Vendor:
VALVITALIA S.p.A.
Vendor
Document No. MAN00-2017-A88 Rev 1+CRS
Signature &
Date
C1 / APP - Reviewed & accepted. Manufacture may Proceed.For
documents status IFR\IFA, resubmit as IAA at next revision code.
For documents status IAA, no action required.
C2 / AWC - Reviewed & accepted as marked. Manufacture may
proceed. For documents status IFR\IFA, resubmit as IAA at next
revision code.
For documents status IAA, resubmit as Re-IAA at next revision code.
C3 / RWC - Reviewed & returned. Manufacture shall NOT
proceed.For documents status IFR\IFA, resubmit for review Re-
IFR\IFA at next revision code.
For documents status IAA, resubmit as IFA at next revision code.
C4 / IFI -Review not required. Manufacture may proceed
Resubmit for information as IFI at next Revision Code.
C5 / REJ - REJECTED Manufacture shall NOT proceed.
Revise document and resubmit for review.
Remarks:-
VPC ERECTION INSTALLATION COMMISSIONING OPERATION AND
MAINTENANCE PROCEDURES FOR FLOATING BALL VALVES
VPC-MAN-CST-GEN-002
Revision:P3-1 Status: Re-IAA Date: 05/03/18 Page 3 of 21
Sheet 1 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
REVISION SHEET
Sheet 2 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
INDEX
1. INTRODUCTION....................................................................................... 5
1.1. SCOPE ..........................................................................................................................5
1.2. REFERENCE DOCUMENTS ...........................................................................................5
1.3. SUITABILITY ................................................................................................................5
2. ERECTION ................................................................................................ 5
2.1. USE ..............................................................................................................................5
2.2. PRECAUTIONS .............................................................................................................6
2.3. NAMEPLATE ................................................................................................................6
2.4. ADDITIONAL NAMEPLATE ..........................................................................................7
3. INSTALLATION ......................................................................................... 7
3.1. DEPRESERVATION ......................................................................................................7
3.2. Handling......................................................................................................................8
3.3. Receipt and storage ...................................................................................................8
3.4. Installation..................................................................................................................8
3.5. Supports......................................................................................................................8
4. COMMISIONING ..................................................................................... 9
5. OPERATION ............................................................................................. 9
CHECKS OR REQUIREMENTS .................................................................................................9
6. MAINTENANCE........................................................................................ 9
6.1. DISASSEMBLY .............................................................................................................9
6.1.1. Adaptor plate disassembly.................................................................................. 10
6.1.2. Top cover disassembly ........................................................................................ 10
6.1.3. Stem disassembly ................................................................................................ 10
Sheet 3 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
Sheet 4 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
1. INTRODUCTION
1.1. SCOPE
The purpose of this manual is to furnish the right indications for the installation, use and
maintenance of Side Entry floating ball valves, with bolted body. It is highly recommended to read
carefully the instructions related to other equipment fitted to the valve before starting any of the
following operations.
Use and maintenance manual for valves conformed to the follow specifications:
API 6D / ISO 14313
Directive 97/23/CE (PED)
1.3. SUITABILITY
This document is only for Side Entry floating ball valves with bolted body, installed on pipeline
with operating conditions described on chapter 5.
2. ERECTION
2.1. USE
The VALVITALIA’s Side Entry floating ball valves are designed for services of flow control in
the pipeline where the valves are in fully open or fully close position. The valves must not be
used to regulate the flow. Improper uses for flow control may invalidate the guarantee.
The valve’s open and close operations shall be done using the instruments furnished and selected
for the valve (wrench, gear, actuator). VALVITALIA refuses any responsibility for manoeuvre
done with different operators.
Sheet 5 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
2.2. PRECAUTIONS
Protective clothing and equipment normally required when working with the fluid involved is
recommended.
Depressurise the line and cycle the valve as follows:
place the valve in the open position and drain the line, cycle the valve to relieve residual pressure in
the body cavity before removal from the line. After removal and before any disassembly, cycle the
valve again several times.
2.3. NAMEPLATE
Via Tortona 69
Rivanazzano(PV) ITALY
Sheet 6 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
-API logo and license, CE logo(for European community only), ATEX logo(for E.C. only):
According to project requirement an additional nameplate, reporting all the data required
by marking specification, is fixed below the main nameplate described at point 6.1.
In the following table is possible to find all the fields included in the additional nameplate
with a brief explanation
Both the additional and the main nameplate are in double language English/Turkish as per
project requirement.
3. INSTALLATION
3.1. DEPRESERVATION
Sheet 7 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
Before the valve’s SET-UP, it should be carefully checked in order to verify that there are not
evident damage due to the shipping and handling. It very important verifying that the inside bore
of the valve is free from any foreign particles that might damage the seats and ball.
3.2. Handling
Floating ball valves are supplied without lifting lugs due to the low weight. Place the lifting
ropes around the valve body. Never lift the valve placing the ropes around the actuator.
3.3. Receipt and storage
Check that the valve was not damaged before installation and store the valve properly.
Keep it at covered and dry ambient before need on the erection site.
Do not remove the protection plates before installing the valve into the pipeline.
The valve is always delivered in the open position.
3.4. Installation
3.5. Supports
Whenever possible, try to support properly the valve. This would minimise pipeline induced
stress and vibrations into the valve body.
