Professional Documents
Culture Documents
Documents Reference: CP05-03-MMC-MST-ELE-0025 Subject T&C Method of Statement for FDB– M/s. Menasco
Comment Response
Ref. Status
Date Reviewed by Reviewer comments Response by Contractor Response checked by original reviewer
SN Description
CP05-03-MMC-MST-ELE-0025 REV.00 Testing & Commissioning of final DB, has been reviewed and is
1
accepted for further submission.
5.3.4 Live test- External Loop impedance (Ze) test and Prospective Fault
2
Current Measurement test (page.10/19)
- Live test report (Page.19/19) to be updated to record the measured Ze & PFC values as per 5.3.4
Page 1 of 1
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-MMC-MST-ELE-0025
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF FINAL
Revision 00
Dubai, UAE DISTRIBUTION BOARD (FDB)
Issue Date 16-April-2023 Page 1 of 14
METHOD STATEMENT
FOR TESTING AND COMMISSIONING OF
FINAL DISTRIBUTION BOARD (FDB)
CONTENTS
4) RESPONSIBILITIES
4.1 PROJECT MANAGER
4.2 ELECTRICAL SITE ENGINEER
4.3 ELECTRICAL SUPERVISOR
4.4 QA/QC ENGINEER
4.5 SAFETY ENGINEER
5) PROCEDURE / METHOD TO BE EMPLOYED
9) RISK ASSESSMENT
10) ATTACHMENTS
2.2 DEFINITIONS
• MAIN CONSULTANT means M/S LACASA Architects & Engineering Consultants
• MAIN CONTRACTOR means Ali & Sons Contracting L.L.C
• MEP SUB-CONTRACTOR means MENASCO Mechanical Contracting. LLC.
Electrical site engineer coordinates all site activities required for testing and
commissioning activities as per specification, manufacture datasheet and approved
drawing.
He should ensure to:
• Check the continuity between phase and Earth by shorting at the Distribution Board
side.
• Check the continuity from the terminals of the farthest connection point or socket
outlet.
• A small buss sound (or resistance value) will confirm continuity passed.
• Repeat the test between phase and neutral.
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-MMC-MST-ELE-0025
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF FINAL
Revision 00
Dubai, UAE DISTRIBUTION BOARD (FDB)
Issue Date 16-April-2023 Page 7 of 14
• It is, however, most important to ensure that all single-pole lighting switches are
connected in the phase (live) conductor, rather than in the neutral.
• Record the result on the cable test sheet.
Ring circuits:
• First, the end-to-end resistances of the line, neutral and earth are measured
separately at the distribution board side.
• The insulation resistance test is carried out to measure the insulation resistance
between phases to phase/phase to neutral/phase to earth (Phase to phase for three
phase circuits only).
• Ensure that cable is disconnected at the testing end as well as other end and
someone is looping the cables being tested from another end.
• For single phase circuits, connect the test leads to the two conductors to be tested.
(Phase and Neutral).
• Set the test instrument to required voltage. Sigle phase (230V) shall be tested at
500 DCV and for 3 phase (400V) at 1000 DCV.
• Press TEST and record the values on the approved test sheet (Attached)
• Disconnect test leads and discharge.
• Repeat above for Phase & Earth, neutral & Earth.
• For three phase circuits, perform the insulation resistance test for Phase to phase,
phases to neutral, phases to earth and neutral to earth.
• Record the test results accordingly on the approved test sheet.
• Caution testing to be carried out under live condition & warning notice must be put
in place and necessary permit to be signed for that particular test. All to be prepared
prior to test.
• For single phase circuits, a test of polarity should be carried out to verify that every
fuse and single pole control and protective device is connected in the phase
conductor only.
• For socket outlets, connect the tester in the live sockets and an indication will show
correct polarity.
5.3.4 Live test- External Loop impedance (Ze) test and Prospective Fault
Current Measurement test
• Caution testing to be carried out under live condition & warning notice must be put
in place and necessary permit to be signed for that particular test. All to be prepared
prior to test.
• Carry out earth loop impedance (Ze) test on the board. Ensure that the main and
outgoing circuit of the board under test is in OFF position and the main earth cable
termination is disconnected from the board main earth terminal. Check instrument
for safety and correct settings.
