EAST COAST RAIL LINK

PROJECT

SUPERVISING CONSULTANCY
WEEKLY REPORT BY AECOM
PACKAGE 2 (SECTION 5)
(JUNE 4th TO JUNE 10th 2020)

China Communications Construction Company


SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 2 of 34

SC – Section 5
Weekly Report # 45
(AECOM)

Document No : 2020-Weekly-45
Revision : Rev 00
Date of Issue : [25-07-2019]

Prepared by Reviewed by Approved by

Kamarul Azman Abd Ir. Cheng Kim


Name Name Vincent Kew Name
Ghaffar Bong

Section Engineer Package Chief


Position Position Section Leader Position
Supervisor
Contents

1 SUPERVISION MAIN ACTIVITIES 4

(MAIN DESCRIPTION OF MAIN ACTIVITIES) 4

2 STAFF MOBILIZATION 8

(GENERAL DESCRIPTIONS OF STAFF MOBILIZATION) 9

3 QA/QC 11
3.1 SITE PATROL AND WITNESS 12
3.2 METHOD STATEMENT 13
3.3 INSPECTION LIST 14
3.4 PROBLEM AND RECTIFICATION 14
3.5 QUALITY INSPECTION AND ACCEPTANCE LIST 15
3.6 MATERIAL SUBMISSION APPROVAL 15
3.7 N0N CONFORMANCE REPORT 15
3.8 RAW MATERIAL INSPECTION 16
3.9 QUALITY ACCIDENT AND DISPOSAL 16

4 HSE 17

4.1 GENERAL INTRODUCTION 18


4.2 SPECIAL WORKERS STATISTICS 18
SPECIAL WORKERS STATISTICS TABLE 18

5 MAIN PROBLEMS AND SOLUTIONS 19

5.1 MAIN PROBLEMS & SOLUTIONS 20

5.2 QC ISSUE & SOLUTION 21

6 OTHERS 25

6.1 GENERAL 26
6.2 SUMMARY OF OFFICIAL LETTERS AND SPECIAL MEETING 26
6.3 PROJECT PHOTOS 27

7 MAIN WORK NEXT WEEK 33


SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 4 of 34

1 SUPERVISION MAIN ACTIVITIES


(Description of Main Activities)

➢ Method Statements (MS; 1 nos) submitted by Section 5 during this period of reporting

• Method Statement for Foundation (piling & pile cap) for TNB Pylon Relocation (CH231+600)

➢ Attend to Request for Inspection (RFI; 52 nos) submitted by Section 5 during this period of reporting.

• Site 4 Inspection for relative crown settlement, piezometer, inclinometer & horizontal relative
clearance change surveying data record from May 31, 2020 June 06, 2020 of Kuantan Tunnel

• Site 3 Inspection for ground settlement, crown settlement, and horizontal relative clearance change
surveying data record from May 31, 2020 June 06, 2020 of Kuantan Tunnel

• Inspection for permanent lining (ø100 PVC Transverse Penstock, water swelling water stop, back
sticking waterstop,2M wide waterproof board & nonwovens) of inverted arch for Kuantan Tunnel at
CH310+069

• Site 3 Inspection for casting concrete of Kuantan Tunnel central drainage ditch from CH310+069

• Site 3 Inspection for casting concrete of Kuantan Tunnel central drainage ditch from CH310+079.85

• Site 3 Inspection for setting out and excavation of bench part 1 (CH310+131), R part 2
(CH310+125.5), L part 2 (CH310+122), R part 3(CH310+100.5), L part 3(CH310+099) at Kuantan
Tunnel

• Site 3 Inspection of setting out and excavation of inverted arch of kuantan tunnel at CH310+079.85

• Site 3 Inspection Permanent Lining (Steel Mesh, Formwork, Concrete) of Inverted Arch & Invert
Arch Filing at CH310+079.85

• Inspection for primary support (initial shotcrete, steel arch, steel mesh, lock foot anchor pipe
installation & grouting shotcrete) bench part1(CH310+131), R Pt 2(CH310+125.5), L Pt
2(CH310+122), R pt3(CH310+100.5), L pt 3(CH310+099)