It is recommended to support the valve by means of connected pipes and not by the valve
body itself.
Do not use, in any case, the flange or body bolts or parts of the actuator.
Sheet 8 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
4. COMMISIONING
After valve set-up, proceed to clear the pipeline to remove any foreign materials. Close and
open the valve at least three times and verify the correct operations.
5. OPERATION
CHECKS OR REQUIREMENTS
Check there is no visible leak from the valve body, closure or other parts before the valve
opening or closing. If any leak is detected, further inspection shall be done to identify the
reason of the leak, before removing the valve from service.
Check there is no visible leak from the actuator, before the valve opening or closing. If any
leak is detected, further inspection shall be done to identify the reason of the leak, before
removing the valve from service.
Check that the valve line and the body cavity are not under pressure before proceed with any
dismounting procedures.
Grease fitting(injection devices are provided only for stem and on larger diameter)maybe
carried out also when the valve line is under pressure, due to the presence of security check
valves.
A batch of standard spare parts are always required for “routine”maintenance. If those
particulars are not included in the original scope of supply have to be requested to
VALVITALIA through a service order.
6. MAINTENANCE
6.1. DISASSEMBLY
Before disassembling the valve, ensure you have the relevant spare parts available.
Observe carefully always the instructions given in the PRECAUTIONS section 2.2.
Before starting valve disassembly the following operation shall be carried out:
• Remove the valve with its actuator from the pipeline then operate the valve to remove all
flow media trapped in the body cavity.
Sheet 9 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
If the media is TOXIC or CORROSIVE, flush the valve TO AVOID ANY ACCIDENTS.
In case that the valve should be returned to the manufacturer for repair works, please DO
NOT disassemble it.
• When disassembling the valve, please use a clean surface such as cardboard, plastic or
wood
• disassemble the actuator from the coupling flange following the instructions given by the
actuator manufacturer in the relevant manual
• place the valve in the vertical position keeping the ball in the OPEN position
Sheet 10 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
6.2. MAINTENANCE
Good operation procedure requires periodic control to ensure the correct functioning of the
valve. The frequency of these controls has to be established in relation to the type of service.
Two main points must be observed:
* STEM LEAKAGE
* SEAT LEAKAGE
STEM LEAKAGE
Stem leakage could occur if ‘O’ rings have been damaged.
On this type of valve, external stem packing may be replaced while the valve is under
pressure. Stem thrust washer is capable of generating a reasonable tight seal while the valve
is under pressure for the period of time required to change stem packing. Should a under
pressure repair be chosen, every precaution and procedures required to operate with the used
fluid shall be adopted.
SEAT LEAKAGE
In order to check the proper sealing action of the seats, put the valve in closed position and
bleed it through an appropriate connection downstream.
No leakage should occur after the body cavity pressure and temperature are stabilised.
In case of leakage of one of the seats, this type of valve will not seal properly in both
directions.
Sheet 11 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
Whenever you discover that a seal fails, ensure you have available in stock the suitable spare
parts to prevent any further damages.
6.3. INSPECTION
Regardless to the reason of taking the valve apart we highly recommend all steps mentioned
hereinafter to be followed.
• Clean ball surface with a soft cloth and a solvent, if required
• check ball surface for major scratches, pitting or erosion particularly in the seat sealing
area
• if scratches in ball bearing are found, immediately refer to the manufacturer since, unless
especially requested, bearings are not included in the spare parts kits
• if scratches or other damages are found on the ball it must be changed, NO REPAIR IN
ANY WAY IS ALLOWED, refer immediately to the manufacturer since the ball is not
included in the spare parts kit
• check the stem packing and sealing area; there must be no evident scratches or wear on
the surface
• in case of minor scratches it is recommended to polish or grind that surface
• check the seal of seat for any damage or deformation
• no scratches or deformations are allowed on the seal of seat. In case you find a damaged
seat change the complete seat.
After having inspected all items and replaced the fault ones, clean down all parts for
assembly. All ‘O’ rings and sealing rings must be replaced at any time a valve becomes
disassembled.
6.4. ASSEMBLY
A good lubricant compatible with the flow media should be applied seats, seals, ball and
stem to facilitate assembly and for ease of initial operation.
Clean seats and seals areas and all other parts before assembly.
Assembling requires a certain skill from the operator. Before starting any assembly, please
become familiar with the procedure lay down afterwards.
Firesafe valves have grafoil seal rings throughout.
Handling and installation of these seals requires a great amount of precautions since they are
very fragile and can not be repaired.
Sheet 12 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
Sheet 13 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
If the valve is cryogenic: adaptor plate is not present and stop collar(061)shall be
tighten on top of top cover.
After assembly operate several times the valve to be sure that there are no sticks or
interference.
Install all accessories in accordance to their own instruction manual, test the valve in
accordance to the approved procedures.
For a correct screwing of the bolts, refer to Table 3 – torque wrench settings. The table is
applicable only to the body to closure bolting and not cover line flange bolting
TABLE 3
Sheet 14 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
Sheet 15 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
Sheet 16 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
11. APPENDIX A)
Sheet 17 of 18
VPC ERECTION, INSTALLATION,
COMMISSIONING, OPERATION AND Doc. no. MAN00-2017-A88
MAINTENANCE PROCEDURES FOR rev.1
FLOATING BALL VALVES
Sheet 18 of 18