydraulic Rig machine yet to operational due to
3 101 518 their Tools & Accessries arrangement expected 01 nos start by 23-
03-23 , 02nos. By 25-03-23 & 01nos. 27-03-23.
01 Rig Machine Sany-185 display theft from P8-4 Vaiduct.

72 702

01 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel Lvl yet decided by GEC another 01 pile cage steel
fixing work in progress
- 173 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178 Shortage of Labour Manpower at P-7 Viaduct

from 06-03-23

0-Mt received 215-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 52 127 15.9

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.5

3 Pile cap Nos 173 15 - 15 1.9

4 Pier Nos 178 6 - 6 0.8

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 484-MT recieved IECCL procurement out of 650-Mt received 215-MT + (fro
5 TMT Bars - PO for 665-MT -done 20mm 0.5 MT & 25mm 0.2 MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/22/2023
Working Days (Sunday Half day working) 8
ACHIEVED

Cumul- Remarks
Today Balance
ative

01 Pile Bore Collapse during the cage lowering at Women ITI STNS
Another 04nos. Hydraulic Rig machine yet to operational due to
3 104 515 their Tools & Accessries arrangement expected 01 nos start by 23-
03-23 , 02nos. By 25-03-23 & 01nos. 27-03-23.
01 Rig Machine Sany-185 display theft from P8-4 Vaiduct.

72 702

01 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel Lvl yet decided by GEC another 01 pile cage steel
fixing work in progress
- 173 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178 Shortage of Labour Manpower at P-7 Viaduct

from 06-03-23

0-Mt received 215-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables i.e. cover block, sonic pipe, polymer, viscocity & PH value meter etc.
SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 54 125 17.9

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.6

3 Pile cap Nos 173 15 0.5 15 2.1

4 Pier Nos 178 6 - 6 0.9

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL & 20mm -3.9-MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/23/2023
Working Days (Sunday Half day working) 7
ACHIEVED

Cumul- Remarks
Today Balance
ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars


Another 04nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 24-
2 106 513 03-23 , 02nos. By 25-03-23 & 01nos. 27-03-23.

01 Rig Machine Sany-185 display will reached today.

72 702

02 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
0.5 173 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178 Shortage of Labour Manpower at P-7 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 56 123 20.5

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.7

3 Pile cap Nos 173 15 0.5 15 2.4

4 Pier Nos 178 6 - 6 1.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL & 20mm -3.9-MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/24/2023
Working Days (Sunday Half day working) 6
ACHIEVED

Cumul- Remarks
Today Balance
ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars


Another 04nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 24-
2 108 511 03-23 , 02nos. By 25-03-23 & 01nos. 27-03-23.

01 Rig Machine Sany-185 display will reached today.

72 702

02 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
0.5 173 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178 Shortage of Labour Manpower at P-7 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 60 119 23.8

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 0.8

3 Pile cap Nos 173 15 0.5 15 2.9

4 Pier Nos 178 6 - 6 1.2

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL & 20mm -3.9-MT dia stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/25/2023
Working Days (Sunday Half day working) 5
ACHIEVED

Cumul- Remarks
Today Balance
ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars


Another 04nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 25-
4 112 507 03-23 , 02nos. By 27-03-23 & 01nos. 01-04-23.

01 Rig Machine Sany-185 display will reached today.

72 702

02 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
0.5 173 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178 Shortage of Labour Manpower at P-7 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 64 115 28.8

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 1.0

3 Pile cap Nos 173 15 0.5 15 3.6

4 Pier Nos 178 6 - 6 1.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/27/2023
Working Days (Sunday Half day working) 4
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars

112 4 116 503 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 28-
03-23 , 01nos. By 31-03-23 & 01nos. 01-04-23.

72 72 702

02 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
1 0.5 173 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 178 Shortage of Labour Manpower at P-7 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 619 179 68 111 37.0

2 PIT & Sonic Test(CHSL) Nos 774 60 56 4 1.3

3 Pile cap Nos 173 15 1.5 14 4.5

4 Pier Nos 178 6 - 6 2.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/28/2023
Working Days (Sunday Half day working) 3
ACHIEVED

Cumul- Remarks
Today Balance
ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars

4 120 499 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 28-
03-23 , 01nos. By 31-03-23 & 01nos. 01-04-23.

72 702

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
1.5 172 Another 01 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 178 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 179 70 109 54.5

2 PIT & Sonic Test(CHSL) Nos 835 60 56 4 2.0

3 Pile cap Nos 178 15 1.5 14 6.8

4 Pier Nos 183 6 - 6 3.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
TRO RAIL PROJECT
ROGRESS REPORT
Date: 3/29/2023
Working Days (Sunday Half day working) 2
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars

120 3 123 545 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 30-
03-23 , 01nos. By 31-03-23 & 01nos. 01-04-23.

72 72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 01 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 179 72 107 107.0

2 PIT & Sonic Test(CHSL) Nos 835 60 56 4 4.0

3 Pile cap Nos 178 15 1.5 14 13.5

4 Pier Nos 183 6 - 6 6.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/30/2023
Working Days (Sunday Half day working) 1
ACHIEVED

Cumul- Remarks
Today Balance
ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars


Shortage of Cement at batching plant
2 125 543 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 01-
03-23 , 01nos. By 02-03-23 & 01nos. 03-04-23.

72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
1.5 177 Another 01 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 179 75 104

2 PIT & Sonic Test(CHSL) Nos 835 60 56 4

3 Pile cap Nos 178 15 1.5 14

4 Pier Nos 183 6 - 6

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 3/31/2023
Working Days (Sunday Half day working) 0
ACHIEVED

Cumul- Remarks
Today Balance
ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars


Shortage of Cement at batching plant
3 128 540 Another 03nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 01-
03-23 , 01nos. By 02-03-23 & 01nos. 03-04-23.

