BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

PD&T PROJECTS AND TECHNICAL SUPPORT DEPARTMENT


CAPITAL PROGRAM MANAGEMENT

BI-10-02126

REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL

Weekly Progress Report # 28


(Week Ending August 01, 2020)
Revision 00

Prepared by:

Page 1 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

TABLE OF CONTENTS

1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (AUGUST 01, 2020)....................3


1.1 ENGINEERING............................................................................................................................... 3
1.1.1 PROCESS...................................................................................................................................... 3
1.1.2 INSTRUMENTATION..................................................................................................................... 3
1.1.3 PIPING............................................................................................................................................ 3
1.1.4 COMMUNICATION........................................................................................................................ 3
1.1.5 STRUCTURAL/CIVIL..................................................................................................................... 3
1.1.6 ELECTRICAL................................................................................................................................. 3
1.1.7 FIRE PROTECTION (OSB)............................................................................................................ 4
1.1.8 CORROSION MANAGEMENT PROGRAM (CMP)........................................................................4
1.1.9 MECHANICAL................................................................................................................................ 4
2.0. AREAS OF CONCERN.................................................................................................................. 4
3.0. ATTACHMENTS............................................................................................................................ 4

Page 2 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

1.1.1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (August 01, 2020)

1.1 ENGINEERING

1.1.1 PROCESS

 Incorporation of level alarm comment in package


 Incorporation of flushing line E-review comment of manual sampling
 Mark up P&IDs issued for information to disciplines
 Inputs to Piping and instrument for flushing line set up and level alarm
 Resolution on disagreed comments for flushing and level alarm

1.1.2 INSTRUMENTATION

 Responding 90% batch-2 comments


 TBE for second sampling skid Vendor.

1.1.3 PIPING
 Update Mechanical Completion plan
 Response to hot tap bidder
 Mark on Piping drawings to include new Flushing line connection

1.1.4 COMMUNICATION

1.1.5 STRUCTURAL/CIVIL
 Updating the package for Pre-IFB submittal
 Created New Local Level Alarm support and foundation
 Incorporated New Local Level Alarm on Plot Plan
 Coordinated with PE for input to other deliverables

1.1.6 ELECTRICAL

 Finalized and submit electrical DD LOD and MHR estimate.


 Provide input to schedule C document.
 Weekly progress updates.

Page 3 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

1.1.7 FIRE PROTECTION (OSB)


 Review first batch comments
 Weekly progress update

1.1.8 CORROSION MANAGEMENT PROGRAM (CMP)

 Response to SA comments on 90% Package.


 Weekly progress update.

1.1.9 MECHANICAL

 Review vendor quotation


 Input to SOW

2.0. AREAS OF CONCERN

 There is impact of COVID-19 Safety & Health Measures on the project progress.

3.0. ATTACHMENTS
 Weekly Progress Summary
 Weekly Overall discipline progress
 Weekly Progress Report Details
 Weekly Progress overall S-Curve

Page 4 of 4