Professional Documents
Culture Documents
Date: 23.12.23
SCOPE SUMMARY:
Page 1 of 6
7 FRE TA: APS Decontamination M/s Span chem 5200033167
technologies
8 FRETA-23 furnaces APS (31f1) n M/s Dattatray Enterprises 5300015175 KOM conducted on
VPS (32f1) jobs 16.11.2023
9 FRE Flare line (PPC37) M/s Excellent Projects (PO No 5300015770) KOM conducted on
replacement contract 15.12.2023. Gate passes preparation in progress.
7 APH
Page 2 of 6
FRE APS (31-F-1) Furnace
Panel shop Work
Total Panel cutting ETC for
welding done in
Sr. No. Description panel completed Pre-fab REMARK
completed last 24
(nos.) (nos.) completion
(RM) hours
1 Radiant Side 142 47 40 10 RM 15.01.2024 Scaffolding for Radiant
section completed and
2 Radiant End 72 0 15.01.2024 green tag received.
Convection Scaffolding for APH and
3 40 0 15.01.2024 duct in progress.
Side
Convection Total 2700/3500 cubic meter
4 29 0 15.01.2024 scaffolding completed.
End
Refractory mock up test
5 Roof Area 15.01.2024 done.
6 Duct Area 15.01.2024
7 APH
Work Remarks
Total Job done ETC for
TA Unit Total Pre- Completed / Total
Vendor scope in last Pre-fab
Job TA Scope Pre-fab.
24 completion
hours
Piping Simpag 17,732 ID 11284 / 16436 ID 102 15.01.2024 Jobs i/p on Utility Loops -
U1F/G, U7, U8, U12,
19,248 ID U21, 36A
HC loops – 17C/D, 41,
42, 24A
Page 3 of 6
Jobs i/p on OSBL loops –
15,794 ID PCTC-80, 73, 3, 83, 92.
Jyotsna 11055 ID 6637 / 11055 ID 70 15.01.2024
FRE P to P Loop 15, 17,
1, 19, 20
Gate Pass preparation in
Excellent
11,672 ID 7004 ID 0 / 7004 ID 0 15.01.2024 progress. Fab start ETC
Projects
26th Dec.
31 MT Erection of Temporary
17 MT –
Structure 10 MT – platform done for cutting
Structure
25 MT Structure of 1st deck at VPS
Structura SK 15 MT
Grating 10 MT Grating 0 15.01.2024 Condenser area.
l Cons Grating
500 RM – 300 RM – Hand
500 RM –
Hand railing
Hand railing
railing
Page 4 of 6
Pre-TA Exchanger Status
Page 5 of 6
4. Fit up for casing welding in progress. continue.
5. Flue gas duct elbow insulation removed 4. Fit up & welding of Panels.
and manual cleaning done 5. Shot blasting to be continued.
2. M/s Roto stat 1. Tagging of equipments completed. 1. Tagging of equipment to be
2. Survey for equipment structural continued.
replacement in progress. 2. Servicing of test rings to be
3. Servicing of test rings in progress (14/35 continued.
completed). 17 test rings shot blasting in 3. Scaffolding for Equipment.
progress. 4. Survey for equipment structural
4. Certification of welding/grinding machines replacement to be continued.
in progress. 5. Spade cutting.
5. BOM for Spading of drums & tower
prepared.
6. HE Handing over plan prepared.
Page 6 of 6