Professional Documents
Culture Documents
Contractor/ EPCM
Logo Qual
Controlled Activities
2 Excavation
2.1 Safe Access Handovers Certificate from Earthworks contractor METC/KICO SA.
3 Backfilling
Use select material to backfill in layers (Approved by METC/KICO
3.1 MCS/KICO/IMIR-061
SA )
4 Compaction
5 Punch Inspection
5.4 Phase 2 - Punch List Inspection - METC Punch & acceptance MCS/KICO/PLP_2-076
5.6 Phase 3 - Punch List Inspection - KICO Punch & acceptance MCS/KICO/PLP_3-076
Name:
Signed :
Date :
DEFINITION OF INTERHENTION POINTS: A point of inspection in the QCP that requires the presence of the inspection
H - where the next stage of the production/construction process cannot proceed beyond this point until an inspection has bee
W - where production cannot proceed beyond this point if the inspection organization has not attended, provided due notice
R - where a reviews of the records developed by the supplier to ensure that the reliant activity has been performed satisfactor
H - where the next stage of the production/construction process cannot proceed beyond this point until an inspection has bee
M- Monitoring
MINING CHEMICAL SUPPLIERS
L PLAN EARTHWORKS
NA M = Monitoring Area:
MCS/QCP/001 H H H
METC/KICO SA. H H H
METC/KICO SA. H H H
MCS/MS/0045 H H H
Procedure H H H
Certificates H H H
METC/KICO SA. H H R
MCS/KICO/STR-003 H W W
MCS/KICO/EXC-004 H H M
METC/KICO SA. H W R
MCS/KICO/PLP_1-076 H H R
MCS/KICO/RFI-070 H W R
MCS/KICO/PLP_2-076 H H H
MCS/KICO/RFI-070 H W R
MCS/KICO/PLP_3-076 H H R
MCS/KICO/RFI-070 H R
METC/KICO SA. H H H
METC/KICO SA. H H H
Data Book H H H
Approval's
Rating
1
1. Critical X
9/3/2022 2. Major
SANS 1200 D -
1988 (As
3. Minor
amaended
1990)
rol
Remarks
KICO (Client)
KICO (Client)
as met/achieved.
contract.
as met/achieved.