10/11/2014
1 Highlights
2 HSSE
3 Operations (TOA)
Flared Gas 115490 SCM 4,08 MMSCF 5646472 SCM 199,40 MMSCF
25000
20000
15000
Water Injection
Oil Production
Flared Gas PFC
10000
5000
0
13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct
b. Wells
Page 2 / 7
ASHTART
10/11/2014
c. Process
TEG unit:
- Preventive instrumentation visit ongoing: change of control valves, SDV and
transmitters ongoing.
- Internal visit of different capacities and pipes ongoing.
- Spading the contactor V1910/V1900. Preparations for hydraulic test.
- Thickness measurement and visual inspection of V1910 and V1900 in
presence of an accredited organism: OK.
- Hydraulic test of V1910 and V1900 unsuccessful: leak at 155 bars on spades
inter-capacities.
- Replacement of the level indicator LG3982 of D1920 and LG3980 of D1910.
Dismantling, maintenance and control of the pressure transmitters PT3944,
PT3945 and PT3922.
- Calibration of temperature transmitter. Replacement of PCVs (D1920 &
D1910).
E3960:
- Rehabilitation, mounting and cabling the level switch.
- Filling with TEG (39 drums).
- Replacement of broken jars, maintenance of ADF control box, control and
calibration of safety ON/OFF pressures of the immerged heaters.
- Seal test of the serpentine with N2 up to 133 bars: OK. Powering the heater
Page 3 / 7
ASHTART
10/11/2014
Page 4 / 7
ASHTART
10/11/2014
d. Water injection
ASH13: installation of the new flow line ongoing.
P1005A/B/C: weekly lubrication guide.
Z700C:
- Removal and lifting the old crank shaft out of the package.
- Montage à blanc des paliers principaux, serrage au couple, métrologie
et contrôle dimensionnel, contrôle par ressuage (penetring test) des
supports des paliers au niveau demi-bâti inferieur RAS.
- * Z 700C : Montage vilebrequin, coussinets des paliers et butée.
- * Z 700C : Serrage au couple des paliers principaux et relevé des jeux du
vilebrequin, freinage des vis de fixation chapeaux des paliers, nettoyage
à fond bloc cylindre.
- * Z 700C: Montage du bloc moteur.
- * Z 700C: Serrage au couple de 400N.m du bloc moteur.
* NNP100X : Suite de la visite préventive de l'armoire de protection
indirecte : nettoyage de l'armoire et contrôle, réglage des relais CEEE.
* NNP100X : Fin de la visite préventive de l'armoire de protection indirecte
nettoyage de l'armoire et contrôle, réglage des relais CEEE.
PF3: replacement of lights out of service and rehabilitation of normal and
emergency lighting circuits.
IFR II: vibration control campaign on the machinery.
Z2700: rehabilitation of ESDV2712 (drainage valve of the 1st stage). Clean-up of
the inlet diesel sandwich filter. Replacement of the BP diesel filters due to high
differential pressure.
GES 700KVA: connection of power and control cables. Connection of fire and gas
Page 5 / 7
ASHTART
10/11/2014
safety cables.
NNP 100: start of the E2 preventive visit for the distribution panel 380 V.
maintenance of the breaker of the network looping (case 32 & 52).
Batteries PF1 & PF3: start of the E2 preventive visit; clean-up, density control and
voltage measurement.
IFR II: inert gas central N°2: removal of the diesel motor for reparation.
IFRIKIA II:
* Electricité / Instrumentation:
- Alimentation en autonome de deux groupes en parallèle 470KW-50,5HZ.
- Retour alimentation de PFC 14h30.
IFRIKIA II:
* Mécanique:
- Electropompe incendie n°1 : Visite E1 pompe incendie principale.
* Electricité / Instrumentation:
- Tableau de distribution n°1 : Reprise visite : Entretien départ différents
tiroirs.
- Entretien et charge batteries 12gv pour remplacement sur PCII.
- Réparation fuite sur compresseur climat n°2.
- Vérification du bon fonctionnement du climat n°1.
IFRIKIA II:
* Mécanique:
- Unité Climat n°2: Réparation par soudure conduite séparateur huile,
entretien des filtres intérieurs, etanchement fuite capote extérieur de
l'unité, appoint fréon et réglage des paramètres.
* Electricité / Instrumentation:
- Tableau de distribution n°1: Suite de la visite, entretien départ
différents tiroirs.
- Frigo Vivre: Recherche défaut non fonctionnement du compresseur n°1.
- Climat n°2: Etanchéité de la centrale de climat n°2,
fin réparation fuite huile compresser et mise en marche.
IFRIKIA II:
Page 6 / 7
ASHTART
10/11/2014
* Mécanique:
- Equipement IFRIKIA: Prélèvement échantillons d'huiles des machines
IFRIKIA selon OT.
* Electricité / Instrumentation:
- Tableau de distribution n°1: Suite de la visite, entretien départ
différents tiroirs.
- Frigo vivre: Fin recherche défaut non fonctionnement du compresseur
n°1, relai temporisé 10T HS.
- Conduite des installations frigorifiques.
Page 7 / 7