STEEL KONNECT INDIA PVT LTD.

SKIPL/PLN/P - 01
PROCEDURE MANUAL PAGE : 1 OF 1
REVISION : 00
PROCEDURE FOR PRODUCTION PLANNING
DATE : 01.02.2013

1.0 PURPOSE:

To ensure that quality of Product & System are maintained in the company.

2.0 SCOPE:

The scope includes QAP / Process Chart, and all consumables.

3.0 GENERAL:

Head production will ensure that all the Consumables e.g. Welding Wire, Flux, Welding
Electrodes, and Tools for Beveling, etc are available as per requirement.

After receiving the Controlled Copy of Work Order from planning department and
approved QAP & process chart from QA&C department he will assign to Director
production for further production activities.

Director Production will set the mill parameters & do the setting of hydro tester and
beveling machine as per Process Chart. He will qualify the welding procedure
specification for auto SAW & SMAW.

Director Production will ensure that all the measuring instruments are calibrated & SAW
& SMAW welders are qualified.

Production in-charge will receive the Plate / Beam / Angle release note from QA&C
department for the first day production (if required). After getting satisfactory first day
results, production In-charge can start the mass production.

Engineer Production will record the daily production and break down status at the end
of shift in the logbook. In every morning shift he will make the daily production report
along with break down status. (if any) and also record in the computer.

Director Production will monitor the progress day-to –day basis and update the plan it
as required.

4.0 REFERENCE DOCUMENTS:

Cl. No. 5.4.1 OF QSM, Internal work order, Process Chart, WPS, PQR & Daily Production
Report

Prepared By Reviewed By Approved By

Head Production Director Production Management Representative