• Site 3 Installation and grouting for Ф42mm Double layer advanced small pipe from CH310+132 of
Kuantan Tunnel
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 5 of 34

• Inspection for permanent lining (ø100 PVC Transverse Penstock, water swelling water stop, back
sticking waterstop,2M wide waterproof board & nonwovens) of inverted arch for Kuantan Tunnel at
CH310+079.85

• Site 4 Kuantan Tunnel Inspection for casting concrete central drainage ditch from CH312+743-
CH312+731

• Site 4 Inspection for setting out and excavation of bench part 1 (CH312+655.032), L pt 2
D6(CH312+655.032), R pt 2 D6 (CH312+655.032), L pt 2 D3(CH312+720.8), R pt 2(CH312+706.4)
at Kuantan Tunnel

• Site 4 Inspection of setting out and excavation of inverted arch for kuantan tunnel at CH312+731 -
CH312+719

• Site 4 Inspection Permanent Lining (Steel Mesh, Formwork, Concrete) of Inverted Arch & Invert
Arch Filing at CH312+731-CH312+719

• Inspection primary support (initial shotcrete, steel arch, steel mesh, lock foot anchor pipe
installation, grouting shotcrete) bench pt1(CH312+655.032), D6[L pt2(CH312+655.032), R
pt2(CH312+655.032)], D3[L pt2(CH312+720.8), R pt2(CH312+706.4]

• Site 4 Installation and grouting for Ф42mm Double layer advanced small pipe from CH312+655 of
Kuantan Tunnel

• Inspection for permanent lining (ø100 PVC Transverse Penstock, water swelling water stop, back
sticking waterstop,1M wide waterproof board & nonwovens) of inverted arch for Kuantan Tunnel at
CH312+731-CH312+719

• Installation & grouting for Ø25mm radial anchor at CH312+676.2 of Kuantan Tunnel (The
longitudinal spacing of radial anchor bolt is 1.2m)

• Site 4 The advanced tunnel geological forecast at CH312+655-CH312+625

• Inspection for excavation to formation, laying geotextile separator and replacement sand (45cm)
both side from CH254+300-CH254+930

• Inspection for formation level at CH254+300-CH254+930 both side (630m)

• Inspection for filling material of working platform, top level of working platform and mackintosh
probe test at CH235+950-CH236+160 (210m)

• Inspection for Setting Out & Installation of PVD at CH235+431-CH235+640 both side (209m)

• Inspection for second layer of filling material at CH257+180-CH287+420 both side (240m) (300mm)

• Inspection for first layer of compacted filling material (300mm) and compaction test at CH256+060-
CH256+080 side (20m)
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 6 of 34

• Site 3 Inspection for ground cutting works from CH309+513-CH309+720 (3th slope -right side) &
CH309+550-CH309+700(3th slope-left side)

• Inspection for site clearance and site removing trees at CH308+260-CH310+540 both side (280m)

• Appearance & Liquid Penetrate Test for Steel Arch at Site 3 Fabrication Yard

• Appearance & Liquid Penetrate Test for Steel Arch at Site 4 Fabrication Yard

• Site 4 Cement Test (Soundness,2d & 28d compressive strength, standard of consistence, initial
and final setting time) of YTL Cement (I 42.4 N & II 52.5N)

• Site 3 42.5N Cement Test (Soundness,2d & 28d compressive strength, standard of consistence,
initial and final setting time) of YTL Cement

• Soil field (CH254+030 (500m left)) 1. Compaction test 4.5kg Rammer Method 2.Particles Sizes
Distribution 3.Liquid Limit, Plastic Limit & Plasticity Index

• Sampling and testing of rebar at Site 1: 20mm & 32mm steel bars (Tensile Test & Bending Test)

• Site 1 Site access of material, Sampling & testing for fine aggregate [1. grading 2.Clay,silt,dust] of
Silver system (quantity :500t)