• For single phase board, connect the earth clip of the earth loop impedance tester to
the disconnected main earth conductor, then connect the other line probe to phase
terminal of the incoming cable on the incoming side of main disconnect (isolator).
Note: Refer to manufacturer’s instructions for correct settings and connections.
• Press the test button and record the results on the approved test sheet already
containing the cold test results.
• For three phase board, connect the earth lead of the earth loop impedance tester to
the main earth conductor and then connect the other line probe to RED phase
terminal of the incoming cable on the incoming side of main disconnect (isolator).
Next, take the reading for the remaining BLUE and YELLOW phase.
• The highest reading obtained is recorded as the external earth loop impedance.
• After the completion of the Ze, reconnect the main earth cable on the board main
earth terminal.
• Carry out measurement of the maximum prospective fault current (IPF) between
line-to-neutral and line-to-earth. Refer to manufacturer’s instructions for correct
settings and connections.
• Press the test button and record the test report in approved test format (Attached).
• Switch panel main disconnect ‘’on’’ and switch on the outgoing circuits.
• For single phase circuit, take the earth loop impedance (Zs) reading at the farthest
most point from the board of the outgoing circuit under test. Connect the test probes
as per manufacturer’s instructions for correct connections.
• Press the test button and record the results on the approved test sheet already
containing the cold test results.
• For three phase circuits, take the Zs reading of each phase (R, Y and B). Connect
the test probes as per manufacturer’s instructions for correct connections.
• The highest reading obtained is recorded as the earth fault loop impedance (Zs) for
3 phase circuit.
• The value of Zs should not exceed the maximum loop impedance as per
manufacturer's recommendation.
• Record the test report in approved test format (Attached).
Contract specifications supersedes all material described in this document.
DIFC CP-05 Office
DOCUMENT NUMBER
Building-Main METHOD STATEMENT CP05-MMC-MST-ELE-0025
Works Package & FOR TESTING AND
Link Bridge Project, COMMISSIONING OF FINAL
Revision 00
Dubai, UAE DISTRIBUTION BOARD (FDB)
Issue Date 16-April-2023 Page 11 of 14
• After the taking the reading of Zs of a circuit, proceed with the ELCB trip test.
• Ensure that the breaker of the circuit under test is in ‘’ON’’ position.
• Turn/select the select the switch to ‘’ΔT RCD time’’ position.
• Select the RCD current rating (30mA, 100mA) depending on the RCD rating of the
circuit under test. Then, select test knob in carry out the test for (x1/2, x1 and x5)
times of rated trip current.
• Connect the RCD testing device at the farthest most point from the board of the
outgoing circuit under test. Connect the test probes as per manufacturer’s
instructions for correct connections.
• Record the test report in approved test format (Attached).
8 RISK ASSESSMENT
Prior to the commencement of any activities the risk assessment (refer to
attachments) shall be reviewed jointly by the construction and the HSE team to
ensure that all the risks are addressed and the required mitigation measures are in
place and remain fully implemented during operation.
9 ATTACHMENTS
• Checklist for Pre-commissioning and commissioning.
• Risk Assessment.
INSPECTION CHECKLIST
Pre-commissioning Check List for Final Distribution System (FDB)
2
Check the installation as per approved shop drawings
4
Ensure that the correct rating of the components is as per the approved
drawings.
5
Check the Tightening of all connections and Termination of cables on
the panels.