72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
1.5 177 Another 01 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJECT
DAILY PROGRESS REPORT

Working Days (Sunday H


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 3 342 11.8

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.1

3 Pile cap Nos 178 46 - 46 1.6

4 Pier Nos 183 30 - 30 1.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
Total TMT 488-MT recieved IECCL procurement out of 650-Mt received 219-MT + (fro
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase Continue delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, 4nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consumab
O RAIL PROJECT
GRESS REPORT
Date: 4/1/2023
Working Days (Sunday Half day working) 29
ACHIEVED

Cumul- Remarks
Today Balance
ative

Shortage of 20mm, 25mm & 32mm 500D TMT Bars


Shortage of Cement at batching plant
3 131 537 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 03-
03-23 & 01nos. 04-04-23.

72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
1.5 177 Another 01 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

0-Mt received 219-MT + (from 64-MT Shiva Infra+ Sadbhav-74-MT) + RSK- 113-MT + AVC-17.77 MT
n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further

3 & now continue delivery started at site.

nt construction work in progress.

Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Mar- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 6 339 12.1

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.1

3 Pile cap Nos 178 46 - 46 1.6

4 Pier Nos 183 30 - 30 1.1

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 297-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/2/2023
Working Days (Sunday Half day working) 28
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 25mm & 32mm 500D TMT Bars


Shortage of Cement at batching plant
131 3 134 534 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 03-
03-23 & 01nos. 04-04-23.

72 72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 01 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 6 339 12.6

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.2

3 Pile cap Nos 178 46 - 46 1.7

4 Pier Nos 183 30 - 30 1.1

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 297-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 25mm NIL , 20mm -NIL-MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/3/2023
Working Days (Sunday Half day working) 27
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 25mm & 32mm 500D TMT Bars


Shortage of Cement at batching plant
131 3 134 534 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 03-
03-23 & 01nos. 04-04-23.

72 72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 01 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


n Critical at site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 22 323 12.4

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.3

3 Pile cap Nos 178 46 - 46 1.8

4 Pier Nos 183 30 - 30 1.2

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-3 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/4/2023
Working Days (Sunday Half day working) 26
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

145 9 154 514 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 03-
03-23 & 01nos. 04-04-23.

72 72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 02 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 27 318 12.7

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.4

3 Pile cap Nos 178 46 - 46 1.8

4 Pier Nos 183 30 - 30 1.2

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 01 erected 04 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-3 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/5/2023
Working Days (Sunday Half day working) 25
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

154 5 159 509 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
03-23 & 01nos by 10-04-23.

72 72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 32 313 13.0

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.5

3 Pile cap Nos 178 46 - 46 1.9

4 Pier Nos 183 30 - 30 1.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 02 erected 03 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-2 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/6/2023
Working Days (Sunday Half day working) 24
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

159 5 164 504 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.

72 72 763

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 35 310 13.5

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.6

3 Pile cap Nos 178 46 - 46 2.0

4 Pier Nos 183 30 - 30 1.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 02 erected 03 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-2 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/7/2023
Working Days (Sunday Half day working) 23
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8 Piling work 100% complete, RIG Machine shifted to


164 3 167 501 Viaduct P5.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 39 306 13.9

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.7

3 Pile cap Nos 178 46 - 46 2.1

4 Pier Nos 183 30 - 30 1.4

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 02 erected 03 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/8/2023
Working Days (Sunday Half day working) 22
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8 Piling work 100% complete, RIG Machine shifted to


167 4 171 497 Viaduct P5.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 42 303 14.4

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 2.9

3 Pile cap Nos 178 46 - 46 2.2

4 Pier Nos 183 30 - 30 1.4

Others -
1 Erection of Batching Plant -M-1 (60cum) 65% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 04 erected 01 to be erect
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/9/2023
Working Days (Sunday Half day working) 21
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8 Piling work 100% complete, Viaduct P5 Piling starts.


171 3 174 494 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 47 298 14.9

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 3.0

3 Pile cap Nos 178 46 - 46 2.3

4 Pier Nos 183 30 - 30 1.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/10/2023
Working Days (Sunday Half day working) 20
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8 Piling work 100% complete, Viaduct P5 Piling starts.


174 5 179 489 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 52 293 15.4

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 3.2

3 Pile cap Nos 178 46 - 46 2.4

4 Pier Nos 183 30 - 30 1.6

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/11/2023
Working Days (Sunday Half day working) 19
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8 Piling work 100% complete, Viaduct P5 Piling starts.


179 5 184 484 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 57 288 16.0

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 3.3

3 Pile cap Nos 178 46 - 46 2.6

4 Pier Nos 183 30 - 30 1.7

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours, for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consum
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/12/2023
Working Days (Sunday Half day working) 18
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8 Piling work 100% complete, Viaduct P5 Piling starts.


184 5 189 479 Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 07-
04-23 & 01nos by 10-04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 03 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 01 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

ank Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 65 280 16.5

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 3.5

3 Pile cap Nos 178 46 - 46 2.7

4 Pier Nos 183 30 - 30 1.8

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/13/2023
Working Days (Sunday Half day working) 17
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P5 Piling


189 8 197 471 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 69 276 17.3

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 3.8

3 Pile cap Nos 178 46 - 46 2.9

4 Pier Nos 183 30 - 30 1.9

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 332-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/14/2023
Working Days (Sunday Half day working) 16
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P5 Piling


191 4 195 473 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 74 271 18.1

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 4.0

3 Pile cap Nos 178 46 - 46 3.1

4 Pier Nos 183 30 - 30 2.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/15/2023
Working Days (Sunday Half day working) 15
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P5 Piling


195 5 200 468 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 78 267 19.1

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 4.3

3 Pile cap Nos 178 46 - 46 3.3

4 Pier Nos 183 30 - 30 2.1

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/16/2023
Working Days (Sunday Half day working) 14
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P5 Piling


200 4 204 464 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 83 262 20.2

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 4.6

3 Pile cap Nos 178 46 - 46 3.5

4 Pier Nos 183 30 - 30 2.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/17/2023
Working Days (Sunday Half day working) 13
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P5 Piling


204 5 209 459 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 88 257 21.4

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 5.0

3 Pile cap Nos 178 46 - 46 3.8

4 Pier Nos 183 30 - 30 2.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/18/2023
Working Days (Sunday Half day working) 12
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