• Inspection of Site 2 Batching Plant

• Inspection for removing of existing culvert at CH264+067, CH264+600

• Inspection for fabrication and installation of reinforcement cage, Installation of steel casing, drilling
of bore hole, base cleaning and pouring concrete for Pile No. 1 Pile Cap No 04 Bridge 14

• Inspection for fabrication and installation of reinforcement cage, Installation of steel casing, drilling
of bore hole, base cleaning and pouring concrete for Pile No. 4 Pile Cap No 04 Bridge 14

• Inspection for fabrication and installation of reinforcement cage, Installation of steel casing, drilling
of bore hole, base cleaning and pouring concrete for Pile No. 4 Pile Cap No 05 Bridge 14

• Inspection for fabrication and installation of reinforcement cage, Installation of steel casing, drilling
of bore hole, base cleaning and pouring concrete for Pile No. 1 Pile Cap No 05 Bridge 14

• Inspection for fabrication and installation of reinforcement cage, Installation of steel casing, drilling
of bore hole, base cleaning and pouring concrete for Pile No. 1 Pile Cap No 06 Bridge 14

• Inspection for fabrication and installation of reinforcement cage, Installation of steel casing, drilling
of bore hole, base cleaning and pouring concrete for Pile No. 4 Pile Cap No 06 Bridge 14

• Inspection for fabrication and installation of reinforcement cage, Installation of steel casing, drilling
of bore hole, base cleaning and pouring concrete for Pile No. 7 Pile Cap No 06 Bridge 14

• Inspection for setting out, steel casing level and pile location of Pile No.4, Pile Cap No 6 Bridge 14
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 7 of 34

• Inspection for setting out, steel casing level and pile location of Pile No.1, Pile Cap No 6 Bridge 14

• Inspection for setting out, steel casing level and pile location of Pile No.7, Pile Cap No 6 Bridge 14

• Inspection for setting out, steel casing level and pile location of Pile No.1, Pile Cap No 4 Bridge 14

• Inspection for setting out, steel casing level and pile location of Pile No.4, Pile Cap No 4 Bridge 14

• Inspection for setting out, steel casing level and pile location of Pile No.1, Pile Cap No 5 Bridge 14

• Inspection for setting out, steel casing level and pile location of Pile No.4, Pile Cap No 5 Bridge 14

• Inspection for removing trees and site clearance of original ground at CH233+220.175-
CH234+726.075 (Bridge 09)

➢ Material Submission Approval (MSA; 2 nos) from CCCC HQ or Section 5 submitted in this reporting
period.

• MSA for High Polymer Modified Bitumen Waterproofing Membrane & Primer & Polyurethane
waterproof coating

• MSA for Round Bar (50mm)


SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 8 of 34

SECTION 2
STAFF MOBILIZATION
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 9 of 34

2 STAFF MOBILIZATION
Section Discipline Mobilization
Name Position Remark
Date
Package Chief Section 5 &
1) Ir. Cheng Kim Bong 28th May 2019
Supervisor Section 6
Demobilized to Section
2) Mohd Naserddin Bin Dari Section Leader Section 5 1st June 2019
6 on 09/06/2020
3) Mohd Hisyamuddin Bin
Section Engineer Section 5 1st June 2019
Muhammad Nor
4) Kamarul Azman Bin Abdul
Section Engineer Section 5 1st July 2019
Ghaffar

