                        Date: 02.03.2020 

Dear Sir, 

Undersigned was on tour from 28.02.2020 to 01.03.2020 to coordinate with BTPS Site and Manufacturing units so as 
to ensure smooth work progress towards completion of COD activities. 
 
Unit‐1 current status to achieve COD: 
 
 Station Transformer‐1 was charged on 28.02.2020 
 Unit‐1 Boiler was Lighted up at 14:08 Hrs on 28.02.2020 
 Generator Transformer‐1, Unit Transformer‐1 A & B were also charged and load test was completed. 
 TG is on barring. 
 Fire protection system completion areas: 
 Temporary spray header is lined up and made operational for DV station of GT, ST, & UAT and 
demonstrated to Customer. 
 Spray and foam system for HFO TANK‐1 is ready. 
 Foam system for LDO tanks is ready 
 Spray system for BCN 10, Conv. 6a/b, and bunker Conv. is ready.  
 APRDS, Seal steam system and HP/LP bypass lines charging was completed. 
 Coal filled in 3 Nos of bunkers up to 250T out of 648T through Coal conveyors (ERH route). 
 3 Feeders (A, B & C) lined up and Firing with Coal is also completed. 
 Safety valve floating completed yesterday: Details as given below 

Valve Set Pressure 
Sl No  Service  Valve Tag  % Blowdown 
Open  Close 
1  CRH  SV‐8  47  44.7  5 
2  HRH  SV‐9  43.9  41.7  5 
3  HRH  SV‐10  43.9  41.7  5 
4  HRH  SV‐11  46.0  43.7  5 
5  HRH  SV‐12  46.0  43.7  5 
6  SH  SV‐4  165.6  159  5 
7  SH  SV‐5  165.6  159  5 
8  Drum  SV‐1  182.5  175.2  5 
9  Drum  SV‐2  186.2  176.9  5 
10  Drum  SV‐3  188.0  178.6  5 
 
 Steam dumping is in progress, followed by synchronisation after achievement of steam quality 
parameters.  

Steam quality parameters on 01.03.2020 @ 05:00 Hrs 
 
Sl. No.  Equipment/Area  Ph  Conductivity (ms/cm)  Silica (ppb) 
1  Drum  8.0  3.20  820  
2  MS line  7.45  1.58  22 
 

 Unit‐1 is ready for synchronisation with ESP PASS‐B; Day wise completion plan of balance works for 
COD of Unit # 1 is attached as Annexure‐1 

 
 

 
 
ESP PASS‐B Insulation completed  ESP PASS‐A Insulation is in progress 
 

 
Course ash evacuation system readiness from APH & DUCT hoppers 
 

 
 

 
Course ash tank, piping work is in progress 
 

Firing with is completed on 29.02.2020 with Feeder‐B 
 
 

 
Service Building 
 

Total civil status is attached as Annexure‐2. 

   
UF system contingency controller  HRH Safety valves 
 

 
 
UF System commissioning: 
 1st Stream UF System commissioning is completed on 29.02.2020 with BHEL made contingency controller. 
 Balance 2nd & 3rd will be completed with system PLC only. 
 
DM water quality at MB (Mixed Bed) outlet is around 9/10ppb (with in allowable limits). 

DM Water availability: 
DM Tanks: 2 Nos of DM tanks (each capacity 1500KL or 12Meter Height).
CST Tanks: 2 Nos of CS tanks (each capacity 750KL or 10Meter Height).

Note: Round the clock, Customer (from TSGENCO) available, DM water generation will be carried out as
per requirement.

HFO System:  
LDO forwarding pumps for unit 1 & 2 are ready and operational. 
LDO Tank: 2 nos tank ready and operational. 
HFO Tank: 1st tank erection completed along with unloading system (trail completed with one HFO road tanker). 7th 
lift of 2nd tank completed. HFO unloading Pump erection completed. 
 
Sl No  ACTIVITY DESCRIPTION  UOM  Total Qty.  Cumulative   Balance Work (%) 
Boiler # 2 Erection & Commissioning 
MS line internal HT completed on 05.12.19. 
(M/s INDWELL) 
Erection‐ Structure  MT  3236  3029  6% 
Erection‐ Pressure Parts  MT  3363  3229  4% 
Erection‐ Non Pressure Parts  MT  1828  1362  25% 

Erection‐ Rotary  MT  1000  833  17% 
Erection‐ Piping  MT  950  737  22% 
Hangers & Supports  MT  300  128  57% 
Erection‐ Insulation  MT  739  416  44% 
Erection ‐ Total  MT  11416  9734  15% 
ESP # 1 Erection & Commissioning  ESP‐2 Pass A ATT completed. ESP#2 balance jobs awarded to 
(HARJI)  M/s. SV Infratech on 16.01.2020 
2  Erection Unit # 2  MT  4050  2620  35% 
Duct Erection Unit # 2  MT  820  601  27% 
Erection ‐ Total  MT  10000  7924  21% 
ESP # 2 Erection & Commissioning  
     
(M/s SV Infratech) 

Erection Unit # 2  MT  4050  2620  35% 
Duct Erection Unit # 2  MT  820  601  27% 
 

