Package 1
Supplier/Sub-Contractor Name
Supplier/Sub-Contractor Number
M-BCW-1F4TS0-GC00-SUB-000001
Document Title
ITP for HVAC Duct works
Document No. M-BMF-1F4TS0-CMAC-ITP-000001
Signatures:
Engineer Review Status Date: 05 October 2019 Name: Raymond JB. Ricasio
CWP No M-BMF-1F4TS0-CMAC-CWP-000001 CWP Title : ITP for Installation of HVAC Duct and Accessories. Location: STATION 1F4
Method of Verification
Inspection/Test Requirements Acceptance criteria Reference Documentation
(see Legend) Demonstrated Evidence Report /
Activity No. Activity Description
SUBCON. Checklist
Test/Inspection Performed Stage/Frequency (Greater or equal to the value) Code/Spec/Etc. BACS RMTC
QC
1.0 Document submittals
Project specification (M-BCW-
Project specification,Method Approved Specificationss,Approved
Before 000000-CMAC-ESP-015815,clause
statement,ITP,Material Method Statement,MAR, Materials Test
1.1 Document review commencement of 2.1 to 2.13,1.6,015820-clause 2.1 to H R R
approvals,Shop drawings,welder Certificate & Compliance Certificate, IFC
work 2.11,015081-clause 2.1 to
certificates(if any) drawings & ITP
2.5,1.3D,015855-clause 2.1 to 2.2)
2.0 Supplied materials inspection
Project specification (M-BCW-
Inspection of supplied key 000000-CMAC-ESP-015815,clause
Visual inspection/Physical First delivery of ZP-W-001 : Material Receiving
2.1 materials based on the Approved MAR/Verify MTC 2.1 to 2.13,1.6,015820-clause 2.1 to H W W
inspection material Checklist,IRF, MIR
specification 2.11,015081-clause 2.1 to
2.5,1.3D,015855-clause 2.1 to 2.2)
Project specification (M-BCW-
Inspection of supplied key 000000-CMAC-ESP-015815,clause
Visual inspection/Physical Succedding delivery ZP-W-001 : Material Receiving
2.2 materials based on the Approved MAR/Verify MTC 2.1 to 2.13,1.6,015820-clause 2.1 to H W S
inspection of material Checklist,IRF
specification 2.11,015081-clause 2.1 to
2.5,1.3D,015855-clause 2.1 to 2.2)
Visual inspection/Physical Every delivery of
2.3 Material Storage and handling Manufacturer recommendation Manufacturer Recommendations I S S
inspection material
3.0 Execuion and installation
Project specification (M-BCW-
As per IFC drawing, Specification and
3.1 Support Instalaltion Visual Inspection Every location 000000-CMAC-ESP-015815,clause I W W ZP-M-001, WIR, IRF
Method Statement,Approved WPS.
1.4-D,E,1.6,3.5-C)
Page 1 of 2
2 of 2
RIYADH METRO PROJECT – PACKAGE 01
Inspection Checklist
Electronic documents once printed, are uncontrolled and may become outdated. Refer to Aconex for current version.
AREA/UNIT: WP NO.:
MATERIAL DESCRIPTION :
ITP REF.:
ITEM RE-INSP.
Activity YES (√) NO (x) N/A
No. DATE
1
Visually inspect all incoming material /equipment for damage.