5) Zulkefli Bin Muhamad Package Secretary Section 5 15th July 2019

6) Irai Asmurni Remeli Section Clerk Section 5 15th Aug 2019


7) Mat Ropi Bin Saman Sr Inspector of Work Section 5 3rd Sept 2019
8) Ahmad Rizal Bin Mohd
Sr Inspector of Work Section 5 29th Oct 2019
Noor
9) Eric Ong Kin Being Section Sr. Engineer Section 5 11th Nov 2019
10) Mohd Noor b Awang Inspector of Work Section 5 18th Nov 2019
11) Tsau Nyok Kong Sr Inspector of Work Section 5 2nd Dec 2019
12) Muhd Zarizam b Ismail Sr Inspector of Work Section 5 16th Dec 2019
13) Nik Herryfazeli b Nik
Section Engineer Section 5 6th Jan 2020
Mokhtar
14) Ummu Hatikah Najwa Section Clerk Section 5 6th Jan 2020
15) Badrul Hisham Section Sr. Engineer Section 5 24th Feb 2020
16) Vincent Kew Section Leader Section 5 24th Feb 2020
17) Mohd Rizal Abdullah Section Engineer Section 5 16th Mar 2020
18) Mohd Rizalman Inspector of Work Section 5 1st June 2020
19) Mohd Sahir Ghazali Inspector of Work Section 5 1st June 2020
20) Mohd Kamarul Bahrin Sr Section Engineer Section 5 1st June 2020
21) Mohd Sazalie Ramlee Section Engineer Section 5 1st June 2020
22) Ahmad Zafi Mohd Inspector of Work Section 5 1st June 2020
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 10 of 34

Mobilization Plan

Name Proposed Position Work Zone Discipline Proposed Date Remark

1) Arshad Ali Inspector of Work Section 5 15th June 2020

Note: The above proposed SC Manpower Mobilization dates are based on Section 5 CCCC priority works.
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 11 of 34

SECTION 3
QA/QC
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 12 of 34

3 QA/QC
3.1 Site Patrol and Witness
There were 52 RFIs received for Section 5 during this reporting period.

Inspection and witnessing by relevant SC staffs were performed according to the RFI’s raised.

Site patrols were happened by SC-senior regularly wherever activities going on as needed.

Once per week (Section Leader)


Once half month (Deputy PCS)
Once per month (PCS)

Routine Package Chief Supervisor; PCS and Section Leader; SL site patrol to Kuantan Tunnel (exit),
site discussion with SC’s, Section 5 QAQC and Section 5 Tunnel Team

Section Leader; SL site patrol to Site 1 and Site 2 on 8th June, 2020 to check bored pile works at
Bridge 14, PVD at CH 256.080, laid geotextile for PVD works at CH 258.900 and temporary road
diversion at existing bridge demolition site CH 269
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 13 of 34

The arrangement on SC supervision scope divided into site-1; site-2; site-3 and site-4 for
Section-5 as below:
Site Office 2 (base-camp & BP#2),

--- Senior Section Engineer (SSE: two nos) - to in charge of Site 2 overall supervision and tunnel works.
Another one new SSE joint on 1st June 2020 to in charge of Site 1 overall supervision works.

--- Section Engineer (SE: two nos) - to supervise Site 1 & Site 2 respectively. Another one new SE joint
on 1st June 2020 to assist on Site 2

--- Senior Inspector of Work (SIOW: one no) - to supervise Site 1. Another one new IOW joint on 1st
June 2020

--- Inspector of work (IOW: one no) - to supervise Site 2. Another one new IOW joint on 1st June 2020

Scope of works involved RFI, laboratory work, PVD installation, R&R, embankment, DSM, site
clearance and bridge demolition works and bridge piling works.

Site Office 3 (BP#3)

--- Section Geotechnical Engineer (SGE: one no) - to in charge of overall tunneling works.

--- Section Engineer (SE: two nos) - to supervise Site 3 & Site 4 tunneling and subgrade works.

--- Senior Inspector of Work (SIOW: three nos) - to supervise tunneling works (two-shift) and subgrade
works. Another one new IOW joint by 1st June 2020 to assist supervision tunnel works

Scope of works involved RFI, laboratory work, tunneling works, infra works, earthwork, site clearance.

