Professional Documents
Culture Documents
Minutes of Special Meeting on “RGMO/FGMO and PSS Tuning of Generators in Eastern Region” held
at ERPC, Kolkata on 31.01.2019 at 11:00 hrs
Member Secretary, ERPC chaired the meeting. He welcomed all the participants in the meeting. He informed
that the issue of RGMO/FGMO and PSS Tuning is being reviewed in every OCC Meeting. But there was no
significant improvement in the performance of the generators. In order to discuss the issue in detail, in 148th
OCC Meeting held on 20.08.2018, it was decided that a separate meeting on Restricted Governor /Free
Governor Mode Operation and PSS Tuning of generators with the power station authorities in the Eastern
Region shall be convened for detailed deliberation.
He informed that vide CERC order dated 31st July 2017 in Petition No. 84/MP/2015, the Commission directed
the following:
Section 23 “
a) Considering the fact that further measures have been put in place to facilitate desirable primary
response, the Commission, starting from the month of September, 2017 shall be closely watching the
primary response of ISGSs as reported by POSOCO/NLDCs. At the State level, SLDCs shall report
the frequency response of intra-State generators to the concerned SERCs.
b) NLDCs and SLDCs through the assistance of POSOCO shall start the process of selecting
independent third parties capable of undertaking periodic checkups to monitor the RGMO/FGMO
response. To start with, selected independent third parties shall be sent to the generating stations which
are not providing the desired RGMO/FGMO response. Independent Third Parties shall ensure that the
generator has not, in any way, prevented/disabled the governor from providing the desired response. In
case, even after enabling the governors, units are not able to provide the desired response as per the
provisions of the Grid Code, third parties, based on the submissions of the generators, shall bring out
the technical constraints, if any, which limit the primary response of the units.
c) All ISGSs are directed to provide primary response compulsorily in terms of Regulation 5.2 (f), (g),
(h) and (i) of the Grid Code failing which we would not hesitate in initiating action under Section 142
of Electricity Act, 2003 for not providing desired RGMO/FGMO response without any valid reasons.
”
Section 24
“….. The Committee (on implementation of FGMO / primary response) has also recommended that there is no
requirement for granting any exemption even to LMZ units from operation under RGMO/FGMO with manual
intervention.”
“… has the option of either expediting the R&M of old units which shall include installation of new EHG
governors capable of providing adequate primary response or to go in for retrofit of mechanical governors for
adopting RGMO features or to operate on FGMO with manual intervention…”
He advised all the power stations to take the necessary action to improve the performance of the generators.
ERLDC gave detailed presentation on Primary Response of Generators in the Eastern Regions. The
presentation is enclosed at Annexure-I.
During the meeting, the generating stations raised queries pertaining to the following:
1. Regulatory requirement from the IEGC, CERC orders and Expert Committee recommendations
2. Exemption to old units from providing FGMO / RGMO response
3. Triggering criteria for frequency response, rate/quantum/duration of response
4. Data logging (resolution) and assessment of response
The queries raised by the generating stations were clarified by ERLDC/ERPC as under:
1. Primary frequency control is automatic and it aims to arrest the grid frequency variations by
automatically varying generator output as per its droop characteristics. Restoration of frequency to the
nominal i.e. 50 Hz in case of India is achieved through secondary and tertiary controls ranging from
few minutes to hours.
2. Time frame for primary governor control action is of the order of a few seconds i.e. 5- 30 seconds and
should last for at least 3-4 minutes to enable secondary control to take over which will allow the
primary reserves to be restored. (Ref: 17.2 of Report of the Committee on Free Governor Mode
Operation of Generating Units, Ref: Chapter 4, Page 34 of Report of Expert Group to review
and suggest measures for bringing power system operation closer to National Reference
Frequency).