Best regards 
EGURLA KUMARA SWAMY  
Dy. Manager 
PS PMG 
4x270 MW BTPS Manuguru
Day wise completion plan of balance works for COD of Unit # 1 
Target 
Sl. No. Activity Agency Status as on 01.03.2020
Completion
1 Hot PA Duct 15‐Jan‐20 M/s PCP Completed
2 Cold PA Duct 20‐Jan‐20 M/s PCP Erection & ATT completed. Insulation pending (not critical for coal firing)
3 ESP Pass B Mechanical Readiness 15‐Jan‐20 M/s Harji Completed
4 ESP Pass A Mechanical Readiness 18‐Jan‐20 M/s Harji Completed
5 ESP Pass A to Control Room Cabling 18‐Jan‐20 M/s Vasavi Cabling works in progress, expected completion by 05.03.2020
6 ESP Pass B field charging 18‐Jan‐20 M/s Vasavi Completed.
HVR erection commenced, 18/18 HVRs lifting & placement to roof completed. 
7 ESP Pass A field charging 22‐Jan‐20 M/s Vasavi
HVRs testing works commencement by 05.03.2020
8 Soot Blowing System Commissioning 24‐Jan‐20 M/s Vasavi  Completion by 05‐03‐2020
9 Feeder A & B Erection completion 11‐Jan‐20 M/s PCP Completed
10 Feeder D‐F commissioning 14‐Jan‐20 M/s KSL Completed
11 Feeder A‐C commissioning 22‐Jan‐20 M/s KSL Completed
12 Coal Piping with support 15‐Jan‐20 M/s PCP Completed.
13 Mills A‐C coupled trial  18‐Jan‐20 M/s PCP Mill‐A to C coupled trial completed with Roller setting.
14 Seal Air Piping 14‐Jan‐20 M/s PCP Completed
15 Seal Air Fan Trial 14‐Jan‐20 M/s PCP Completed
16 HFO Tank 1 readiness 20‐Jan‐20 M/s GMW Ready
17 HFO unloading system readiness 20‐Jan‐20 M/s GMW Completed & trial is also completed with HFO road tanker.
18 HFO forwarding piping 20‐Jan‐20 M/s PCP Insulaool tion works ompleted.
All three streams in manual mode made available.
DM Plant 2nd & 3rd stream in manual  M/s Ion 
19 22‐Jan‐20 1st Stream UF system commissioning completed with BHEL made contigency 
mode Exchange
controller and presently in service. 
M/s RA, 
20 AHP pipe rack stucture completion 15‐Jan‐20 Completed
M/s BVR
21 AHP Piping Works Completion 22‐Jan‐20 ISG Completed
22 AHP Cable racks readiness 11‐Jan‐20 TSGENCO Ready
23 AHP MCC‐1 Charging 14‐Jan‐20 M/s PRV Completed on 14‐01‐20
AHP Cable laying in ASPH, AVPH, AWPH & 
24 20‐Jan‐20 ISG Completed for U#1; In progress for other units and standby pumps
BAH
Commissioning of Drives in ASPH, AVPH, 
25 25‐Jan‐20 ISG All Drives for U#1 Commissioned 
AWPH & BAH
26 Input Power supply to CHP MCC # 2 08‐Jan‐20 M/s Vasavi Completed.
27 DCS Panels programming & testing 18‐Jan‐20 ISG Completed for CHP.
Transformers, MCC Panels Charging & 
28 11‐Jan‐20 ISG Completed
testing
29 HT motors trial run for BCN 10, 6B, 7B 10‐Jan‐20 ISG Completed.
30 Mobile Crusher Commissioning 16‐Jan‐20 ISG Commissioned with coal
31 ERH Drives Commissioning 16‐Jan‐20 ISG Completed
32 BCN 10 Trial Run 14‐Jan‐20 ISG DCS Trial completed on 31‐01‐20.
Conveyor 6A/B drives commissioning &  
33 15‐Jan‐20 ISG DCS Trial completed on 31‐01‐20.
Trial run
34 Coal availability at Mobile crusher 15‐Jan‐20 TSGENCO Approx 6800T coal available 
35 CHP MCC‐3 Charging 13‐Jan‐20 ISG Completed
Cabling for 6A/B & 7 A/B completed for COD. Cabling for 6A and 7A shall be 
36 Cabling work from MCC‐3 to Field 17‐Jan‐20 ISG
taken up later.
37 TP‐5 Drives Commissioning 20‐Jan‐20 ISG DCS Trial completed on 31‐01‐20.
Conveyor 7A/B drives commissioning &  
38 22‐Jan‐20 ISG DCS Trial completed on 31‐01‐20.
Trial run
39 Tipper Commissioning 22‐Jan‐20 ISG Trial done
40 Mills Clean Air Flow Test  20‐Jan‐20 M/s PCP Completed
Pneumatic Knives to be operated. Compressed air line is to be taken, header 
41 Mill Reject System ‐
made available tapping works to be done. Expected readiness by 05.03.2020
42 FPS (for coal firing) ‐ Completed in Unit‐1 Areas
43 Coal Firing 23‐Jan‐20 With ESP Pass‐B done on 29.02.2020
44 Safety valve floating 24‐Jan‐20 Completed on 01.03.2020
45 Syncronisation 25‐Jan‐20 With ESP Pass‐B, expected on 02.03.2020
46 COD 31‐Jan‐20