3.2 Method Statement (MS) List

Detail of submission Method Statement for Section 5:


Receiving Feedback Comments (Code
No. Item Remarks
Date Date 1&2&3)

Method Statement for


Pending
Foundation (piling & pile
1 10/06/20 - - Review
cap) for TNB Pylon
(Rev 00)
Relocation (CH231+600)
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 14 of 34

Summary of Method statement for Section 5:


Submitted Code 1 Code 2 Code 3 Pending Review

1 - - - 1

3.3 Inspection List

No. Item Quantity First Pass Yield Disqualification Disposal

1 Tunnel - Portal 20 1

2 Viaduct 0 0

3 Earthwork 9 0

4 Concrete Related Item 2 0

5 Other Material 5 0

6 Plant and Equipment 1 1

7 Bridge 15 4

8 Drainage 0 0

TOTAL 52 6

3.4 Problem and Rectification

No major problem identified during this reporting period.

(Please refer Section-5: Main problems and solution)


SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 15 of 34

3.5 Quality Inspection and Acceptance List


Section Item Quantity First Pass Yield Disqualification Disposal

Material
5 0
Testing
Section 5
Concrete Cube
2 0
Test

3.6 Material Submission Approval (MSA) List

Receiving Feedback
No Item Code Remarks
Date Date

MSA for High Polymer


Modified Bitumen Pending
1 Waterproofing Membrane & 05/06/2020 - - Review
Primer & Polyurethane (Rev 00)
waterproof coating

Pending
2 MSA for Round Bar (50mm) 06/06/2020 - - Review
(Rev 00)

3.7 Non-Conformance Report

Issuance Closure
No Item Remarks
Date Date

Kuantan Tunnel rock slippage due to wedge failure


1 at CH 312 + 655.03 to Ch 312 + 653.7 not follow 10/06/2020 - -
IFC drawing
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 16 of 34

3.8 Raw Material Inspection


As above

3.9 Quality Accident/Noncompliance and Disposal


No quality noncompliance observed on site during this reporting period.
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 17 of 34

SECTION 4
HSE
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 18 of 34

4 HSE
General Introduction
The project was located at Chukai, Kemaman and was registered with DOSH Pahang
PH/17/03/114976 (CH275+780 Cherating to CH313+500 Kuantan) and DOSH Terengganu
TG/17/03/117030 (CH229+500 Kerteh to CH275+780 Binjai)

The alignment of the project ECRL as approved in the schedule 2A EIA (REF: JAS
50/013/602/007(31) dated 20th Jun 2017.

Special Workers Statistics


Description Actual this Cumulative Cumulative to
month last month date
A. Construction
Man-hours Worked * 118,536.00 835,456.00 953,992.00
Number of Lost Time Injury (LTI's) - - -
Number of Lost Workdays (LTI's) - - -
LTI Frequency - - -
LTI Severity - - -
Number of Restricted Work Incidents (RWI's) - - -
Number of Medical Treatment Incidents (MTI's) - - -
Number of First Aid Treatment Incidents (FTI's) - - -
Number of Minor Fire Incidents - - -
Number of Property Damage Incidents - - -
Total Recordable Case Frequency (TRCF) - - -
Number of Near Misses - - -

B. Office Support
Man-hours worked - - -
Number of lost Time injury (LTI’s) - - -
Number of Lost Workdays (LTI’s) - - -

GRAND TOTAL MANHOURS 118,536.00 835,456.00 953,992.00


SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 19 of 34

SECTION 5
MAIN PROBLEMS AND SOLUTIONS
5 MAIN PROBLEMS AND SOLUTIONS
5.1 Main Problems:
1) Limited transport for SC Staff mobilization to supervise the increasing number of works at site.

2) Wi-fi/Internet connection not stable & weak/insufficient

3) CCCC failed to provide construction record as soon as work done for SC to sign off

4) Starting from 12th May 2020 SC staff started partially WFH and WFO in SC cabin-office cause of insufficient office spaces.

5) To follow MOH-SOP; worker/Staff resume to work must be gone through Health-screening.

Solution:
1) CCCC to provide additional pick-up for SC staff.

2) CCCC to make sure smooth Wi-fi/Internet connection

3) CCCC to prepare & submit the construction record as soon as work done for SC to sign

4) SC staff to make sure basic PPE to be there and keep social-distancing.

5) All SC staff have already gone through Health-screening.


SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 21 of 34

5.2 QC Issues and Solution Lists:

NO BEFORE AFTER

Ent-tunnel,Poor shotcrete
surface quality at bench part 2 Rectification done with another layer
1 (LHS) CH 310 +116.5 – 121.5 shotcrete

To make sure sub-soil drain in


Using guide alignment to make a sub-
2 straight line at Site 1 PVD
soil drain in straight line
area CH 235
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 22 of 34

NO BEFORE AFTER

To improve/maintain
temporary access road for Improvement temporary access road
3 concreting works after heavy done by using excavator
rain at Bridge 14

To add more signage for notify


heavy vehicle (IN&OUT)
crossing of main existing road
4
(Jalan Batu Putih) near to
CH235+050
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 23 of 34

NO BEFORE AFTER

No proper labelling on the


Labelling done before sending to curing
cube test for concreting bored
5 room
pile works at Bridge 14

Bored pile sludge from Bridge


14 needs to remove from site
Dumping area CH 254+300 at Site 1
6 and dump at the approval
disposal area
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 24 of 34

NO BEFORE AFTER

Honeycomb need to repair in


the invert wall of Kuantan Repair works for honeycomb surface in
7 Tunnel ditch near entrance progress
(north) portal at CH 310 + 069
to CH 310 + 079

8
SECTION 6
OTHERS
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 26 of 34

6 OTHERS
General
An announcement by the Malaysian Government on 16th March 2020; a Movement Control Order (MCO)
starting from 18th to 31st March 2020 to deal with the spread of the Covid-19 under the prevention and
control of Infectious Diseases Act 1988 and The Police Act 1967.

The 5th announcement made on 10th May 2020 to extend the MCO to 9th June 2020.

The 6th announcement made on 7th June 2020 to continue Recovery MCO to 31st August 2020

Summary of Official Letters and Special Meeting

No Reference No Reason Date/Time

1 Bil (09) dlm JKR.CPAB. 100.019/004 Letter of exemption from JKR to allow Kuantan 21/03/2020
Tunnel works to be carried out during MCO which
items with safety concerned.

2 O-00018114 MITI letter to CCCC on Resumption of Work 18/04/2020


During MCO period

3 O-00071055 MITI letter to Aecom on Resumption of Work 25/04/2020


During MCO period

4 SC Meeting via MT Meeting chaired by Mr. KB Cheng agenda on 09/06/2020


site-SHE/QAQC/progress/MCO matters.

5 Training by CCCC via ZOOM Testing of Material & Workmanship 19/05/2020

6 Training by CCCC via ZOOM RFI-Training 21/05/2020

7 Training by CCCC via ZOOM Mass Concrete Temperature Control & Crack 23/05/2020
Prevention

8 Training by CCCC via ZOOM Piling-Section-12 29/05/2020

9 Training by CCCC via ZOOM Method Statement Preparation Training 02/06/2020

10 Internal Training to SC staff Bored pile works, attend to RFI, preparation SC 09/06/2020
Weekly/Monthly Report
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 27 of 34

Supervision Photos

Photo 1 – Drilling bored pile point P4/BP2 (Pile cap No 4 of


bored pile point no 2) of Bridge 14 at Site 1 CH 255 + 264 to
CH 255 + 472

Photo 2 – Preparation PVD platform working area with laying


sand as filter layer at Site 1 CH 235 + 460 to CH 235 + 640

Photo 3 – PVD works at CH 256 + 060 to CH 256 + 080 of


Site 2; area left out from previous PVD works (CH 256 + 060 -
CH 257 + 440) because of transition area and 3 location of
existing demolished culvert area
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 28 of 34

Photo 4 – Geotextile laid for PVD works area at Site 2 CH 256


+ 660 to CH 257 + 120 before start lay sand as filter layer for
PVD works

Photo 5 – Preparation new access road for subgrade area


diverted from existing Petronas rail track alignment at Site 2
CH 265 still in progress