6
Check the cables size as per approved load schedule
7 Wiring/Cable not damaged along its entire length.
10
11
12
13
14
15
16
17
18
Remark:
Remarks:
Severity
Likelihood 1 2 3 4 5
Certain 5 5 10 15 20 25
Very Likely 4 4 8 12 16 20
Likely 3 3 6 9 12 15
May Happen 2 2 4 6 8 10
Unlikely 1 1 2 3 4 5
Trivial Risk - No further improvements necessary provided control measures are maintained
Adequately Controlled Risk - Risk is tolerable when control measures identified are implemented
Moderately controlled Risk - Further risk reduction measures should be considered
Intolerable Risk - Seek specialist advice/ support
Aravi Ashok Designation Proj, HSE Manager Date: 30th May 2023 Signature:
Salman Abu Assali Designation Project Manager Date: 30th May 2023 Signature:
MENASCO MECHANICAL CONTRACTING L.L.C. Page 2 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
01 Access to work Unfamiliarity to the site Minor injury 3 2 6 The Ali & Sons Contracting Project HSE Plan 1 2 2 Compliance to
area Unauthorized parking Property / asset shall be strictly complied with by all M/s DM, COP- CHP
Unauthorized access to site or damage MENASCO personnel and sub-contractors 2- 2.1, 2.3
taken shortcut under our control. Y
warning alarm/ warning light All work shall be carried out in accordance to Manager
Slip, trip and fall all applicable UAE Laws and Regulations, DM
Obstructed the walkway /traffic Regulations and MMC Project HSE Senior Project
activity
All material shall be segregated accordingly to Driver & Helper
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Testing And
Short circuits and overloads: Minor Permit to Work to be obtained prior to
03 Commissionin Personal injury activity.
Fire hazards:
g Procedure Property / assets MSRA & TBT to be communicated with the
Arc Flash Hazards
damage operatives by the foreman or supervisor.
Unauthorized Access Commissioning
Cold Test- Review the electrical design and Engineer
Accidental contact with live parts,
Continuity specifications to understand the
improper operation of the circuit
Test requirements for the Final DB.
breaker. Project Manager
Ensure that all necessary permits and
Cold Test- Machinery Hazard
approvals are in place.
Construction
Insulation Electrical hazards 4 3 12 1 3 3
Before starting a continuity test, the test Manager
Environmental hazards
lead resistance should be nulled such that
Resistance Human error
it does not add extra resistance to the
Senior Project
Test Untrained operatives.
circuit being measured.
Engineer
Live test- Defect/ damage tool/equipment. Y
Perform a continuity test to ensure that all
Polarity/ Lack / poor supervision connections within the Final DB are
Site Engineer
Phase Incompetent/untrained operatives properly established.
Rotation test Poor lightening Conduct an insulation resistance test to
HSE Officer
Trip, slip and fall check the integrity of the insulation
Live test- Uninspected equipment materials within the DB.
Supervisors
External Loop Shortcut maneuvering Test the functionality of various
impedance Obstructed access components within the Final DB, such as
Foreman
(Zed) test and Poor Housekeeping circuit breakers, relays, contactors, meters,
Prospective
and protective devices.
operators
Fault Current
Verify that the DB operates as intended
Measurement
and that all controls, indicators, and alarms
test
are functioning properly.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 7 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Used of Electrocution Minor Injury The Ali & Sons Contracting Project HSE Plan
05 temporary Slip / Trip and falls Major Injury shall be strictly complied with by all
power supply Untrained operative. Property All works shall be regularly monitored and
and Use of damage extension damaged supervised by M/s MENASCO site team to
Extension leads. Project Manager
leads. ensure full compliance
Use of damaged equipment's MENASCO shall provide adequate
Construction
Lack of PPE. resources, as appropriate to ensure safe
Manager
Work In wet areas with execution of work scope.
to its workers
Operators
Only competent person can carried out the
electrical task at site
T & C Engrs
Inspected and color-coded extension leads to
be used on site.
All electrical tools and equipment's free from
defects and fit to safe use
MENASCO MECHANICAL CONTRACTING L.L.C. Page 11 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Board (EDB).
insulated.
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Work at Height Falling of men and materials from Major Injuries The Ali & Sons Contracting Project HSE Plan
07 - Using Scaffold,
height Minor Injury
shall be strictly complied with by all DM – Compliance
A-Type ladder / All works shall be regularly monitored and CHAPTER 8
Presence of overhead services Fatality Scaffolding
Podium Ladders supervised by M/s MENASCO site team
Safety
Incompetent workers Property damaged to ensure full compliance 101CHAPTER
MENASCO shall provide adequate resources, 4Personal
Lack of supervision
as appropriate to ensure safe execution of work Protective
Improper use of work platform
scope. Equipment
44Project
Unauthorized access to the All work shall be carried out in accordance to all
Manager
applicable UAE Laws and Regulations, DM
equipment
Regulations and MMC Project HSE Management Construction
Untrained operator
System. Manager
Unfavourableclimatic conditions MSRA to be communicated with the operatives
3 3 9
1 3 3 Y
by the foreman or supervisor. Senior Project
Unbalancing of work platform
Permit For work at height on scaffolding to be Engineer
Caught-in between
available and approved from concerned team prior
Working under direct sun light to start of work. Site Engineer
Pre-Task briefing or TBT to be carried out by
Dust
foreman or supervisor prior to start of work HSE Officer
Noise
communicating hazard and control measures to its
Slippery surface due to leak of oil workers. Supervisors
Only Competent scaffolder which is 3rd party
certified to erect mobile Aluminum scaffolding and Foreman
platform.
