BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

PD&T PROJECTS AND TECHNICAL SUPPORT DEPARTMENT


CAPITAL PROGRAM MANAGEMENT

BI-10-02126

REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL

Weekly Progress Report # 12


(Week Ending April 11, 2020)
Revision 00

Prepared by:

Page 1 of 5
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

TABLE OF CONTENTS

1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (APRIL 04, 2020) ........................ 3
1.1 ENGINEERING ................................................................................................................................ 3
1.1.1 PROCESS ........................................................................................................................................ 3
1.1.2 INSTRUMENTATION ...................................................................................................................... 3
1.1.3 PIPING ............................................................................................................................................. 3
1.1.4 COMMUNICATION .......................................................................................................................... 3
1.1.5 STRUCTURAL/CIVIL ...................................................................................................................... 3
1.1.6 ELECTRICAL .................................................................................................................................. 3
1.1.7 FIRE PROTECTION (OSB) ............................................................................................................. 4
1.1.8 CORROSION MANAGEMENT PROGRAM (CMP) ........................................................................ 4
1.1.9 MECHANICAL ................................................................................................................................. 4
2.0. AREAS OF CONCERN ................................................................................................................... 5
3.0. ATTACHMENTS .............................................................................................................................. 5

Page 2 of 5
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (APRIL 11, 2020)

1.1 ENGINEERING

1.1.1 PROCESS

• Provided inputs to PPN scope of work


• Reviewed IDR of PPN scope of work
• Submitted final package to after incorporating QA/QC comments
• Coordination with Sampling vendor

1.1.2 INSTRUMENTATION

• Responding 60% package


• Preparation for HAZOP
• Reviewing MR for Auto sampling skid
• Preparing RFQ for Rockwell PLC

1.1.3 PIPING

• Prepared Final Package and submitted


• SOW reviewed and provided input

1.1.4 COMMUNICATION

• Review and provide inputs in the overall SOW particular in SAES standards, SAEP, SAMMS and other international
standards.
• Review the EIDR for Project proposal narrative (Scope of work).
• Review Documents related to the project.

1.1.5 STRUCTURAL/CIVIL

• Incorporated all comments by other discipline to submit the 60% package


• Continued specifications for Concrete and Structural to be submitted for 90% submittal
• Reviewed Subcontractors preliminary reports such as TOPO and GPR study.
• Continued working on drawings and other documents for 90% submittal

1.1.6 ELECTRICAL

Page 3 of 5
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

• Issued final package


• Incorporate EIDR Comments
• Provide input on PPN

1.1.7 FIRE PROTECTION (OSB)

• Provided inputs to PPN scope of work


• Reviewed IDR of PPN scope of work
• Finalizing the Basis of Design
• Finalizing Technical Specifications for Fire Protection Equipment
• Finalizing coverage drawings
• Finalized and issued 60% package.

1.1.8 CORROSION MANAGEMENT PROGRAM (CMP)

• Developed Materials Selection diagrams and corrosion loop diagrams.


• Attended PRM Session
• Attended CS Session
• Attended LLI Session
• Developed coating map
• Developed CMP report
• Developed Non-Metallic Material Study
• Discipline review completed for 60% Submittal
• Issued EIDR for 60% Submittal
• Incorporated the reviewer’s comments
• Submitted the package for QA/QC
• Responded to Constructability Study, PRM and LLI reports.

1.1.9 MECHANICAL

• Completing 60% package


• Review and providing Input to scope of work
• Replying to TQ # 19
• Reviewing constructability and LLI reports

Page 4 of 5
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

2.0. AREAS OF CONCERN

• There is impact of COVID-19 Safety & Health Measures on the project progress.

3.0. ATTACHMENTS

• Weekly Progress Summary


• Weekly Overall discipline progress
• Weekly Progress Report Details
• Weekly Progress overall S-Curve