3. IEGC permits a ripple filter of 0.03 Hz. This implies that the unit shall provide primary response
whenever the change in frequency is more than 0.03 Hz. The time between two successive frequency
measurements shall be suitably tuned to provide primary response within 5-30 seconds of the grid
event causing the change in frequency. (Ref : IEGC 5.2(f))
4. After the automatic primary response the unit may be brought back to its scheduled load at the rate of
1% per minute though local supplementary control. (Ref: IEGC 5.2(i))
5. The ex-bus schedule shall be restricted to MCR less normative auxiliary consumption. Operation in
Valve wide-open mode is prohibited. The control valves shall be kept throttled to provide governor
response at all times. (Ref: IEGC 5.2(h))
6. No exemption has been granted by CEC to LMZ units for operation under RGMO/FGMO. In case of
difficulty to operate in RGMO, generators may operate under FGMO with manual intervention for
providing mandated response as per the provisions of the Grid Code. (Ref: CERC order in Petition
No. 65/MP/2014, Ref: CERC order in Petition No. 84/MP/2015,Ref: 19.9 of Report of the
Committee on Free Governor Mode Operation of Generating Units).
7. The methodology used for computing the Frequency Response Characteristics shall be as per the
procedure approved by Hon’ble CERC vides order dated 3rd May 2013. All generators as well HVDC
were advised to calculate their response as per the described procedure during the meeting.(Ref:
CERC order in Petition No. 47/MP/2012). SLDCs were advisedto report the frequencyresponse of
intra-State generators to the concerned SERCs. (Ref: CERC order in Petition No. 84/MP/2015).
8. A generator response which is minimum 40% of ideal FRC is to be considered as adequate response.
(Ref: 9.6 (b) of Report of Expert Group to review and suggest measures for bringing power
system operation closer to National Reference Frequency).
9. The MW and frequency data available at station DCS shall be archived at a resolution of at least 1
second, for post-facto analysis of the adequacy of the response.
All the station representatives stated that the gap in understanding the provisions of the grid code had been
addressed through the deliberations in the meeting. They assured that the governor settings would be re-tuned
in the next few days to provide the response expected as per the IEGC 5th amendment. All the generating
utilities updated the latest status and their action plan which is enclosed at Annexure-IA.
The two frequency response events, which occurred in the month of January 2019, were also informed by
ERLDC to all generators. It was decided that all generators would submit high resolution (1 sec) data of MW
output, Frequency (Hz), and RGMO influence in MW (if available) along with FRC calculation and suitable
explanation of response by 4th Feb 2019 to erldcprotection@posoco.in and erpcprotection@gmail.com.
Events Date and Time:
After detailed deliberation, the following decisions were taken in the meeting:
1. All the generators would take necessary tuning of their units along with the Boiler logic to provide
adequate RGMO/FGMO response
2. Generator which cannot provide automatic response should operate on FGMO with manual
intervention
3. All the generators would address the issues related to implementation of RGMO/FGMO during R &
M works immediately.
4. All the generators shall calculate the RGMO/FGMO response for the events informed by ERLDC.
5. All the generators shall submit the high resolution data to SLDC and ERLDC for computation of the
response.
6. The status of implementation of RGMO/FGMO and the performance of the generators shall be
reviewed in monthly OCC Meetings.
ERLDC gave a detailed presentation on role of Power System Stabilizer and the importance of its tuning.
Presentation is enclosed at Annexure-II. ERLDC explained the following during the PSS Tuning Session:
1. Low frequency oscillation and its adverse effect on the grid as well generating plants
2. Basics of PSS tuning, PSS Tuning Requirement as per Regulation/Standards
3. Criteria for PSS tuning and analysis of PSS tuning.
4. Exciter, PSS Data and its tuning details as received from various generators (Annexure-II A)
5. Analysis of PSS tuning field reports submitted by the various generators (Annexure-II B)
6. Need for Model data submission from generators and its utilization
After detailed deliberation, the following decisions were taken in the meeting:
1. Generators who had already done the PSS tuning shall submit the details of the Excitation System,
PSS tuning and its report as per the list attached at Annexure-II A. The generators shall submit the
Generator terminal voltage, Field voltage, Real power, Reactive Power, Generator Speed, and PSS
output in excel/.csv format for better analysis of the result.
