BRIEF INTRODUCTION

 Electric Loco Shed, Tughlakabad was commissioned on


15th June, 1988.
 Initial holding 100 locos for mail / exp. & goods
locomotives.
 Present Loco Holding: 224 Locos

WAG-9 WAP-7 TOTAL

129 95 224

2
ORGANIZATION: GAZETTED

Sr. DEE / TRS / TKD

DEE / TRS / TKD SMM / TRS / TKD

ADEE / TRS / TKD ADEE - Vacant


STAFF POSITION

% Vac. In
Sanctioned
Posts MOR Vac. Sanctioned
Strength
Strength

Supervisor 99 85 24 14.14

Technician 658 627 31 04.71

Unskilled 109 14 95 87.16

Total 866 726 140 16.17

4
PERFORMANCE

S. 2019-20 2020-21
Parameter % Imp/Det
No. (Up to Feb) (Up to Feb)

1 Accident cases on loco a/c 0 0 0

Punctuality loss
2 111 23 79.28
( Incidences)

Reconciled Failure/100
3 30.41 20.1 33.90
locos/Month

Unscheduled lifting / 100


4 6.52 4.56 30.06
loco / Month

2315
(including
5 Training Man days 2304 0.48
online
Webinars)

Scrap Disposal (in MT) (Upto March, 2021)


Ferrous Non-Ferrous Rs
( MT) ( MT)
Target 220 15 1,01,00,000
Actual 344.09 5.43 1,53,13,000

5
LOCO HOLDING BREAK-UP

WAP-7 WAG-9 TOTAL


95 129 224

WAP-7 WAG-9 WAG-9H TOTAL


99 21 108 224

WAP-7 WAG-9 WAG- TOTAL


9H
GTO 20 17 19 56
IGBT 75 5 88 168

MAKE WISE IGBT TRACTION CONVERTER


LOCO HOLDING

ABB BHEL BT MEDHA TOTAL

62 49 44 13 168
(Prop-35) (Prop-29) (Prop-22) (Prop-13) (Prop-99)
7
65th RAILWAY WEEK GM AWARD -2019 -20

Shri Krishan Mohan Singh Shri Vijay Kumar


Mahra / SSE/TKD Upadhyay/ SSE/TKD
BRONZE MEDAL IN NATIONAL WRESTLING
CHAMPIONSHIP HELD AT PHAGWARA

Shri Amit Kumar


OS/TRS/TKD

Shri Deepak Ujjawal


Tech./TRS/TKD
10
PROVISION OF DPWCS (DISTRIBUTED POWER
WIRELESS CONTROL SYSTEM)

 LocoNo-31214, 31207, 31504, 31220, 31185


& 31195 commissioned on 04.12.2020.

11
PROVISION OF CVVRS CREW VOICE AND VIDEO
RECORDING SYSTEM

CVVRS (Crew Voice and Video Recording System) have been


provided in 11 Locos (30460, 30653, 31482, 30513, 30488,
39025, 30516 , 30361, 39024 , 39031, 30721, 30340, 30519
and 30496).
“SARTHI”
BATTERY CUM AC OPERATED DUAL MODE SHUNTING
LOCOMOTIVE

2 nd PRIZE
Winner for Suggestion Scheme of
Best Innovation 2019
DUAL SHUNTING MODE LOCO - SARTHI

 Condemned WAM-4 loco has been converted into a dual


shunting mode loco which can work both on OHE as well as
Battery

 This has eased the shunting process in non electrified areas

Earlier shunting in non electrified areas was done with the


provision of additional dead locos / wagons as a means of
pushing or pulling arrangement which was unsafe and
cumbersome

Now only one loco is sufficient for any shunting


CDAC TCN VCU TEST SETUP

15
CDAC TCN VCU TEST SETUP

Electric loco shed Tuglakabad developed test jig for testing DIO cards of
CDAC TCN based vehicle control unit with help of D413 tool and CDAC
VCU Rack. DIO (digital input output ) cards receives various digital signal
(e.g. Panto status, VCB status etc) and gives desired output signals (e.g.
VCB ON/Off command, Panto Raising command etc) based on the logic
performed in processor cards.

The Shed is testing DIO cards of locomotives given trouble on line and

till date 10 cards found defective. At present this Setup is for testing DIO

but it will be extendable for other cards also. The same was agreed to by
16
the concerned firm in joint checking with Shed representatives.
TEST BENCH FOR HIGH-REACH
PANTOGRAPH

 Shed has developed this test bench to test various


parameters of High-Reach Pantograph in-situ.
 Panto Pan pressure on OHE can be measured without
physical weight from the floor only..
DUST FREE BEARING ROOM FOR AUX.

 Bearing condition being checked with the help of


magnifying glass.

 Maintenance / storage of bearings in dust free


environment.

 There shall be reduction in unscheduled visits due to


bearing failures of Aux. motors.
IN-HOUSE REPAIR OF MRB, TMB, OCB FILTER

TKD shed developed Vortex tubes through a local supplier and


started to repair scrap filters in-house.

19
PROVISION OF OHE SENSOR IN INSPECTION PIT

RED Bulb - OHE Live Position GREEN Bulb - OHE Isolate Position
20
HOG WORKING AND PHASE SEQUENCE TESTING
UNIT

 Volt Meter:- Three volt meters for showing output phase in


three phase.

 Phase Sequence Meter:- Three yellow LED’s for open phase


check. Green LED for showing correct phase sequence.
Red LED for showing reverse phase sequence.

21
HYDRAULIC JACK ARRANGEMENT FOR AXLE BOX
AND DRAFT GEAR

For axle box attention in 3 Phase loco, the loco had to be partially
lifted and it entailed opening of bellow, sensor, brake rigging of that
wheel, damper etc. and it took around 16 hours.

Now this shed is using Hydraulic Jack to check/attend the axle box
and do not required opening of bellow, sensor, brake rigging of that
wheel,, damper etc. also and loco given ready only 04 hours.

We can attend two axle boxes at same time. It saves both time and
man power.

The same arrangement is also used for dropping the CBC draft gear
without damaging the yoke of CBC. 22
PIVOT HOUSING CHANGING ARRANGEMENT

 Motorised Pivot Housing Changing Kit for fitting &

dismantling of pivot housing with suitable Zig fixture and


accessories.

23
DEVELOPMENT OF NEW PARK

24
DEVELOPMENT OF NEW PARK

25
COVID-19 – THE WAY AHEAD

• The regular loco minor schedule maintenance has

been split into two shifts so that staff can be

staggered.

• As of now the staff is being called in 6-14, 8-16, 10-18,

14-22, 16- 24 and 24-08.

• All the file work has been shifted to E-OFFICE.

• ARSENIC ALB 30 DISTRIBUTION has been done four

times to the staff

• Strict contact tracing and quarantine measures are

being adhered.

26
Thermal
Screening at
Shed Entrance

Touch Less Hand Hands Free Water


27
Wash Dispenser
Social distancing during tool distribution and
other common areas

28
Social distancing & Self Protection During Regular Work

29