Page 1 of 1
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
S.No Description of work Status  as  on 29‐02‐2020 Remarks
UNIT‐1
a Base Raft Completed
1 b Columns Completed
c Deck slab Completed
d Condenser walls(2 Nos) Completed
POWER HOUSE
Erection of Steel structure 
a Foundations upto bolt lift Completed
is in progress.
2 b Floor Slabs Completed
c Roof Slab Completed Water proofing pending
d Cladding on A‐Row side Completed
BOILER
a Foundations upto bolt lift Completed
3
Pending due to material 
b Grade slab
clearance
MILL & BUNKER
a Foundations upto bolt lift Completed
4 b Feeder Floor at EL+18.815m Completed
c Mill foundation Completed
d Tippler Floor @50mtr lvl Completed
ESP
Erection works are in 
5 a Foundations upto bolt lift Completed
progress.
Grade slab Completed
ID DUCT FOUNDATIONS
a Right side of boiler Completed
b Left side of boiler Completed
c Boiler to ESP Completed
6
d ESP to Chimney
    i) Rafts  Completed
    ii)Pedestals (1st lift) Completed
    iii) Pedastals (bolt lift) Completed
MACHINERY FOUNDATION @ EL 0.00 M
a PA fan foundations
i)Left side of the boiler Completed
ii)Right side of boiler Completed
b FD fan foundations
i)Left side of the boiler Completed
ii)Right side of boiler Completed
c ID fan foundations
7
i) ID fan ‐A.
        I)Raft, Plinth beam Completed
Deck Completed
i) ID fan‐B
       IV)  Deck Completed
d BFP 
i) PCC Completed
ii) Raft Completed
CW PIT
a Raft Completed
8 b Walls Completed
c Pedastals Completed
TRANFORMER YARD
GENERATING TRANSFORMER
a Rafts completed
9 b walls completed
Transformer placed in 
c railing completed
position.
OIL WATER PIT
10 a Raft completed
b walls& Slab completed
DG Building for Unit1&2

Page 1 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
a DG foundations completed
11 b Cable trench Reinforcement binding is in progress
internal plastering is 
c Plastering
pending
STATION TRANSFORMER
a Raft Completed
b Walls Completed
d Raft for fire wall Completed
12 e Fire wall Completed
f Basin Slab Completed
Unit Transformer
UT#1A, UT#1B Completed
Fire wall Completed
CCR for Unit 1&2
a Foundations upto bolt lift Completed
b Grade slab @ EL+0.00m completed.
C Floor slabs
i) A‐B bay All floor slabs completed. Painting works and flooring 
13 i) B‐C bay All floor slabs completed. works are in progress in all 
ii) C‐F Bay All floor slabs completed. switch gear rooms and 
d Roof slab completed.
e Brick work completed.
f A‐ row sheeting ‐ Work is in progress.
Unit‐2
TG Foundation
a Base Raft Completed
14 b Columns Completed
c Deck slab Completed
d Condenser walls(2 Nos) Completed
POWER HOUSE
a Foundations upto bolt lift Completed
   b Floor slabs
i A‐B bay All floor slabs completed.
15
ii B‐C bay All floor slabs completed.
iii Misc. Floor slabs
MOT slab Completed
c Roof slab completed.
BOILER
16 Erection works are in 
a Foundations upto bolt lift Completed
progress.
MILL & BUNKER
Erection of steel structure 
a Foundations upto bolt lift Completed
is in progress.
b Mill foundations 3 completed out of 6.
Reinforcement placing for 
17
c Feeder Floor @EL+19.0m Grid 11‐13 completed. balance work is in 
progress. 
d Tripper floor@EL+50.0m Completed
Reinforcement placing is in 
e Roof slab ‐
progress.
ESP
a Foundations upto bolt lift Completed
18
Clearance not available for 
b Grade slab  50% completed.
balance work.
ID DUCT FOUNDATIONS
a Right side of boiler Completed
b Left side of boiler Completed
19 c Boiler to ESP Completed
d ESP to chimney
Footings 26 completed out of 27
Columns 33 completed out of 36
MACHINERY FOUNDATION @ EL 0.00 M
a PA fan foundations
i) Left side of boiler Completed

