BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

PD&T PROJECTS AND TECHNICAL SUPPORT DEPARTMENT


CAPITAL PROGRAM MANAGEMENT

BI-10-02126

REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL

Weekly Progress Report # 30


(Week Ending August 15, 2020)
Revision 00

Prepared by:

Page 1 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

TABLE OF CONTENTS

1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (AUGUST 15, 2020)....................3


1.1 ENGINEERING............................................................................................................................... 3
1.1.1 PROCESS...................................................................................................................................... 3
1.1.2 INSTRUMENTATION..................................................................................................................... 3
1.1.3 PIPING............................................................................................................................................ 3
1.1.4 COMMUNICATION........................................................................................................................ 3
1.1.5 STRUCTURAL/CIVIL..................................................................................................................... 3
1.1.6 ELECTRICAL................................................................................................................................. 3
1.1.7 FIRE PROTECTION (OSB)............................................................................................................ 4
1.1.8 CORROSION MANAGEMENT PROGRAM (CMP)........................................................................4
1.1.9 MECHANICAL................................................................................................................................ 4
2.0. AREAS OF CONCERN.................................................................................................................. 4
3.0. ATTACHMENTS............................................................................................................................ 4

Page 2 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

1.1.1.0 WEEKLY PROGRESS REPORT ACTIVITIES WEEKENDING (August 15, 2020)

1.1 ENGINEERING

1.1.1 PROCESS

 Replies for 90% E review comments


 Incorporation of flushing line E-review comment of manual sampling
 Inputs to Piping and instrument for flushing line set up and level alarm

1.1.2 INSTRUMENTATION
 Responding 90% batch-2 comments & closing disagreed comments

1.1.3 PIPING
 Comments response.
 Prepare the IFB package

1.1.4 COMMUNICATION

 No activity

1.1.5 STRUCTURAL/CIVIL

 Responded to SA disputed comments on 90% Package


 Coordinated with Piping for possible solution on Berth-64 Sampler relocation due to crane access
 Coordinated with the Civil Designer for Plot Plan and other drawing updates per 90% comments
 Started revising Civil/Structural IFB package

1.1.6 ELECTRICAL

 Response to SA comments on 90% Package

1.1.7 FIRE PROTECTION (OSB)


 Review first batch comments

Page 3 of 4
BI-10-02126– (REPLACE CRUDE OIL SAMPLERS AT YANBU NORTH TERMINAL)- 530074

 Weekly progress update

1.1.8 CORROSION MANAGEMENT PROGRAM (CMP)

 Response to SA comments on 90% Package.

1.1.9 MECHANICAL

 Response to SA comments on 90% Package


 Working on vendor TBE of sampling skid
 Working on vendor quotations LOG

2.0. AREAS OF CONCERN

 There is impact of COVID-19 Safety & Health Measures on the project progress.

3.0. ATTACHMENTS
 Weekly Progress Summary
 Weekly Overall discipline progress
 Weekly Progress Report Details
 Weekly Progress overall S-Curve

Page 4 of 4