2. Generators for which PSS tuning was not carried out shall take up the PSS Tuning with OEM
immediately
3. Generators for which PSS was not in service shall take up the issue with OEM immediately to bring
the PSS into service.
4. For any future tuning, it was recommended to all generators to collect the response along with data in
.csv/excel format.
5. All the generators where the PSS tuning was done and PSS not in service shall submit their action plan
for PSS Tuning in line with IEGC and CEA standards before the next OCC meeting to
ERPC/ERLDC.
***********
Annexure-I
Delta f = 0.13 Hz
Droop = 5% , MCR = 1000 MW
Ideal Response = (0.13/50) x (100/5) x 1000=52 MW
Actual response = 42 MW = Delta P observed
Actual response as % of Ideal Response = 80 %
Delta f = 0.13 Hz
Droop = 5% , MCR = 500 MW
Ideal Response = (0.13/50) x (100/5) x 500 = 26 MW
Actual response = 22.9 MW = Delta P observed
Actual response as % of Ideal Response = 88 %
RGMO was out of service for unit 1, 2 & 3 and unit 5 was out of service
Unit 2 & 3 were out of service * Based on data received from TSTPP
Barh
Barh generation Actual response
Frequency Change after the as % of Ideal
Event No Date Time
Change Event(As per Response(Assu
ERLDC SCADA) ming 5 % Droop)
Event-1 23-04-18 10:42 0.287 Hz Dip 2.82 4%
Event-2 06-05-18 16:50 0.055 Hz Dip -1.1 -4 %
Data not Updating at Data not Updating
Event-3 10-05-18 06:11 0.054 Hz Dip
ERLDC at ERLDC
Data not Updating at Data not Updating
Event-4 10-07-18 08:14 0.062 Hz Dip
ERLDC at ERLDC
Event-5 30-07-18 20:48 0.071 Hz Dip 0.169 0%
- 6.4 (Ramp Down in
Event-6 06-08-18 13:06 0.13 Hz Rise 27 %
Units going on)
- 9.35 (Ramp Down
Event-7 07-08-18 14:17 0.035 Hz Dip -58 %
in Units going on)
Event-8 29-08-18 04:02 0.056 Hz Dip - 0.23 -1 %
Event-9 30-10-18 19:23 0.19 Hz Dip 2.75 4%
Event-10 16-01-19 12:25 0.05 Hz Dip -0.2 -0.7%
01-Feb-19 (c) POSOCO 34
Barh response on 07th August 2018 at 14:17 hrs
50 Hz
Negative Response
from the Unit
50 Hz
No Response
Units at Teesta III was not in RGMO/FGMO before 06-12-2018. During Event on 16-01-18 , units
at Teesta III were not in service. * Based on data received from Teesta III
RGMO out of service due to low generation of RGMO out of service due to low generation of
poor coal stock poor coal stock
Frequency response observed in WB control area for this event was 11% of ideal response
(Assuming 5% governor droop and 4%/Hz load response)
RGMO/FGMO status:
Generator Name Discussion during the Comments from Time frame and
meeting Generators Action Plan
Farakka Unit 1,2,3 Adequate Response is not The DCS are old and due DCS will be replaced
observed due to old DCS to any faulty card, under R & M activity
system. response is not observed. in the next overhauling
The response will be as per the proposed
intermittent as there is no annual outage plan
facility to provide alarm to approved by ERPC.
real time operator for early
replacement of faulty card
module.
Farakka Unit 4 Response is not adequate The RGMO logic and Fine Tuning of logic
and withdrawal of response ramp down logic after for RGMO will be
is not in line with IEGC. RGMO operation needs completed by end of
Over generation was tuning. March 2019
observed due to which
Primary response margin
was not adequately
available.