Page 2 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
ii)Right side of boiler Completed
b FD fan foundations
i) Left side of boiler Completed
hii)Right side of boiler Completed
20 c GR fan foundations 1st lift completed for 1 foundation.
Power House
d BFP  foundations completed.
e DMCW pump foundations completed.
f Vacuum pump foundations Completed.
g ID fan foundations
ID fan‐A completed(upto deck slab).
ID fan ‐B completed(upto deck slab).
21 CW PIT Completed.
TRANFORMER YARD
22
GENERATING TRANSFORMER Completed.
23 OIL WATER PIT Completed.
ESP Control Room for unit 1&2
a Foundations upto bolt lift Completed
b Erection of structural steel Completed
c 3.5mtr floor Completed
d 9mtr floor Completed
24
brickwork till El+0.00mtr 
completed, brick work 
e Brickwork @3.5mtr lvl: brick work 
above lintel beam is in 
progress
Central Lube Oil Room
25 Erection of steel structure 
a Columns upto bolt lift 6 completed out of 6.
is in progress.
Unit‐3
TG Foundation
a)TG Raft Completed
26 b)TG Columns Completed
c) TG Deck Completed
d) Condenser walls Completed
Power house Building
27 Structural Steel erection is 
a a)Power House Foundations Completed
in progress
Boiler
28 Structural Steel erection is 
a a)Boiler foundations Completed
in progress.
ESP
29 Structural Steel erection is 
a a)ESP foundations Completed
in progress.
MILL & BUNKER
Structural Steel erection is 
a a)Bunker foundations Completed
in progress.
Placing Reinforcement is in 
30 b)Mills 4 out of 6 completed
progress for 4th mill
c)Feeder floor Grid 19‐23 completed
d)Trippler floor
 i)Interconnection Between Unit2&3 Completed
ii) Unit#3 floor Completed
ID Duct foundations
a a)Right side of Boiler Completed
31
b b)Left side of Boiler Completed
c c)Boiler to ESP Completed
Machinery foundation @ EL‐0.00m
a a)PA Fan foundations
on hold for ease in 
i)Right side of Boiler Plum PCC Completed accessibility towards boiler 
erection
ii)Left side of Boiler Completed

Page 3 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
b B)FD Fan foundations
on hold for ease in 
i)Right side of Boiler Completed accessibility towards boiler 
erection
32
ii)Left side of Boiler Completed
ID fan foundations
i) ID fan ‐A
      I)Deck Completed
i) ID fan‐B
       I) Deck Completed

c C)BFP Foundations
i) Plumb PCC Completed
ii) RCC Completed
CW Pit
i) CW Pit walls Completed
33
insert plates yet to be 
ii)Pedestals RCC Completed
inserted.
Generating Transformer
i)Foundation Rafts Completed
ii)Pedestal upto bottom of slab Completed
34
iii)walls (final lift) Completed
Transformer placed in 
iv)Railings Completed
position.
DG Building Unit 3&4
i) Rafts Completed
ii) Pesetals upto plinth beam Completed
35
Brick wall and Sand filling Completed
DG Foundation Completed
Plinth beam Completed
Station Transformer
i) Raft Completed
Transformer placed in 
36 ii)walls Completed
position.
iii)Fire wall Completed
iv)Railings Completed
Oil water pit
i)Raft‐RCC Completed
ii) walls Completed
SPBD
i)Raft‐RCC 29 completed out of 62
i)Pedestals‐1st lift 44 completed out of 110
Power House#3&4 and CCR ( Unit 3&4)
a a)CCR Foundations Completed
b Floor slab
i)A‐B Bay
At EL +3.5m Grid 26a‐30 completed
At EL +4.5m Grid 24‐25 completed(MOT)
At EL +8.5m Grid 26a‐30 completed.
At EL +9.00m Grid 20‐26 completed.
At EL +11.5m Grid 26a‐30 completed
At EL +15.5m Completed
ii)B‐C Bay
37 At EL +3.5m Grid 26a‐30 completed
At EL +8.5m Grid 26a‐30 completed
At EL +9.0m Grid 18‐26 completed.
At EL +12.5m Grid 26a‐30 completed
At EL +15.5m Grid 18‐33 completed.
At EL +21.0m Grid 18‐32 completed
iii) C‐E Bay
At EL +8.00m Completed
At EL +12.5m completed
At EL +15.5m Grid 26a‐30 completed(4/4)
At EL +21.0m Grid 26a‐30 completed

Page 4 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
iv) E‐F Bay
At EL +5.00m Completed
At EL +8.00m Completed
At EL +12.5m completed(4/4)
At EL +15.5m completed.(2/2)
At EL +21.0m completed.(2/2)
Unit‐4
TG Foundation
a a)TG Raft Completed
38 b b)TG Columns Completed
c c) TG Deck Casting completed on 25‐06‐18.
d Condenser walls  Completed
Power house Building
39 Structural Steel erection is 
a a)Power House Foundations Completed
in progress.
Boiler
40 Structural Steel erection is 
a a)Boiler foundations Completed
in progress.
ESP
41 Structural Steel erection is 
a)ESP foundations Completed
in progress.
MILL & BUNKER
42 Erection of steel structure 
a a)Bunker foundations Completed
is in progress.
43 FAE TOWER Foundations Completed.
ID Duct foundations
a a)Right side of Boiler Completed
b)Left side of Boiler Completed
44 c) Boiler to ESP Completed
d) ESP to Chimney
          i)Rafts 17 out of 27 completed
          ii) columns upto final lift 30 out of 36 completed
Machinery foundation @ EL‐0.00m
a)PA Fan foundations
on hold for ease in 
i)Right side of Boiler Plum PCC Completed accessibility towards boiler 
erection
ii)Left side of Boiler completed
B)FD Fan foundations
on hold for ease in 
i)Right side of Boiler Plum PCC Completed accessibility towards boiler 
45
erection
ii)Left side of Boiler completed.
C)BFP Foundations
ii) RCC 3 Nos completed out of 3
D) ID FAN Foundations
a) ID Fan‐A Completed upto bottom of main beam.
b) ID Fan‐B up to deck slab Completed
E) GR fan foundation
a)GR Fan‐A 1st lift completed ‐
CW Pit
i) CW Pit walls Completed
46
insert plates yet to be 
ii)Pedestals RCC Completed
inserted.
Generating Transformer
i)Foundation Rafts Completed
ii)Pedestal upto bottom of slab Completed
47
iii)walls (final lift) Completed
iv)Railings Completed Back filling is in progress.
Oil water pit
48 i) Raft  completed
ii) walls completed
Unit Transformer