209 5 214 454 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 93 252 22.9

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 5.5

3 Pile cap Nos 178 46 - 46 4.2

4 Pier Nos 183 30 - 30 2.7

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 364-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/19/2023
Working Days (Sunday Half day working) 11
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


214 5 219 449 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 97 248 24.8

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 6.0

3 Pile cap Nos 178 46 - 46 4.6

4 Pier Nos 183 30 - 30 3.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 405-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/20/2023
Working Days (Sunday Half day working) 10
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


219 4 223 445 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 98 247 27.4

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 6.7

3 Pile cap Nos 178 46 - 46 5.1

4 Pier Nos 183 30 - 30 3.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 405-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/21/2023
Working Days (Sunday Half day working) 9
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


220 1 221 447 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 99 246 30.8

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 7.5

3 Pile cap Nos 178 46 - 46 5.8

4 Pier Nos 183 30 - 30 3.8

Others -
1 Erection of Batching Plant -M-1 (60cum) 75% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 405-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/22/2023
Working Days (Sunday Half day working) 8
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


221 1 222 446 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 101 244 34.9

2 PIT & Sonic Test(CHSL) Nos 835 60 - 60 8.6

3 Pile cap Nos 178 46 - 46 6.6

4 Pier Nos 183 30 - 30 4.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 488-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-NIL & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/23/2023
Working Days (Sunday Half day working) 7
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


222 2 224 444 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement expected 01 nos start by 20-
04-23.

72 72 763

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 104 241 40.2

2 PIT & Sonic Test(CHSL) Nos 835 60 8 52 8.7

3 Pile cap Nos 178 46 - 46 7.7

4 Pier Nos 183 30 - 30 5.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-9.82 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/24/2023
Working Days (Sunday Half day working) 6
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


224 3 227 441 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

72 8 80 755

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 106 239 47.8

2 PIT & Sonic Test(CHSL) Nos 835 60 8 52 10.4

3 Pile cap Nos 178 46 - 46 9.2

4 Pier Nos 183 30 - 30 6.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-9.82 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/25/2023
Working Days (Sunday Half day working) 5
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


227 2 229 439 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

72 8 80 755

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


site.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 109 236 59.0

2 PIT & Sonic Test(CHSL) Nos 835 60 8 52 13.0

3 Pile cap Nos 178 46 - 46 11.5

4 Pier Nos 183 30 - 30 7.5

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-8 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/26/2023
Working Days (Sunday Half day working) 4
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 12 mm & 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


229 3 232 436 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

72 8 80 755

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
2 1.5 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 113 232 77.3

2 PIT & Sonic Test(CHSL) Nos 835 60 8 52 17.3

3 Pile cap Nos 178 46 - 46 15.3

4 Pier Nos 183 30 - 30 10.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/27/2023
Working Days (Sunday Half day working) 3
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


232 4 236 432 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

72 8 80 755

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical


steel pier vertical steel bar threading work in progress in
progress
- - - 178 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 116 229 114.5

2 PIT & Sonic Test(CHSL) Nos 835 60 8 52 26.0

3 Pile cap Nos 178 46 1 45 22.5

4 Pier Nos 183 30 - 30 15.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/28/2023
Working Days (Sunday Half day working) 2
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


236 3 239 429 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

72 8 80 755

01st Pilecap Casted, 04 Pile Cap Steel Reinf. fixing


completed & Pier Vertical steel pier vertical steel bar
threading work in progress in progress
- 1 1.0 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 119 226 226.0

2 PIT & Sonic Test(CHSL) Nos 835 60 8 52 52.0

3 Pile cap Nos 178 46 1 45 45.0

4 Pier Nos 183 30 - 30 30.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/29/2023
Working Days (Sunday Half day working) 1
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


239 3 242 426 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

72 8 80 755

01st Pilecap Casted, 04 Pile Cap Steel Reinf. fixing


completed & Pier Vertical steel pier vertical steel bar
threading work in progress in progress
- 1 1.0 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

Working Days (Su


PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the Apr- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 345 123 222 222.0

2 PIT & Sonic Test(CHSL) Nos 835 60 8 52 52.0

3 Pile cap Nos 178 46 1 45 45.0

4 Pier Nos 183 30 - 30 30.0

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 4/30/2023
Working Days (Sunday Half day working) 0
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


242 4 246 422 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

72 8 80 755

01st Pilecap Casted, 04 Pile Cap Steel Reinf. fixing


completed & Pier Vertical steel pier vertical steel bar
threading work in progress in progress
- 1 1.0 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJEC
DAILY PROGRESS REPORT

PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the May- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 226 226 8.7

2 PIT & Sonic Test(CHSL) Nos 835 60 60 2.3

3 Pile cap Nos 178 51 51 2.0

4 Pier Nos 183 8 8 0.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase delivery started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
TRO RAIL PROJECT
ROGRESS REPORT
Date: 5/1/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 32mm 500D TMT Bars

Viaduct P8, WITI Piling work 100% complete, Viaduct P6 Piling


246 246 422 starts.
Another 02nos. Hydraulic Rig machine yet to operational due to
their Tools & Accessries arrangement

80 80 755

01st Pilecap Casted, 04 Pile Cap Steel Reinf. fixing


completed & Pier Vertical steel pier vertical steel bar
threading work in progress in progress
1 1.0 177 Another 04 nos. pile cap Steel cutting & Bending done at
Casting yard & 21 nos. Pile Cap PCC Completed & 02 nos
Pile cap Group Pile Head Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
IECCL Target for Achieved Today
S.N. Description of Work Unit
SCOPE the May- for the Balance Asking
23 month Rate
A STATIONS + VIADUCT

1 Pile Nos 668 226 226 9.0

2 PIT & Sonic Test(CHSL) Nos 835 60 60 2.4

3 Pile cap Nos 178 51 51 2.0

4 Pier Nos 183 8 8 0.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/2/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Shortage of 32mm 500D TMT Bars


Viaduct P9 Piling hold due to Land issue
Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling hold due to shortage of labour & sonic pipe.
Rig-2 Viaduct P6 Piling hold due to shortage of labour & sonic pipe.
246 246 422 Rig-3 Bhimrad Station - Piling hold due to shortage sonic pipe.