2
Verify the Quantity as per delivery note or packing list
3
Verify the Material / Equipment confirmed to specification or approved MAR
4
Verify Shipping documents (check MTC along with material delivery if Applicable)
5
Verify Equipment / Materials are properly protected during transportation
6
Verify the material storage as per project requirement
REMARKS:
REFERENCE DOCUMENTS:
DATE
Attachment 4
INSPECTION REQUEST FORM
DRAWING No.:
ITEM TO BE INSPECTED:
LOCATION:
TYPE OF INSPECTION:
Witness Hold
ADDITIONAL INFORMATION/COMMENTS:
Use, disclosure or reproduction of this information only by permission of the Project Director. All rights reserved
Riyadh Metro Project - Package 1
Work Inspection Request (WIR)
Location: WP:
Inspection Date and Time: ITP Ref.:
Item to be Inspected: DWG. Ref.:
Attachment: Checklist Survey Data Others:
Description of Inspection:
RMTC Comments:
Status: Work May Proceed Work May Proceed as Noted Work May not Proceed
RMTC Representative
Print Name Signature Date
Document No. M-BAC-000000-GQ00-FOR-000002_Rev. 009 M-BCW-000000-GQQC-PRO-000001
Page 1 of 2
© 2013 Saudi Arabian Bechtel Company and Almabani General Contractors and Consolidated Contractors Company WLL
Use, disclosure or reproduction of this information only by permission of the Project Director. All rights reserved.
Page 2 of 2
© 2013 Saudi Arabian Bechtel Company and Almabani General Contractors and Consolidated Contractors Company WLL
Use, disclosure or reproduction of this information only by permission of the Project Director. All rights reserved.
RIYADH METRO PROJECT – PACKAGE 01
Inspection Checklist
Electronic documents once printed, are uncontrolled and may become outdated. Refer to Aconex for current version.
AREA/UNIT: WP NO.:
DESCRIPTION :
ITP REF.:
ITEM RE-INSP.
Activity YES (√) NO (x) N/A
No. DATE
REMARKS:
REFERENCE DOCUMENTS:
DATE
RIYADH METRO PROJECT – PACKAGE 01
Inspection Checklist
Electronic documents once printed, are uncontrolled and may become outdated. Refer to Aconex for current version.
AREA/UNIT: WP NO.:
DESCRIPTION :
ITP REF.:
ITEM RE-INSP.
Activity YES (√) NO (x) N/A
No. DATE
REMARKS:
REFERENCE DOCUMENTS:
DATE
RIYADH METRO PROJECT – PACKAGE 01
Inspection Checklist
Electronic documents once printed, are uncontrolled and may become outdated. Refer to Aconex for current version.
AREA/UNIT: WP NO.:
DESCRIPTION :
ITP REF.:
ITEM RE-INSP.
Activity YES (√) NO (x) N/A
No. DATE
REMARKS:
REFERENCE DOCUMENTS:
DATE
RIYADH METRO PROJECT – PACKAGE 01
Inspection Checklist
Electronic documents once printed, are uncontrolled and may become outdated. Refer to Aconex for current version.
AREA/UNIT: WP NO.:
DESCRIPTION :
ITP REF.:
ITEM RE-INSP.
Activity YES (√) NO (x) N/A
No. DATE
REMARKS:
REFERENCE DOCUMENTS:
DATE
RIYADH METRO PROJECT – PACKAGE 01
Inspection Checklist
Electronic documents once printed, are uncontrolled and may become outdated. Refer to Aconex for current version.
AREA/UNIT: WP NO.:
DESCRIPTION :
ITP REF.:
ITEM RE-INSP.
Activity YES (√) NO (x) N/A
No. DATE
REMARKS:
REFERENCE DOCUMENTS:
DATE
RIYADH METRO PROJECT – PACKAGE 01
Inspection Checklist
Electronic documents once printed, are uncontrolled and may become outdated. Refer to Aconex for current version.
AREA/UNIT: WP NO.:
DESCRIPTION :
ITP REF.:
ITEM RE-INSP.
Activity YES (√) NO (x) N/A
No. DATE
1
Check the Duct installation and insulation is completed as per IFC
2
Verify All required inspection activities are completed and documented
3
All penetrations and openings closed and sealed with approved material-if applicable
4
Verify Mechanical Identification as per project specification
5
Verify labelling and identification of access doors as per schedule.
6 Verify all ductworks have been pressurized to normal operating pressure to achieve
minimum audible leakage
7
Verify system is ready for commissioning.
REMARKS:
REFERENCE DOCUMENTS:
DATE