Page 5 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
UT#A
i)Raft‐RCC Completed
49 Shuttering is in progress 
ii) walls 1st lift completed
for remaining lifts
UT#B
i)Raft‐RCC Completed
Erection of steel structure 
50 ESP Control Room for unit 3&4 Completed upto bolt lift of columns
is in progress.
Structural steel fabrication and Shot blasting
For Power house#1 2665.125 MT completed out of 2665.125MT Fabrication completed.
For Power house#2 2665.125 MT completed out of 2665.125MT  Fabrication completed.
For CCR# 1&2 2474.424 MT completed out of 2474.424 MT Fabrication completed.
ESP Control Room 1&2 417.462 MT completed out of 417.462 MT Fabrication completed.
For Power house#3 2839.111 MT completed out of 2839.111 MT Fabrication completed.
51 Fabrication of Remaining 
For Power house#4 2800.32 MT completed out of 2839.111 MT
quantity is in progress.
For CCR# 3&4 2478.285 MT completed out of 2478.285 MT Fabrication completed.
ESP Control Room 3&4 417.462 MT completed out of 417.462 MT Fabrication completed.
Fabrication of Remaining 
For Bunkers (unit‐1 to Unit‐4) 14252 completed out of 15500 MT.
quantity is in progress.
Structural steel Erection
For Power house#1 2665.125 MT completed out of 2665.125MT Erection completed.
For Power house#2 2665.125 MT completed out of 2665.125MT  Erection completed.
For CCR# 1&2 2474.424 MT completed out of 2474.424 MT Erection Completed.
ESP Control Room 1&2 417.462 MT completed out of 417.462 MT Erection Completed.
Erection of Remaining 
For Power house#3 2780.321 MT completed out of 2839.111 MT
quantity is in progress
Erection of Remaining 
For Power house#4 2650.321 MT completed out of 2839.111 MT
quantity is in progress
For CCR# 3&4 2478.285 MT completed out of 2478.285 MT Erection Completed.
52
Erection of Remaining 
ESP Control Room 3&4 415.462 MT completed out of 417.462 MT
quantity is in progress. 
Erection of Remaining 
Bunker (Unit‐1) 3433 MT Completed.
quantity is in progress
Erection of Remaining 
Bunker (Unit‐2) 3168completed.
quantity is in progress
Erection of Remaining 
Bunker (Unit‐3) 1972 completed.
quantity is in progress
Erection of Remaining 
Bunker (Unit‐4) 37 MT completed.
quantity is in progress
Chimney
Unit 1&2 EL:270/270 m
i) Raft Completed
ii) Shell concreting Completed
iii) Structural Steel Erection
53
Internal Platforms @EL:269m, 265m, 225m, 185m,  Flue can for Unit#1 
Structural Beam Erection 
145m& 105m completed erection completed
43/51 Flue can assembled for Unit#2 lifting for erection of fifth 
Flue Can Erection 
segment is in progress
Unit 3&4 EL: 270.00/270.00 mtr
i) Raft Completed
ii) Shell concreting completed
iii) Structural Steel Fabrication
____a) Floor Beam  324.627/325.55 MT
____b) Flue Can ‐ Unit‐III 309.000/401.500 MT
____c) Flue Can ‐ Unit‐IV 116.000/401.500 MT
54
iv) Structural Steel Errection
____a) Floor Beam  324.627/325.55 MT
____b) Flue Can ‐ Unit‐III 117.247/401.500 MT
____c) Flue Can ‐ Unit‐IV 0.00/401.500 MT