Farakka Unit 5 No response has been HP CV 4 is 100 % stuck In the next overhauling
observed so RGMO operation is not (as per the ERPC
proper and desired approved shutdown of
response is not observed. unit), the issue will be
resolved.
Farakka Unit 6 Response is not adequate The RGMO logic and Fine Tuning of logic
ramp down logic after for RGMO will be
RGMO operation needs completed by end of
tuning. March 2019.
Kahalgaon Response is not adequate The new DCS have been NTPC intimated that
1,2,3&4 installed and there is a by 4th Feb 2019 the
need forfine-tuning the fine-tuning activity
RGMO Logic. It was would be completed
informed that Boiler for
the units is not responding
as per the requirement
envisaged response for
FGMO.
Kahalgaon 5,6,7 Unit 5 has provided Need of fine-tuning the NTPC intimated that
oscillatory response. While RGMO Logic for all the by 4th Feb 2019 the
unit 6 and 7 has provided units. fine-tuning activity
poor response. would be completed.
Talcher 1,2 No response Observed The DCS (ABB make) is Fine-tuning of RGMO
very old. During the next is going on and
overhauling, response of expected to be
PSS will be tuned and completed by Next
other issues will be Overhauling.
attended.
Talcher Unit Good Response in Unit 4 Unit 3 Boiler R & M is NTPC intimated that
3,4,5&6 observed while inadequate over and tuning of RGMO by 4th Feb 2019 the
response in other units. is required. fine-tuning activity
For the units 5 and 6 , Fine would be completed.
tuning of RGMO logic is
required.
Barh 4 &5 Based on the submitted NTPC intimated that the NTPC will take up the
plots for events, it has been events will be analyzed matter of data
observed that the units may and fine-tuning will be collection in .csv
be responding during done in the RGMO logic format with their
nominal frequency changes for complying with IEGC. OEM.
in the grid and thus
adequate response has not NTPC will calculate
been observed during the FRC of units for
frequency response events. the last three events
and submit it to
ERLDC by 4th Feb
2019.
Teesta V 1,2,3 Based on the submitted NHPC intimated that they Due to old
plots for different events, it would fine-tune their DCS,NHPC is not able
has been observed that the RGMO logic for to extract the MW and
units may be responding compliance with IEGC. frequency data in .csv
during nominal frequency format. They will take
changes in the grid and thus It was informed by NHPC up the matter with
adequate response has not that during high hydro OEM.
been observed during season they will not be
frequency response events. able to give governor NHPC will calculate
response. However, the FRC of units for
detailed reason could not the recent events and
be provided during the submit to
meeting. ERLDC/ERPC.
BRBCL 1 & 2 Slow Response has been NTPC intimated that they NTPC Intimated that
observed based on the data. would check the reasons tuning of RGMO logic
for the poor response and will be taken up with
action will be taken for OEM.
improving the governor
response.
Teesta 3 1, 2, 3, 4, Response is observed Fine-tuning of RGMO Teesta 3 will be doing
5, & 6 logic will be done. the fine tuning of
RGMO logic and will
intimate
ERLDC/ERPC.
GMR 1, 2 & 3 GMR Units are responding No representative from
however, the response is GMR attended the
slow. meeting.
JITPL 1 & 2 Poor Response has been No representative from
observed. JITPL attended the
meeting.
Adhunik 1 & 2 Response is observed No representative from
however, withdrawal of Adhunik attended the
response is fast. meeting
Dikchu Response is observed but No representative from
slows in nature. Dikchu attended the
meeting.
B. State Generators
Tenughat 1, 2 No details for analysis of TTPS intimated that Unit Tenughat was
Governor Response. 1 is having new DCS intimated to submit the
(Nov’16) so data retrieval data for the events in
is possible as will be order to analyze the
submitted.The unit earlier response of TTPS
was running at de-rated units.
power (160 MW)due to
issues. Presently Unit
overhauling has been
completed however,it is
kept out.
Unstable
Stable
Poorly damped
Source : http://www.meppi.com/Products/GeneratorExcitationProducts/Static%20Excitation%20System/Power%20System%20Stabilizer.pdf
• Additional Input to AVR to improve Damping
Torque.