Rig-4 &5 -Viaduct P5 Piling 02 nos Pile collapus yesterday


Rig-6 VIP Station - work stop due to shortage of steel & labours

80 80 755

01st Pilecap Casted, 06 Pile Cap Steel Reinf. fixing completed


& Pier Vertical steel pier vertical steel bar threading work in
progress in progress
1 1.0 177 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 2 224 9.3

2 PIT & Sonic Test(CHSL) Nos 835 60 60 2.5

3 Pile cap Nos 178 51 1 50 2.1

4 Pier Nos 183 8 8 0.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/3/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

O&M - Non-availability Regular JCB for Batching plant -01 Pile


Concrete yet to start at P-5 Viaduct.
Shortage of 32mm 500D TMT Bars
Viaduct P9 Piling hold due to Land issue
Viaduct P8, WITI Piling work 100% complete,
246 2 248 420 Rig-1 Viaduct P7 Piling hold due to shortage of labour & sonic pipe.
Rig-2 Viaduct P6 Piling hold due to shortage of labour & sonic pipe.
Rig-3 Bhimrad Station - Piling hold due to shortage sonic pipe.
Rig-4 &5 -Viaduct P5 Piling 02 nos Pile collapus yesterday
Rig-6 VIP Station - work stop due to shortage of steel & labours

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
1 1 2.0 176 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress

- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 7 219 9.5

2 PIT & Sonic Test(CHSL) Nos 835 60 60 2.6

3 Pile cap Nos 178 51 1 50 2.2

4 Pier Nos 183 8 8 0.3

Others -
1 Erection of Batching Plant -M-1 (60cum) 80% Completed
2 Erection Batching Plant -CP-30 100% Completed
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
IECCL procurement out of 650-Mt received 564-MT + (from 64.59-MT Shiva Infra+ S
5 TMT Bars - PO for 665-MT -done 12mm-26 MT & 32mm dia 500D NIL stock in Critical at site.
Bulk Material i.e. Cement, Sand, 36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Aggregate, Plasticizer - Purchase started at site.
Requisition (PR) 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now continue delivery
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours for 2nos. Rig machine & Tools i.e.Temp. Casing, Vertical Pump, Water Tank Connection & consuma
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/4/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

O&M - Non-availability Regular JCB for Batching plant -01 Pile


Concrete yet to start at P-5 Viaduct.
Shortage of 32mm 500D TMT Bars
Viaduct P9 Piling hold due to Land issue
Viaduct P8, WITI Piling work 100% complete,
248 5 253 415 Rig-1 Viaduct P7 Piling hold due to shortage of labour & sonic pipe.
Rig-2 Viaduct P6 Piling hold due to shortage of labour & sonic pipe.
Rig-3 Bhimrad Station - Piling hold due to shortage sonic pipe.
Rig-4 &5 -Viaduct P5 Piling 02 nos Pile collapus yesterday
Rig-6 VIP Station - work stop due to shortage of steel & labours

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
2 2.0 176 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress

- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

om 64.59-MT Shiva Infra+ Sadbhav-74-MT)


e.
received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery

3 & now continue delivery started at site.

nt construction work in progress.

nk Connection & consumables etc.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 12 214 9.7

2 PIT & Sonic Test(CHSL) Nos 835 60 60 2.7

3 Pile cap Nos 178 51 1 50 2.3

4 Pier Nos 183 8 8 0.4

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & Sonic Pipe
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/5/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling hold due to shortage of labour & sonic pipe.
Rig-2 Viaduct P6 Piling hold due to shortage of labour & sonic pipe.
253 5 258 410 Rig-3 Bhimrad Station - Piling hold due to shortage sonic pipe.
Rig-4 &5 -Viaduct P5 Piling 03nos. Pile Group required traffic
Diversion.
Rig-6 VIP Station - work stop due to shortage of steel & labours

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
2 2.0 176 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress

- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 14 212 10.1

2 PIT & Sonic Test(CHSL) Nos 835 60 60 2.9

3 Pile cap Nos 178 51 2 49 2.3

4 Pier Nos 183 8 8 0.4

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & Sonic Pipe
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/6/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -01 Pile boring work in progress .
Rig-2 Viaduct P6 Piling hold due to shortage of labour & sonic pipe.
258 2 260 408 Rig-3 Bhimrad Station - work in progress.
Rig-4 -Viaduct P5 Piling- work in progress (03nos. Pile Group required
traffic Diversion).
Rig-5- VIP Station - 01 Rig machine shifted from P-5 to VIP STNS.

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
2 1 3.0 175 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress

- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 19 207 10.9

2 PIT & Sonic Test(CHSL) Nos 835 60 60 3.2

3 Pile cap Nos 178 51 2 49 2.6

4 Pier Nos 183 8 8 0.4

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & Sonic Pipe
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/8/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -01 Pile boring work in progress .
Rig-2 Viaduct P6 Piling hold due to shortage of labour & sonic pipe.
263 2 265 403 Rig-3 Bhimrad Station - work in progress.
Rig-4 -Viaduct P5 Piling- work in progress (03nos. Pile Group required
traffic Diversion).
Rig-5- VIP Station - After 7 Mtr 02 nos. pile found utility boring
stopped.

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
3 3.0 175 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress

- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 21 205 11.4

2 PIT & Sonic Test(CHSL) Nos 835 60 60 3.3

3 Pile cap Nos 178 51 3 48 2.7

4 Pier Nos 183 8 8 0.4

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/9/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 Piling hold due to shortage of labour & sonic pipe.
265 2 267 401 Rig-3 Bhimrad Station - work in progress.
Rig-4 -Viaduct P5 Piling- work in progress (03nos. Pile Group required
traffic Diversion).
Rig-5- VIP Station - After 7 Mtr 02 nos. pile found utility boring
stopped. -Shortage of 8mm dia TMT

80 80 755

07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
3 1 4.0 174 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 22 nos. Pile Cap PCC Completed & 02 nos Pile cap Group
Pile Head Chipping in progress

- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


SURAT METRO RAIL PROJ
DAILY PROGRESS REPOR

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 24 202 11.9

2 PIT & Sonic Test(CHSL) Nos 835 60 60 3.5

3 Pile cap Nos 178 51 3 48 2.8

4 Pier Nos 183 8 8 0.5

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1 Shortage of Labours Manpower & 8mm dia TMT
ETRO RAIL PROJECT
PROGRESS REPORT
Date: 5/10/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 Piling hold due to shortage of labour & Polymer.
Rig-3 & 4 Bhimrad Station - work in progress.
267 3 270 398 Rig-5 -Viaduct P5 Piling- work in progress (03nos. Pile Group required
traffic Diversion).
Rig-6- VIP Station - After 7 Mtr 02 nos. pile found utility boring
stopped matter escalate to Designer GEC/GMRC. Shortage of 8mm dia
TMT

80 80 755

07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel
pier vertical steel bar threading work in progress in progress
4 4.0 174 Another 04 nos. pile cap Steel cutting & Bending done at Casting
yard & 18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group
Pile Head Chipping in progress

- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 27 199 12.4

2 PIT & Sonic Test(CHSL) Nos 835 60 60 3.8

3 Pile cap Nos 178 51 4 47 2.9

4 Pier Nos 183 8 8 0.5

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/11/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 Piling hold due to shortage of labour & Polymer.
Rig-3 & 4 Bhimrad Station - work in progress.
270 3 273 395 Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - After 7 Mtr 02 nos. pile found utility boring stopped
matter escalate to Designer GEC/GMRC. Shortage of 8mm dia TMT

80 80 755

07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
4 1 5.0 173 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 35 191 13.6

2 PIT & Sonic Test(CHSL) Nos 835 60 60 4.3

3 Pile cap Nos 178 51 5 46 3.3

4 Pier Nos 183 8 8 0.6

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/13/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 Piling hold due to shortage of labour & Polymer.
Rig-3 & 4 Bhimrad Station - work in progress.
277 4 281 387 Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - After 7 Mtr 02 nos. pile found utility boring stopped
matter escalate to Designer GEC/GMRC. Shortage of 8mm dia TMT

80 80 755

07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
5 1 6.0 172 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 36 190 14.6

2 PIT & Sonic Test(CHSL) Nos 835 60 60 4.6

3 Pile cap Nos 178 51 5 46 3.5

4 Pier Nos 183 8 8 0.6

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/14/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 Piling hold due to shortage of labour & Polymer.
Rig-3 & 4 Bhimrad Station - work in progress.
281 1 282 386 Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - After 7 Mtr 02 nos. pile found utility boring stopped
matter escalate to Designer GEC/GMRC. Shortage of 8mm dia TMT

80 80 755

07 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
6 6.0 172 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 44 182 16.5

2 PIT & Sonic Test(CHSL) Nos 835 60 60 5.5

3 Pile cap Nos 178 51 6 45 4.1

4 Pier Nos 183 8 8 0.7

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/16/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
287 3 290 378 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
6 1 7.0 171 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 48 178 17.8

2 PIT & Sonic Test(CHSL) Nos 835 60 60 6.0

3 Pile cap Nos 178 51 6 45 4.5

4 Pier Nos 183 8 8 0.8

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/17/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
290 4 294 374 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
7 7.0 171 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 53 173 19.2

2 PIT & Sonic Test(CHSL) Nos 835 60 60 6.7

3 Pile cap Nos 178 51 7 44 4.9

4 Pier Nos 183 8 8 0.9

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/18/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
294 4 298 370 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
7 1 8.0 170 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 58 168 21.0

2 PIT & Sonic Test(CHSL) Nos 835 60 60 7.5

3 Pile cap Nos 178 51 8 43 5.4

4 Pier Nos 183 8 8 1.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/19/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
298 5 303 365 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 755

06 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
8 1 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 62 164 23.4

2 PIT & Sonic Test(CHSL) Nos 835 60 60 8.6

3 Pile cap Nos 178 51 8 43 6.1

4 Pier Nos 183 8 8 1.1

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/20/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
303 4 307 361 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 755

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 & P6 Viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 668 226 66 160 26.7

2 PIT & Sonic Test(CHSL) Nos 835 60 60 10.0

3 Pile cap Nos 178 51 8 43 7.2

4 Pier Nos 183 8 8 1.3

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/21/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
307 4 311 357 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 755

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 70 156 31.2

2 PIT & Sonic Test(CHSL) Nos 838 60 60 12.0

3 Pile cap Nos 178 51 8 43 8.6

4 Pier Nos 183 8 8 1.6

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P7- CP-19 - below 6.0 M
1. P5-27 -below 6 Mtr utility encountered which sewerage line. 2. P7-26 -below 2.5 Mtr ut
2. P5-26 - below 6 Mtr utility encountered which sewerage line. 3. P7-PP20 - RHS - Storm
3. P5-28 - below 6 Mtr utility encountered which sewerage line. 4. Bhimrad -Grid -C' -rising
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables. 5. P-9 Viaduct Land issue
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/22/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
311 4 315 356 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 758

05 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 9.0 169 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 85 141 70.5

2 PIT & Sonic Test(CHSL) Nos 838 60 60 30.0

3 Pile cap Nos 178 51 10 41 20.5

4 Pier Nos 183 8 8 4.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/25/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
320 5 325 346 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 758

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
9 1 10 168 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 85 141 70.5

2 PIT & Sonic Test(CHSL) Nos 838 60 60 30.0

3 Pile cap Nos 178 51 10 41 20.5

4 Pier Nos 183 8 8 4.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/25/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
325 5 330 341 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 758

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
10 1 11 167 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 90 136 136.0

2 PIT & Sonic Test(CHSL) Nos 838 60 60 60.0

3 Pile cap Nos 178 51 10 41 41.0

4 Pier Nos 183 8 8 8.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/26/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
330 5 335 336 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 758

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
11 11 167 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PRO
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 93 133 33.3

2 PIT & Sonic Test(CHSL) Nos 838 60 60 15.0

3 Pile cap Nos 178 51 11 40 10.0

4 Pier Nos 183 8 8 2.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/27/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
335 3 338 333 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 758

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
11 1 12 166 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 94 132 44.0

2 PIT & Sonic Test(CHSL) Nos 838 60 60 20.0

3 Pile cap Nos 178 51 11 40 13.3

4 Pier Nos 183 8 8 2.7

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/28/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
338 1 339 332 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 758

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
12 12 166 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 97 129 64.5

2 PIT & Sonic Test(CHSL) Nos 838 60 60 30.0

3 Pile cap Nos 178 51 11 40 20.0

4 Pier Nos 183 8 8 4.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/29/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
339 3 342 329 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 80 758

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
12 12 166 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 101 125 125.0

2 PIT & Sonic Test(CHSL) Nos 838 60 15 45 45.0

3 Pile cap Nos 178 51 12 39 39.0

4 Pier Nos 183 8 8 8.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/30/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
342 4 346 325 Rig-3 & 4 Bhimrad Station - work in progress.
Rig-5 -Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-6- VIP Station - work in progress.