Photo 6 – Preparation access road for subgrade area at Site 3


CH 308 + 200 still in progress near entrance (north) portal of
Kuantan Tunnel
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 29 of 34

Photo 7 – Installation of 1st bench steel arch ribs as primary


support structure at CH 310 + 130.5 to CH 310 + 131 in
entrance (north) portal of Kuantan Tunnel

Photo 8 – Crawler crane, bored pile machine & accessories


for bored pile works on Site 1 Bridge No 9 at CH 233 + 212;
preparation for bored pile works

Photo 9 – Site clearance and preparation platform for


subgrade works at CH 309 + 000 near entrance (north) portal
of Kuantan Tunnel
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 30 of 34

Photo 10 – Berm drain construction at Site 3 CH 309 + 700


(RHS) to CH 259 + 180 near entrance (north) portal of
Kuantan Tunnel

Photo 11 – Demolition existing culvert at Site 2 CH 264 + 067


in progress as approved by local authority (Jabatan Parit &
Saliran; JPS)

Photo 12 – Installation of PVD started at Site 1 CH 235 + 560


to CH 235 + 600
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 31 of 34

Photo 13 – Embankment filling for 2nd layer of PVD area in


progress at Site 2 CH 257 + 140 – CH 257 + 440

Photo 14 – Shotcrete works for bench part 1 near exit (south)


portal of Kuantan Tunnel at CH 312 + 655 – CH 312 + 653.7

Photo 15 – Temporary road diversion for existing bridge


demolition site at CH 269 + 409 to CH 269 + 516 done
premix works. The preparation done to proceed another
bridge span demolishing works
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 32 of 34

Photo 16 – Joint inspection with MRL & QAQC to Batching


Plant Site 2; checking on materials and machineries

Photo 17 – Site visit by PCS & SL to exit (south) portal of


Kuantan Tunnel to check & discuss on tunnel works issue with
respective tunnel teams

Photo 18 – Concreting works in progress for bored pile works


Bridge 14 CH 255 + 264 to CH 255 point A1/BP1 (abutment no
1 (south), bored pile no 1)
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 33 of 34

SECTION 7
MAIN WORK NEXT WEEK
SC Weekly Report DOCUMENT
(AECOM) 2020-Weekly-45
NUMBER
East Coast Railway Link
SC Weekly Report Issue for Client
Revision
Project (June 4th to June 10th) Review

Issued 【2020-06-11】 Page 34 of 34

7 MAIN WORK NEXT WEEK


The following activities are expected to be carried out.

Referred to approval from Ministry of International Trade and Industry (MITI; ref. O-00018114)
on 18th April 2020.
Staff/workers with their names in the list approved by MITI can work during the Enforcement of
Conditional Movement Control Order (CMCO).

A. Kuantan Tunnel works: -

1. Kuantan Tunnel Exit (South) portal – excavation and installation steel ribs for primary support,
inverted arch and permanent lining
2. Kuantan Tunnel Entrance (North) portal – excavation, installation steel ribs for primary support for
bench part 1, 2, 3 and open cut tunnel inverted arch
B. Bridge
1. Bridge No 14 CH 255.264 to CH 255.472
2. Bridge No 9 CH 233.220 to CH 234.737
C. Subgrade Works: -
1. Site 1 – preparation for PVD works CH 235.400 to CH 235.600; sand blanket CH 253.140 – 253.900
2. Site 2 – earth fill layer for embankment CH 256.080 – 257.460; site preparation for subgrade works
CH 260.200 – 260.650, CH 258.700 – 259.120 & CH 274.400 – CH 274.500
3. Site 3 – earthworks for subgrade area preparation works at CH 308 + 160 to CH 309 + 200
4. Site 4 – earthworks at CH 312 + 935 – CH 313 + 900

It is envisaged that the following major activities will be performed by the SC:

• Review of submission from Sections including MS, MSA


• Closure of RFI submitted
• Working from home (WFH) and monitoring of work on site in respect to HSE/QAQC with detail photos
record.
• Attendance of RFI for work on site and photos record of material sampling and testing