Page 6 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status

Switch yard
Tower Foundations
i)Rafts 63 Nos completed out of 67
55
ii)Pedestals (1st lift) 63 Nos completed out of 67
ii)Pedestals (bolt  lift) 58 Nos completed out of 67
EquipmentFoundations
i)Rafts 718 Nos completed out of 882
56
ii)Pedestals (1st lift) 709 Nos completed out of 882
ii)Pedestals (bolt  lift) 680 Nos completed out of 882
Switch yard Control room
i)Control rom slab Completed
ii)1st floor slab Completed
57
External plastering is in 
iii) Plastering
progress 90% completed
Switch yard Roads
58 i)PCC Completed
ii)RCC Completed
Cable trench
i)PCC Completed
59
ii)RCC Completed
Ash Handling Point
Ash Slurry Pump House ‐1&2
Footings completed
Columns completed
Plinth Beam completed
Sump Tank completed
Slurry walls completed
Crane Beams completed
Roof Beams and Roof Slab completed
60
Parapet Wall over Roof Slab completed
Tool Room and Toilet Room completed
Lintel Beams completed
Cable trench completed
Brick Work completed
Plastering  completed
Equipment foundations  completed
Grade slab completed
Seal Water Tank completed
Thrust Blocks Upto 1st lift completed
Vaccum Pump and Compressor House ‐1&2
Footings Completed
Columns ‐ (24 Nos) Completed
Plinth Beams Completed
Lintel Beams Completed
Brick work and Plastering Completed
Girder Beams Completed
Roof Beams(22 Nos) Completed
Roof Slab Completed
ParapetWall completed
Cable Trench and Cable Slits Completed
61
Conveying Air Compressor Pump Pedestals  (6 
Completed
Nos)
Instant Air Compressor Pedestals ( 2 Nos) Completed
Air Driyers Pedestals(2 Nos) Completed
Air Blowers (3Nos) Completed
Heaters(3 Nos) Completed
Vaccum Pump Pedestals (12 Nos) Completed
Air Coolers (6 Nos) Completed
Air Recievers (3 Nos) Completed
Grade slab Completed

Page 7 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
Sump Tank Completed
Plinth Protection Drain Along the Grid‐A is completed
Ash Slurry Pump House ‐ 3&4
Footings 21 Nos completed out of 23Nos
Columns( 1st lift ) 18 Nos completed out of 24Nos
Columns( 2nd lift ) 16 Nos completed out of 24Nos
Columns upto Girder Beams Completed
Columns upto Bottom of Roof Beams Completed
Plinth Beam 130 m completed out of 155m length
Tie Beams 18m completed
62 Sump Tank 1st lift completed
Slurry Tank Wall wall on Grid‐C completed
Girder Beams  Completed
Roof Slab Completed
Brickwork 90% completed
Plastering  90% completed
Equipment foundations  Raft for 3 Nos Seal Motor pumps completed
Main Cable Trench Raft Completed
Stair Case ‐
MCC‐1 for AHP
Footings Completed
Plinth Beams  Completed
63
Ground Floor Slab @ EL +5.950 Completed
Brick Work Completed
First Floor Slab @ EL +9.950 Completed
Roof  Slab @ EL +15.950 Completed
Cable Trench and Grade Slab Completed
Battery Room Completed
Head Room Slab ‐
Vaccum Pump and Compressor House ‐3&4
Footings 19 Nos completed out of 24Nos 
64
Columns upto bottom of Girdrer/Crane Beam 19 Nos completed out of 24Nos 
Plinth Beam Along Grid‐A and Grid‐C completed
Crane Beam ‐
MCC‐2 for AHP
Footings Completed
Plinth Beams 158m completed
65
Columns upto bottom of the Lintel Beam 27 Nos Completed out of 29 Nos
Columns upto bottom of Roof Beam 26 Nos Completed out of 29 Nos
Roof Slab Scaffolding is completed
66 Silos Utility Building 
Grade Slab  Not yet commenced
Brick work and Plastering completed.
Fly Ash Silos(2 nos)
Slab @ EL +8.90 completed. Balance works are in 
Silo ‐ 1
64 progress.
Silo ‐ 2 Columns 2nd lift completed.
ROADS
RCC Roads
10.0m Wide RCC Road Completed
N‐401.875 , S‐33.75, E‐138, E‐534.25, N‐534.275, W‐
65 7.5m Wide RCC Road
84.250 , S‐94.875 roads completed
5.625m wide RCC Road E‐257.1875  completed
3.75m wide RCC Road E‐273 road around 120m completed
BT Roads
Balance work is in pending 
7.5m wide Patrol Road(1st Layer) 1150m completed out of 1230m
near Gate‐II
66 Balance work is pending in 
3.75m wide Patrol Road(1st Layer) 2559m completed out of 5260m reservoir area and farmers 
land area
3.75m wide BT BOP Internal Roads 1034m completed out of 2758m Work put on hold

Page 8 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
WBM
10m wide Roads Completed Completed
7.5m wide Roads Completed Completed
Work is in progress near CT‐
3&4 and put on hold in 
3.75m wide BOP internal roads 2158m completed out of 2758m
67 CHP Area for erection 
works
Balance work is pending in 
3.75m wide Patrol Roads 3095m completed out of 5260m reservoir area and farmers 
land area
Drain No.111 raft is 
68 Drains 3.8 KM completed out of 22KM length
completed
Deck Slab, parapet wall and PCC for Apron is 
69 Box culvert for Patrol Road (4 vents)
completed
Raw water Reservoir
v) Raw water reservoir water level RL: 71.000/71.000m 
WBM for BT roads for reservoir approach road and 
vi) Roads
71 reservoir bund completed
viii) Toe drain completed
ix) Raw water Rip Rap 1450/1750 Rmt completed
ix) Raw water Grass Turfing 1200/1750 Rmt completed

BOP WORKS
Administrative Building
73
Brick work Ground floor90% & first floor 80% completed.