80 15 95 743

04 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
12 1 13 165 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Shortage of Labour Manpower at P-7 viaduct

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the May- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 226 103 123 123.0

2 PIT & Sonic Test(CHSL) Nos 838 60 25 35 35.0

3 Pile cap Nos 178 51 13 38 38.0

4 Pier Nos 183 8 8 8.0

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/31/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
346 2 348 323 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- VIP Station - work in progress.

95 10 105 733

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
13 1 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 4 171 6.3

2 PIT & Sonic Test(CHSL) Nos 838 60 20 40 1.5

3 Pile cap Nos 178 48 48 1.8

4 Pier Nos 183 16 16 0.6

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/1/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
348 4 352 319 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

105 20 125 713

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 6 169 6.5

2 PIT & Sonic Test(CHSL) Nos 838 60 20 40 1.5

3 Pile cap Nos 178 48 48 1.8

4 Pier Nos 183 16 16 0.6

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/2/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
352 2 354 317 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

125 125 713

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 10 165 6.6

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 1.2

3 Pile cap Nos 178 48 48 1.9

4 Pier Nos 183 16 16 0.6

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/3/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
354 4 358 313 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

125 10 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 14 161 6.7

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 1.3

3 Pile cap Nos 178 48 48 2.0

4 Pier Nos 183 16 16 0.7

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/4/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
358 4 362 309 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock in progress for client check-up

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 20 155 2.9

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 0.6

3 Pile cap Nos 178 48 48 0.9

4 Pier Nos 183 16 16 0.3

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 5/6/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
362 6 368 303 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress in progress
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 25 150 6.8

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 1.4

3 Pile cap Nos 178 48 48 2.2

4 Pier Nos 183 16 16 0.7

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/6/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
368 5 373 298 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 29 146 7.0

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 1.4

3 Pile cap Nos 178 48 48 2.3

4 Pier Nos 183 16 16 0.8

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/7/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
373 4 377 294 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 14 164 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 32 143 7.2

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 1.5

3 Pile cap Nos 178 48 1 47 2.4

4 Pier Nos 183 16 16 0.8

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -

1. P5-27 -below 6 Mtr utility encountered which sewerage line.


1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/8/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
377 3 380 291 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 1 15 163 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -

1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter


2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 37 138 7.3

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 1.6

3 Pile cap Nos 178 48 1 47 2.5

4 Pier Nos 183 16 16 0.8


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/9/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
380 5 385 286 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
14 1 15 163 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 43 132 7.3

2 PIT & Sonic Test(CHSL) Nos 838 60 30 30 1.7

3 Pile cap Nos 178 48 1 47 2.6

4 Pier Nos 183 16 16 0.9


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/10/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
385 5 390 281 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
16 1 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 44 131 7.7

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 1.8

3 Pile cap Nos 178 48 1 47 2.8

4 Pier Nos 183 16 16 0.9


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/11/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
390 1 391 280 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
16 1 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 47 128 8.0

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 1.9

3 Pile cap Nos 178 48 1 47 2.9

4 Pier Nos 183 16 16 1.0


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/12/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
391 3 394 277 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 - 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 49 126 8.4

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 2.0

3 Pile cap Nos 178 48 1 47 3.1

4 Pier Nos 183 16 16 1.1


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 95% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/13/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
394 2 396 275 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 - 17 161 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Mock check-up done with client.
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 55 120 8.6

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 2.1

3 Pile cap Nos 178 48 4 44 3.1

4 Pier Nos 183 16 16 1.1


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 96% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/14/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
396 6 402 269 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 60 115 8.8

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 2.3

3 Pile cap Nos 178 48 4 44 3.4

4 Pier Nos 183 16 16 1.2


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/15/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
402 5 407 264 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing completed & Pier Vertical steel pier
vertical steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 65 110 9.2

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 2.5

3 Pile cap Nos 178 48 4 44 3.7

4 Pier Nos 183 16 16 1.3


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/16/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
407 5 412 259 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 71 104 9.5

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 2.7

3 Pile cap Nos 178 48 4 44 4.0

4 Pier Nos 183 16 16 1.5


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations Excavation & PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/17/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
412 6 418 253 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
17 1 18 160 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the Today
S.N. Description of Work Unit
SCOPE the June- month Balance Asking
23 Rate

A STATIONS + VIADUCT

1 Pile Nos 671 175 75 100 10.0

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30 3.0

3 Pile cap Nos 178 48 5 43 4.3

4 Pier Nos 183 16 16 1.6


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 97% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 & 10
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & now c
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in pro
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
1. P7- CP-19 - below 6.0 M
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
2. P7-26 -below 2.5 Mtr ut
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
3. P7-PP20 - RHS - Storm
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
4. Bhimrad -Grid -C' -rising
5. P5 28A to P530 - Traffic Route Diversion required
5. P-9 Viaduct Land issue
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
METRO RAIL PROJECT
Y PROGRESS REPORT
Date: 6/18/2023
ACHIEVED

Upto Cumul- Remarks


Today Balance
Prev. ative

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
418 4 422 249 Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

135 135 703

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
18 1 19 159 Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
- - 183 Pier shutter Shifted to Site for Pier casting @ CCS
- - 104
- - 938
- - 1,988

from 06-03-23

received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
ed on 13.03.2023 & now continue delivery started at site.

nt construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23

A STATIONS + VIADUCT

1 Pile Nos 671 175 79 96

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30

3 Pile cap Nos 178 48 6 42

4 Pier Nos 183 16 16


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED

Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate

10.7 422 4 426 245

3.3 135 135 703

4.7 19 1 20 158

1.8 - - 183
- - 104
- - 938
- - 1,988

velopment from 06-03-23

Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.

ur Hutment construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
6/19/2023

Remarks

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1 Viaduct P7 Piling -Utilities encountered at location
Rig-2 Viaduct P6 -work in progress.
Rig-3&4 Bhimrad Station - work in progress.
Viaduct P5 Piling- P5-26, P5-27, P5-28 & P5-23 Utilities hindrance
encountered . work in progress.
(03nos. Pile Group required traffic Diversion).
Rig-5- P-6 & VIP Station - work in progress.