Operative Working at height must be trained for T & C Engrs
Safe Work at height.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 16 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
08 Working in hot Heat Stress and Heat-related Major Injuries The midday break regulation from DM to be
whether Illnesses, Risk: Prolonged ensures that outdoor work activities are
Minor Injury
exposure to high temperatures suspended during the hottest part of the day
Fines
(Midday Break can lead to heat stress, heat when temperatures are typically at their peak.
Rule between exhaustion, or even heatstroke. Property damaged This allows workers to rest, hydrate, and seek
June 15th To Dehydration: Working in
hot shade during the most intense heat
Project Manager
September environments can lead to Risk Assessment and Planning:
15th ) excessive fluid loss through Working in heat Training and Awareness shall
Construction
sweating, increasing the risk of be provided
Manager
dehydration Encourage workers to drink plenty of water
Sunburn and Skin Damage risk and fluids before, during, and after work to
Senior Project
of skin cancer. prevent dehydration.
Engineer
All ailments due to excessive Schedule frequent rest breaks in shaded or
heat, like cramps, burns, 4
3 12
air-conditioned areas to allow workers to cool
1 3 3 Y
Site Engineer
headache, dehydration, etc. down and recover from heat exposure.
Plan work activities to minimize exposure
HSE Officer
during the hottest parts of the day, such as
scheduling physically demanding tasks in the
Supervisors
cooler morning or late afternoon hours
Foreman
Ventilation and Airflow
Implement a system for monitoring workers'
T & C Engrs
health and well-being, including regular
checks for signs of heat-related illnesses
Provision of cool drinking water
Proper cotton clothing
Change in work schedule, wherever possible.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 18 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Lack of training to Emergency case Operatives must be trained of safe and proper
responder Fines use of hand tools. Project Manager
Incompetent emergency responders Property damage All tools provided must be assessed to ensure
that they are fit for purpose, they fit for the Construction
Improper or lack of illumination Lack of training to Manager
Improper or lack of ventilation Emergency responder environment in which they are to be used and they
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Proper ventilation to be provided
Proper and safe access to be provided in work
areas.
Ali & Sons HSE Policies and Procedures shall be
followed by Menasco team prior to start of the
Activity.
Menasco to comply with Local Authority
regulations and HSE requirements
Emergency response and contact details to be
made available and known to workers at site.
Emergency vehicle to be available for emergency
rescue to nearest hospital.
Contact: No # 0543057866
MENASCO MECHANICAL CONTRACTING L.L.C. Page 22 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
11 Housekeeping Slips, Trips, and Falls: Improper Major Injuries Workers must be trained and aware and
at workplace disposal of waste can create comply with the housekeeping plan on the site.
Minor Injury
after the task obstacles and clutter, increasing TBT on housekeeping to be given to all.
Fire
the risk of slips, trips, and falls Removal of all waste from work after the
Project
Contamination and Exposure: Property damaged completion of activity.
Manager
Fire and Combustible Materials: Where possible, packaging materials shall be
Improper disposal and storage of removed from the site the earliest opportunity in
Construction
flammable or combustible order to reduce the fire load.
Manager
materials can increase the risk of Materials to be stacked and stored properly.
fire Signage and Labelling:
Senior
Health Hazards: Inadequate Establish a regular waste removal schedule to
Project
disposal of waste can create an prevent accumulation. Dispose of waste in a
3 2 6 1 2 2 Engineer
unhygienic environment, leading timely manner and ensure that waste collection
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Note: If any new scenarios emerge that are not covered by this risk assessment, site management should be contacted immediately, and the task should not be completed until a specific risk
assessment has been completed, issued, and understood.