Plastering Ground floor90% & first floor 80% completed.
Grade slab In progress
Service Building
74
PCC Under progress
Foundations 

Pre Treatment Plant
80 Chlorination Building
Roof Slab completed.
Gate House & Security Building
81 Balance works are in 
Lintel beam @ EL +9.825M  completed
progress.
Canteen Building
82 Slab Roof slab completed.
Brick Work Brick work is in progress.
Fire Station Building
83 Ground Floor slab completed
Floor Slab 50% of Slab centering is in progress
Chemical Lab Building
84 Columns Up to lintel level completed
Lintel beam Is in progress.
85 Effluent Treatement Plant
Balance works are in 
Plint Beam completed
progress.
Coal Handling Plant
Stacker Reclaimer‐1
17 Modules out of 18 Modules completed
83 Foundations 

Tie Beam with Bolt lifts  15/18 No Modules Completed
Stacker Reclaimer‐2
84 Foundations 16 Out of 17 Modules completed. 
Tie Beam with Bolt lifts  12/18 Modules completed
Track Hopper
Excavation Completed
PCC Completed

Page 9 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
85 Raft 10 Nos completed out of 10 Nos.
Wall and counterforts second lift 3Nos(Module 1,2&10) completed out of 10 Nos.
Wall and counterforts first lift 10/10Modules  completed. 
Tranfer Point 1
Raft  completed
86
Slab @‐19.850M  Completed
 Wall and counterforts upto ‐ 16.70Mtr Completed 
Wagon Tippler
Raft Completed 
87
Slab EL ‐ 12.35M  Completed
Apron Feeder Raft Completed
Tunnel 2 A/B ‐Segment 2 (Wagon Tippler to TP 
2)
PCC 52Rm/52 RM completed
88
Raft 52Rm/52 RM completed
Wall first lift  52RM completed 
Slab 42Rm completed 
Transfer point 2
PCC  Completed.
Raft Completed.
89
Slab@‐21.05M Completed
Slab @EL‐16.75M  Completed. 
wall completed upto ‐14.35 mtr complete
Conveyor 8 A/B(Stacker Reclaimer 1 to TP 3)
90
Rafts 10/10 Nos Completed
Tie beam with bolt lifts.  10/10 completed
Conveyor 9A/B(Stacker Reclaimer 2 to TP 4)
91
Raft 10/10Nos completed
Tie beam with bolt lifts.  10/10 Nos completed.
Tunnel 3 A/B(TP 2 to Pent House 1):‐
Raft completed
92 Wall First lift Right side 140Rm/142RM completed
Wall First lift left side 140RM/142 RM completed.
Slab 75RM/142RM completed
Pent House‐1
93 Rafts 4/4 Nos completed
Column upto bottom of Tie beam 4/4Nos completed. 
MCC 1
94 Rafts 30/30 Nos completed.
Columns upto bottom of Tie beam.  30/30Nos completed. 
MCC‐2
Ground floor slab EL(+) 4.00 completed from grid 8 to 20
First floor slab EL(+) 10.00 completed from grid 8 to 14
95
Columns above the plinth beam at EL(+) 0.00 columns are in progress from grid 1 to 8

MCC‐3
columns up to groud floor level 24/24 Nos completed
Ground floor slab completed  completed
96 First floor lintel @EL+6.15M Completed
Roof slab @EL+10.00M Completed
Grade Slab   Soling Completed
Brick work  Ground floor brick is in progress
Dust Supression Pump House
97 Rafts 12/12 Nos completed.
Columns 1st lift 8 Nos/12Nos completed.
Fuel oil unloading pumphouse
98 a) MCC and Control room
Roof slab Completed
Fabrication of structural steel in  CHP
a Transfer point 3 187.76MT out of 200 MT