02 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct

aggregate 01 each truck received on 13.03.2023 & Further Continue delivery


ery started at site.
ne encounter
ine 200mm dia

mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23

A STATIONS + VIADUCT

1 Pile Nos 671 175 83 92

2 PIT & Sonic Test (CHSL) Nos 838 60 30 30

3 Pile cap Nos 178 48 6 42

4 Pier Nos 183 16 16


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED

Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate

11.5 426 4 430 241

3.8 135 135 703

5.3 20 - 20 158

2.0 - - 183
- - 104
- - 938
- - 1,988

velopment from 06-03-23

Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.

ur Hutment construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
6/20/2023

Remarks

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1&2 Viaduct P7 Piling -Utilities encountered at location
Rig-3 Viaduct P6 -work in progress.
Rig-4 Bhimrad Station - work in progress.
Bhimrad Piling- Grid -C Utilities hindrance encountered WIP
VIP Piling- Grid -C & C' Utilities hindrance encountered WIP
VIP Piling- Grid -E' Anchor Pile, Design to be change WIP
P5 (01nos. Pile Group required traffic Diversion).
Rig-5&6- P-6 & VIP Station - work in progress.

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct

aggregate 01 each truck received on 13.03.2023 & Further Continue delivery


ery started at site.
ne encounter
ine 200mm dia

mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23

A STATIONS + VIADUCT

1 Pile Nos 671 175 87 88

2 PIT & Sonic Test (CHSL) Nos 838 60 40 20

3 Pile cap Nos 178 48 6 42

4 Pier Nos 183 16 16


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED

Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate

12.6 430 4 434 237

2.9 135 10 145 693

6.0 20 - 20 158

2.3 - - 183
- - 104
- - 938
- - 1,988

velopment from 06-03-23

Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.

ur Hutment construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
6/21/2023

Remarks

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1&2 Viaduct P7 Piling -Utilities encountered at location
Rig-3 Viaduct P6 -work in progress.
Rig-4 Bhimrad Station - work in progress.
Bhimrad Piling- Grid -C Utilities hindrance encountered WIP
VIP Piling- Grid -C & C' Utilities hindrance encountered WIP
VIP Piling- Grid -E' Anchor Pile, Design to be change WIP
P5 (01nos. Pile Group required traffic Diversion).
Rig-5&6- P-6 & VIP Station - work in progress.

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct

aggregate 01 each truck received on 13.03.2023 & Further Continue delivery


ery started at site.
ne encounter
ine 200mm dia

mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23

A STATIONS + VIADUCT

1 Pile Nos 671 175 91 84

2 PIT & Sonic Test (CHSL) Nos 838 60 40 20

3 Pile cap Nos 178 48 6 42

4 Pier Nos 183 16 16


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED

Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate

14.0 434 4 438 233

3.3 145 - 145 693

7.0 20 - 20 158

2.7 - - 183
- - 104
- - 938
- - 1,988

velopment from 06-03-23

Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.

ur Hutment construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. P7-PP20 - RHS - Storm Water Line
4. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
5. P-9 Viaduct Land issue
6/22/2023

Remarks

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1&2 Viaduct P7 Piling -Utilities encountered at location
Rig-3 Viaduct P6 -work in progress.
Rig-4 Bhimrad Station - work in progress.
Bhimrad Piling- Grid -C Utilities hindrance encountered WIP
VIP Piling- Grid -C & C' Utilities hindrance encountered WIP
VIP Piling- Grid -E' Anchor Pile, Design to be change WIP
P5 (01nos. Pile Group required traffic Diversion).
Rig-5&6- P-6 & VIP Station - work in progress.

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct

aggregate 01 each truck received on 13.03.2023 & Further Continue delivery


ery started at site.
ne encounter
ine 200mm dia

mm diameter encountered
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23

A STATIONS + VIADUCT

1 Pile Nos 671 175 94 81

2 PIT & Sonic Test (CHSL) Nos 838 60 40 20

3 Pile cap Nos 178 48 6 42

4 Pier Nos 183 16 16


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED

Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate

16.2 438 3 441 230

4.0 145 - 145 693

8.4 20 - 20 158

3.2 - - 183
- - 104
- - 938
- - 1,988

velopment from 06-03-23

Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.

ur Hutment construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
4. P-9 Viaduct Land issue
5.Due to unavailablity of machinery (JCB,Hydra etc) work is being hampered in rotation and front wise
6.Due to lack of manpower skilled and unskilled work progress is slow
7.work progress suffers due to lack of supervision staff like foreman, supervisor and site engineers.
6/23/2023

Remarks

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1&2 Viaduct P7 Piling -Utilities encountered at location
Rig-3 Viaduct P6 -work in progress.
Rig-4 Bhimrad Station - work in progress.
Bhimrad Piling- Grid -C Utilities hindrance encountered WIP
VIP Piling- Grid -C & C' Utilities hindrance encountered WIP
VIP Piling- Grid -E' Anchor Pile, Design to be change WIP
P5 (01nos. Pile Group required traffic Diversion).
Rig-5&6- P-6 & VIP Station - work in progress.