• Used to minimize real power oscillations by
rapidly adjusting the field of the generator to
dampen the low-frequency oscillations.
• PSS input has appropriate phase and gain
compensation to modulate field voltage such
that torque are generated that are out of
phase causing Low frequency Oscillation.
• Generator output power is • PSS detects the change in
decided by a turbine’s generator output power,
mechanical torque. controls the excitation
• Can be changed by value, and reduces the rapid
transiently changing the power fluctuation
excitation value
Source : http://www.meppi.com/Products/GeneratorExcitationProducts/Static%20Excitation%20System/Power%20System%20Stabilizer.pdf
1. Definition of PSS :
CEA (Technical standards for connectivity to the
Grid) Regulation, 2007: Power System stabiliser
means controlling equipment which receives input
signal of speed, frequency and power to control the
excitation via the voltage regulator for damping
power oscillation of a synchronous machine”.
2. Provision of PSS :
– CEA Technical Standard for Construction of Electrical Plants and Electric Lines
• For Coal or lignite based Thermal Generating Stations (10.2. g.i: )
• For Hydro power Plan (37.3.e)
– CEA (Technical standards for connectivity to the Grid) Regulation, 2007
• For New generating Units (part II. 1. C)
• For Old Units: (part II. 2. 2):
– Standard technical features of BTG system for supercritical 660/ 800 MW
thermal units, CEA, July 2013 (16.2.4.iii.d.5)
– Standard technical specification for main plant package of sub- critical
thermal power project 2 X (500 MW or above), CEA, Sept 2008 (5.2.4.iv)
P=155MW P=155MW
PSS : Off PSS : On
P=242MW
PSS : On
Contingency
Source : NRLDC
Supporting Slides
• Operating with Weak Tie Line at high loading limits.
• Weak Interconnection in the system.
• Generating Plant operating with high angular separation from adjacent
node.
• Generator Control System Software Problem.
• Issue with Governor System for Generating Unit.
• Generator Testing like governor, ramp test(PG test)
• Switching of transmission element causing large voltage change.
• Severe Fault /Delayed Fault clearance.
• Mal-operation of over speed limiting Gear Mal-operation of over speed
limiting gear.
• Emergency stop and control valve issue during operation.
• Generating Unit synchronization and desynchronization.
• etc.
We cannot AVOID/STOP the above reasons
However, We can improve the System Damping
• Tripping of Transmission line/Generating unit on unwanted operation of
protection.
– e.g.: Tripping of APML Tirora Units/JP Nigrie Units
• Wear and tear of Generator Rotor shaft and reducing their life (Hidden
Failures)
• Wear and Tear of Consumer rotating loads and reducing their life (Hidden
Failures)
Local Global
(Intra Area) (Inter Area)
0.2 Hz Phase
Oscillation Opposition
can be
observed.
Source : POSOCO report, Low Frequency Oscillation in Indian Grid
• Here few generators in one area oscillate w.r.t generators in other areas.
• Not all generators in grid participate.
• E.g. 0.56 Hz LFO between Eastern, North Eastern and Western Grid observed
on 9th -11th August 2014.