Page 10 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
b Transfer point 4 198.15MT out of 212.49MT completed
c Transfer point 5 571.37 out of 557.00MT completed
Conveyor Trestle 3 A/B 119.96MT out of  700.00 MT completed
d Conveyor Trestle 4 A/B 301.60MT out of  310.00  MT completed
e Conveyor Trestle 5 A/B 232.24MT out of  264.23MT complete
f Conveyor Trestle 6 A/B 6751.83MT out of  760.00MT completed
99 g Conveyor Trestle 7 A/B 361.32MT out of  415.00MT completed
Conveyor Trestle 8 A/B 99.43MT out of  108.29 MT completed
Conveyor Trestle 9 A/B 98.12MT  out of  105.00 MT completed
h Conveyor Trestle 10 A/B 109.31MT out of  111.00 MT completed
i Pipe Rack 217.05MT out of  222.80MT completed
j Crusher House 1091.61MT out of  1300.0MT completed
Ash pipe rack  328.69MT out of  1300.0MT completed
Track hopper  89.01of  738.00MT completed
100 Erection of Structural steel in CHP
slow progress due to 
a Transfer point 3 134.24MT out of 222.45MT completed
insufficient machinery
b Transfer point 4 197.33 out of 212.49MT completed
slow progress due to Lack 
c Transfer point 5 489.03MT out of 597.26 MT completed
of labour 
d Conveyor Trestle 4 A/B 288.93 outof  310 MT completed ‐
e Conveyor Trestle 5 A/B 168.34 out of 264.23.0 MT completed
f Conveyor Trestle 6 A/B 500.47 out of  700 MT completed
Conveyor Trestle 7 A/B 50.00MT out of 415.00MT Completed
Conveyor Trestle 9A/B 98.12MT out of 105.00mpleted
Conveyor Trestle 10 A/B 101.65MT out of 111.00mpleted 0
Crusher House 709.79out of  1300 MT completed
g Pipe Rack 154.00 MT out of 222.80MT Completed
NDCT‐3
Balance works
Pavement and drain yet to 
a Stair case 2 FLIGHTS /3 Liftscompleted.
be commenced.
103
c D.pipe‐  1692/1862.98Rmt completed(91% completed)
d Fill Beam‐  414/488No’s completed(85% completed)
e V‐Bar‐ 177189/2,36,757No’s completed(75% completed)
NDCT‐4
1st Half
Fill Installation
a D.pipe‐  1692/1862.98Rmt completed(91% completed)
b Fill Beam‐  414/488No’s completed(85% completed)
104 c V‐Bar‐ 177189/2,36,757No’s completed(75% completed)
2nd half
a G Column 1stlevel :  75/79 No’s completed.
b G bkt 1st level:  73/79 No’s completed
c G Column 2ndlevel : 69/79 No’s completed.
d GBrac 2nd level:  67/79 No’s completed
e PcastErec IMB:  17/132 No’s completed
f PcastErec Main:  54/92 No’s completed
g PcastErec Sec:  184/323 No’s completed
Fill Installation
a D.pipe‐  192/1862.98Rmt completed(10% completed)
b Fill Beam‐  45/488No’s completed(09% completed)
c V‐Bar‐ 18700/2,36,757No’s completed(08% completed)

CW Pump house‐1&2
CW & ACWPump House
a CW Pumphouse raft Completed
b Pump house columns  Completed
CW Pump house slab @ +0.95m EL( Mezzanaine 
c Slab casting completed between B & C rows
105 Floor)
f ACW Pump house raft Completed

Page 11 of 12
Project: 4x270MW Bhdradri TPS As on 29.02.2020
Civil Works Status
g ACW pump house  Slab casting completed. 
CW Pump house slab @ +4.95m EL( Mezzanaine 
d Slab casting completed
Floor)
e Brick work is in progress
Feed pool
106 d Feed Pool segment walls completed
g Counterfort Walls completed
CW Channel
107
a CW channel from NDCT‐02 to pump house Completed
108 b CW channel from NDCT‐01 to pump house Completed
Chlorination Plant
a Footings Completed
109
b Columns up to slab level 31 nos completed out of 31 nos
c Roof slab completed 
CW Treatment Plant
a Footings  Completed
110
b Columns  Completed
c Top Slab & Parapet wall Completed
CW Pump house‐3&4
CW & ACWPump House 
a CW Pumphouse raft Completed
b Pump house columns  Completed
CW Pump house slab @ +0.95m EL( Mezzanaine 
111 c Completed
Floor)
f ACW Pump house raft Completed
g ACW Pump house walls Completed
ACW Pump house slab completed Completed
h CW Pump house slab @ EL + 4.95 m Completed
Feed pool Completed
a Raft 1st lift Completed
b Raft 2nd lift Completed
113
c Stone aggregate of size 63mm to 45mm Completed
f Feed pool segment walls 4thlift completed
i Counterfort Walls 4rd lift completed
CW Channel
114 a CW channel from NDCT‐03 to pump house RCC is in progress
b CW channel from NDCT‐04 to pump house Completed
Chlorination Plant
115 a Footings Completed
b Columns (up to plinth level) 31 nos completed out of 31 nos
CW Treatment Plant
a Footings  Completed
116
b Columns  completed
c Roof slab completed
Nala Diversion
a PCC 2.150/2.150 kms completed
117 b RCC for bottom slab 2.150/2.150 kms completed
c RCC for side walls (1st lift) 2.150/2.150 kms completed
d RCC for side walls (2nd lift) 2.100/2.150 kms completed
Ash water pump house
a Pcc  Completed
b RCC Raft Completed
118 c RCC Walls Completed
d RCC Columns 21 nos completed out of 21 nos 
e RCC Slab  EL ‐1.25 mtr Completed
f RCC Slab  EL 6.40 mtr Completed
Raw Water Pump House, Chemical House for PTP, Clarified Water Storage Pump House &Annexe Building, DM Plant Building, 
Fuel Oil Forwarding Pump House and MCC Building, CST Pump House, IA/SA Compressor House, Chlorination Building 1&2 & 
CW Treatment Plant Unit – 1,2,3 &4.
119 a Status of work for above structures.
* Major civil works are completed. Fixing of doors and windows, painting, rain water pipes, storm water drains, plinth 
protection, roof water proofing & flooring are in progress.

Page 12 of 12