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct

aggregate 01 each truck received on 13.03.2023 & Further Continue delivery


ery started at site.
ne encounter
ine 200mm dia
mm diameter encountered

Hydra etc) work is being hampered in rotation and front wise


skilled work progress is slow
k of supervision staff like foreman, supervisor and site engineers.
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23

A STATIONS + VIADUCT

1 Pile Nos 671 175 97 78

2 PIT & Sonic Test (CHSL) Nos 838 60 40 20

3 Pile cap Nos 178 48 6 42

4 Pier Nos 183 16 1 15


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED

Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate

19.5 441 3 444 227

5.0 145 - 145 693

10.5 20 - 20 158

3.8 - 1 1 182
- - 104
- - 938
- - 1,988

velopment from 06-03-23

Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.

ur Hutment construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
4. P-9 Viaduct Land issue
5.Due to unavailablity of machinery (JCB,Hydra etc) work is being hampered in rotation and front wise
6.Due to lack of manpower skilled and unskilled work progress is slow
7.work progress suffers due to lack of supervision staff like foreman, supervisor and site engineers.
6/24/2023

Remarks

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1&2 Viaduct P7 Piling -Utilities encountered at location
Rig-3 Viaduct P6 -work in progress.
Rig-4 Bhimrad Station - work in progress.
Bhimrad Piling- Grid -C Utilities hindrance encountered WIP
VIP Piling- Grid -C & C' Utilities hindrance encountered WIP
VIP Piling- Grid -E' Anchor Pile, Design to be change WIP
P5 (01nos. Pile Group required traffic Diversion).
Rig-5&6- P-6 & VIP Station - work in progress.

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct

aggregate 01 each truck received on 13.03.2023 & Further Continue delivery


ery started at site.
ne encounter
ine 200mm dia
mm diameter encountered

Hydra etc) work is being hampered in rotation and front wise


skilled work progress is slow
k of supervision staff like foreman, supervisor and site engineers.
SURAT METRO RAIL PR
DAILY PROGRESS REPO

PLANNED
Achieved
IECCL Target for for the
S.N. Description of Work Unit
SCOPE the June- month Balance
23

A STATIONS + VIADUCT

1 Pile Nos 671 175 98 77

2 PIT & Sonic Test (CHSL) Nos 838 60 40 20

3 Pile cap Nos 178 48 7 41

4 Pier Nos 183 16 1 15


5 Pier Cap Nos 104
6 Segment Casting Nos 938
7 Parapet Casting Nos 1988

OTHERS -
1 Erection of Batching Plant -M-1 (60cum) 98% Completed (Trial Batch PCC checked)
2 Erection Batching Plant -CP-30 100% Completed & operational
3 Calibration of Batching Plant -CP30 PCC production started for Casting yard development from 06-03-23
4 Cement Silo Erection 05 erected
5 TMT Bars - From 64.59-MT Shiva Infra+ Sadbhav-74-MT)
36-MT Coarse Sand received 06-03-2023, Plasticizer received 11-03-2023 &
6 Bulk Material started at site & 01 Bulker Cement - 39.01 MT Received on 13.03.2023 & no
7 Casting Goliath Crane foundations PCC work in progress
8 Temp. Structure i.e. Labour Hutment Material received at site 12-03-2023 & Labour Hutment construction work in p
Constraints -
1. P5-27 -below 6 Mtr utility encountered which sewerage line.
2. P5-26 - below 6 Mtr utility encountered which sewerage line.
3. P5-28 - below 6 Mtr utility encountered which sewerage line.
4. P5-23- below 5.0 Mtr encountered Jio Fibre Cables.
5. P5 28A to P530 - Traffic Route Diversion required
5. VIP STNS Grid -D -below 2.5 Mtr utility water pipe line
6. VIP STNS Grid -C' -below 2.5 Mtr utility water pipe line
RAT METRO RAIL PROJECT
DAILY PROGRESS REPORT
Date:
NED ACHIEVED

Today
Upto Cumul-
Asking Today Balance
Prev. ative
Rate

25.7 444 1 445 226

6.7 145 - 145 693

13.7 20 1 21 157

5.0 1 - 1 182
- - 104
- - 938
- - 1,988

velopment from 06-03-23

Plasticizer received 11-03-2023 & 10mm & 20mm aggregate 01 each truck received on 13.03.2023 & Further Continue delivery
MT Received on 13.03.2023 & now continue delivery started at site.

ur Hutment construction work in progress.


Constraints -
1. P7- CP-19 - below 6.0 Mtr Sewerage line encounter
2. P7-26 -below 2.5 Mtr utility water pipe line 200mm dia
3. Bhimrad -Grid -C' -rising main line 500mm diameter encountered
4. P-9 Viaduct Land issue
5.Due to unavailablity of machinery (JCB,Hydra etc) work is being hampered in rotation and front wise
6.Due to lack of manpower skilled and unskilled work progress is slow
7.work progress suffers due to lack of supervision staff like foreman, supervisor and site engineers.
6/25/2023

Remarks

Viaduct P9 Piling hold due to Land issue


Viaduct P8, WITI Piling work 100% complete,
Rig-1&2 Viaduct P7 Piling -Utilities encountered at location
Rig-3 Viaduct P6 -work in progress.
Rig-4 Bhimrad Station - work in progress.
Bhimrad Piling- Grid -C Utilities hindrance encountered WIP
VIP Piling- Grid -C & C' Utilities hindrance encountered WIP
VIP Piling- Grid -E' Anchor Pile, Design to be change WIP
P5 (01nos. Pile Group required traffic Diversion).
Rig-5&6- P-6 & VIP Station - work in progress.

03 Pile Cap Steel Reinf. fixing WIP & Pier Vertical steel pier vertical
steel bar threading work in progress.
Another 04 nos. pile cap Steel cutting & Bending done at Casting yard &
18 nos. Pile Cap PCC Completed & 12 nos Pile cap Group Pile Head
Chipping in progress
Pier shutter fixing WIP for Pier casting @ P7 viaduct

aggregate 01 each truck received on 13.03.2023 & Further Continue delivery


ery started at site.
ne encounter
ine 200mm dia
mm diameter encountered

Hydra etc) work is being hampered in rotation and front wise


skilled work progress is slow
k of supervision staff like foreman, supervisor and site engineers.