PSS
IEEE single
PSS in Report
Type of Exciter Model Model PSS input PSS tuned Last PSS
Power Plant Unit No Service Submitted
Exciter and Vendor of Model or (Yes/No) Tuning Date
(Yes/No) (Yes/No)
Exciter dual
input
West Bengal
Kolaghat-
1-3 Static BHEL ST5A PSS 3B Yes No Long Back No
WBPDCL
Kolaghat- ABB Unitrol
4-6 Static PSS 2B Dual Yes No All Unit : 2014 No
WBPDCL 6800
Sagardighi- ABB Unitrol
1,2 Static No No No
WBPDCL 5000
Step Test on
Sagardighi- Unit 3 in 2018
3,4 Brushless BHEL PSS 3B Yes Yes No
WBPDCL and Unit 4 not
done
Unit 5 in
Santhaldih- 2013 and
5,6 Brushless BHEL AC3A PSS 3B No
WBPDCL Unit 6 is not
Tuned
Bandel-
5 Static BHEL No No
WBPDCL
Bakreshwar-
1 Brushless BHEL-Unitrol PSS-3B Yes No No
WBPDCL
Bakreshwar- BHEL-
2,3 Brushless Yes No No
WBPDCL THYRISIEM-04
Bakreshwar-
4,5 Brushless BHEL-Unitrol PSS-3B Yes No No
WBPDCL
Static
Unitrol F 5000
(through
DPL 7 ST1 PSS 2A Dual No No N.A Not App
Carbon
ABB
Brush)
WBS NO
CE/0800-SH8-
DPL 8 Brushless 48-01 ---- UN0662 Dual Yes No No Not App
BHEL
PPSP Site 1,2,3,4 Thyristor Digital Not Not Single Yes No No Not App.
type, full AVRTOSATEX availa availabl
bridge 100, Vendor- ble e
Toshiba
TLDP III 4 x 33
TLDP IV 4 X 44
CESC
R-R Industrial
Budge Budge-
1, 2 Static Controls Dual Yes Yes 29.07.15 Yes
CESC
Limited
Budge Budge-
3 Static BHEL Dual Yes Yes 28.02.10 No
CESC
Yes during
HEL-CESC 1,2 Static Unitrol 5000 ST1A PSS-2A Dual Yes Commissioni 2015 No
ng
DVC
Bokaro -DVC 500 MW Brushless Yes No No
3 X 210
Bokaro No
MW
Yes during
Mejia-DVC 4 STATIC BHEL OTHER Dual Yes Commissioni No
ng
Yes during
Mejia-DVC 5,6 Brushless BHEL OTHER Dual Yes Commissioni No
ng
U7:2010;
Mejia-DVC 7,8 Brushless BHEL OTHER Dual Yes No
U8:2011
Raghunathpur-
1,2 Brushless Unitrol F 5000 ST1A PSS2A Dual No No Not App
DVC
U1: 2012
Durgapur-DVC 1,2 Brushless OTHER Dual Yes Yes No
U2: 2013
Koderma-DVC 1,2 Brushless BHEL Dual Yes Yes No
Waria 4 No
2 X 250
Chandrapura B No
MW
ISGS
U1: Dec 2017;
Kahalgaon Semi-
1,2,3 ABB 6800 Dual Yes Yes U2: Apr 2016; Yes
NTPC Static
U3 : Sept 2016
Kahalgaon Semi-
4 BHEL Dual Yes Yes U4: May 2015 Yes
NTPC Static
U 5 & 6 : Jan
Kahalgaon
5,6,7 Brushless BHEL Dual Yes Yes 2009; Yes
NTPC
U7:July 2010
All units : Jan
Farakka NTPC 1,2,3 Static BHEL Dual Yes Yes No
2008
All units : Jan
Farakka NTPC 4,5 Brushless Siemens Dual Yes Yes No
2008
Farakka NTPC 6 Brushless BHEL Dual Yes Yes Jan 2011 No
Talcher Stage 2 3,4,5,6 Brushless BHEL Dual Yes Yes Yes
Talcher Stage 1 1,2 Yes No
Nabinagar
1
NPGC
BRBCL 1,2,3
KBUNL 1,2,3,4
ALSPA P320
Teesta V 1,2,3 Static ST7B PSS2A Dual Yes Yes 2008
Alstom
Rangit 3 x 20
IPP
Teesta-III 1,2,3,4,5,6 Static Thyne 5 , ELIN PSS2A Dual Yes Yes 2017 Not App
ALSPA
Static CONTOGEN
Unit No. IEEE
Jorethang Excitatio V3 P320 AVR, PSS2A Dual Yes Yes Sept. 2015 Yes
1,2 421.5
n System VENDOR -
ALSTOM
With Unit 2
Tashiding 1,2 Unitrol 6080 PSS2B Dual Yes Yes 16 Oct 2017
Brushes Submitted
Chuzachen P320 AVR,
1,2 Static ST7B PSS2A Dual Yes Yes 26.04.2013 Yes
HEP ALSTOM
AC7B,ALSTO PSS2A/
Dikchu 1,2 Static AC7B Dual yes yes 11/02/2017 -
M 2B
Maithon 1,2 EAR 50/15- BHEL Dual Yes Yes 2017 -
Power Limited 30/8-3 BHEL EDN747
ESST1 040028
Brushless A 1
IEEE U-1
ADHUNIK 1,2 Brushless ST5B PSS2B Dual YES Yes No
421.5 (21/1/13),U-
2(21/5/13)
2016 : Both
JITPL 1,2 Brushless BHEL Dual Yes Yes Yes
Units
GMR
Orissa
Unit 1 May
Model: 2011 ; Unit 2
IB TPS 1,2 Static Unitrol 5, ST5B PSS2B Dual Yes Yes Jan 2012; Done Not App
Vendor:BHEL during DAVR
Commissioning
Upper
1,2,3,4
Indravati
Balimela 6 X 60
Balimela 2 X 75
Upper Kolab 4 X 80
Rengali 4 X 50
Sterlite 4 X 600
Jharkhand
Tenughat 1,2
Subarnrekha 2 X 65
Bhutan
Tala 6 X 170
Chukha 4 X 84
Updated on: 31-01-19
Annexure-IIB
Intra
Oscillation Oscillation Whether PSS is Whether
Plant Step Size Year of
Name of the Unit periodwith period effective as per step Recommended
Mode of Uref Tuning
out PSS with PSS response test for Tuning
(Hz)
Kahalgaon Unit 1 3% 3 cycle 1 cycle Yes 2017 Yes after Bus
Split
Kahalgaon Unit 2 1.5 Hz 3% 3 cycle 1 cycle Yes 2016 Yes after Bus
Split
Kahalgaon Unit 3 6% - - Provided picture not 2016 To be decided
clear to analyze after
response explanation by
NTPC, Also
after bus split,
returning is
required
Kahalgaon Unit 4 1.876 3% 5 cycle 3 Cycle Yes 2015 Yes after Bus
Split
Kahalgaon Unit 5 4% No Appreciable 2009 To be decided
Response after
Kahalgaon Unit 6 4% No Appreciable 2019 explanation by
Response NTPC, Yes after
Kahalgaon Unit 7 2% Provided picture not 2010 Bus Split
clear to analyze
response
Teesta V Unit 1 2% 5 cycle 2 cycle Yes 2008 Yes in view of
Teesta V Unit 2 2% 5 cycle 1 cycle Yes 2008 changes in
Teesta V Unit 3 2% 5 cycle 1 cycle Yes 2008 network
Talcher Unit 3 3% - - PSS is showing response NTPC may
but active power plant is explain the
not providing details after
appreciable change. which
requirement of
retuning to be
decided.
Talcher Unit 6 3% 3 cycle 2 cycle Yes
Budge Budge 1 2% 5 cycle 1 cycle Yes (Tuned for various 2015 No
contingency)
Budge Budge 2 2% 5 cycle 1 cycle Yes (Tuned for various 2015 No
contingency)
JITPL Unit 1 5% - - No Appreciable 2016 JITPL to
Response explain the
response
JITPL Unit 2 5% - - No Appreciable 2016 based on
Response which it will be
decided.
Chujachen Unit 1 2% 6 cycle 1 cycle Yes 2013 Yes in view of
changes in
Chujachen Unit 1 2% 6 cycle 1 cycle Yes 2013 network
Tashiding Unit 2 1.5 Hz 4% 5 Cycle 1 Cycle Yes 2017 Yes in view of
changes in
network
Annexure Plots:
1. Kahalgaon Unit 1