North-South Commuter Railway Extension

(NSCR-EX) Project
General Consultant Services

Reference No.: NSCR-GCR-N03-ZWD-TRL-DC-000703


26 March 2024

DOCUMENT TRANSMITTAL FORM


GCR Consortium

Usec. Jeremy S. Regino


Undersecretary for Railways
Department of Transportation (DOTr)
12th Floor Primex Tower, EDSA Corner,
Connecticut Street, San Juan City,
1503 Metro Manila

We transmit herewith the following document/(s):

S/N DOCUMENT NUMBER REV DOCUMENT TITLE COPY Remark

NSCR-GCR-N03-ZWD- N-03; Site Daily Activity Report


1
TRL-DC-000703 250324

For:

☐Approval ☐Action ☒Information/Record


☐Revision/Resubmission ☐Other (Specify)

NOTE:

Please acknowledge receipt by signing and returning a copy of this transmittal sheet;
Issued By:
Signature:
Name:
Position:
Date:

GCR Consortium Office: 20th and 21st Floor, Greenfield Tower, Mayflower Street, Greenfield District, Mandaluyong City, 1550 Metro
(Main Office) Manila, Philippines
Tel: +63-2-5322-3700
Oriental Consultants Global Unit 38C, 38th Floor, Rufino Pacific Tower Bldg., 6784 Ayala Avenue, Makati City 1223, Philippines
Philippine Branch Office Tel: +63-2-856-9747~9750 | Fax: +63-2-856-9751
North-South Commuter Railway Extension
(NSCR-EX) Project
General Consultant Services

This is to acknowledge that I received the abovementioned documents;

Received By: DOTR


Signature :____________________________
Name :____________________________
Position :____________________________
Date :____________________________

GCR Consortium Office: 20th and 21st Floor, Greenfield Tower, Mayflower Street, Greenfield District, Mandaluyong City, 1550 Metro
(Main Office) Manila, Philippines
Tel: +63-2-5322-3700
Oriental Consultants Global Unit 38C, 38th Floor, Rufino Pacific Tower Bldg., 6784 Ayala Avenue, Makati City 1223, Philippines
Philippine Branch Office Tel: +63-2-856-9747~9750 | Fax: +63-2-856-9751
North – South Commuter Railway Extension (NSCR-EX) Project
General Consultant
Package CP N-03: Civil Works

Site Daily Activity Report

Date: March 25, 2024 (Monday)


Weather: Sunny

A. Manpower:

Main Sub-
Item Description Remarks
Contractor Contractor
1 Supervisors 79 13
2 Skilled Workers 144 105
3 Unskilled Workers 40 26

B. Equipment:

Main Sub-
Item Description Remarks
Contractor Contractor
1 Drilling Rig 2 1-idle, 1-working
2 Crawler Crane 3
3 Mobile Crane 5
4 Gantry Crane 10
5 Rough Terrain Crane 8
6 Excavator / Backhoe 3
7 Motor Grader 1
8 Loader 1
9 Roller Compactor 2 1-1T, 1-10T
10 Dump Truck 4
11 Boom Truck 3
12 Water Truck 2
13 Telehandler 4T 2
14 Telescopic Forklift 1
15 Desanding Machine
16 Koden Machine 1
17 Vibro Machine/Hammer 2
18 Jack Hammer 3

C. Activities:

C1. Precast Yard Area (Brgy Baliti)


• Pre-concrete survey inspection for SBGs S-835/07(T1), S-833/02(T1M), S-984NB/06(T3-4), S-
985NB/05(T3-3), S-985NB/05(T3-3) & S-1110/06(T1).
• Maintenance, repair & cleaning works of segments’ molds.
• Inspection of rebar cages & repair works of casted segments.
• Rebar cage assembly & fabrication for casting segments.
• Casting of segments S-985NB/05(T3-3), S-985NB/05(T3-3), S-984NB/06(T3-4), S-835/07(T1), S-
1110/06(T1) & S-833/02(T1M).
C2. San Fernando Mainline / Sapang Balen Area (Area 01)
• Survey inspection of temporary casing for bored pile P903-01.
• Bored piling works.
• Site clearing & river diversion works.
• Rebar cage assembly & fabrication at fabrication area.
• Concrete pouring for bored pile P903-01.

C3. Angeles Station Area / Area L Sub-Camp Area (Area 02)


• PDA block hacking works at P989R.
• Rebar works for pile cap at P989L.
• Working platform installation for pier head at P988.
• Chipping of construction joint for pier column at P986.
• LG#1: Duct pressure test and grouting at installed segments.
• Rebar fabrication works at fabrication area.

C4. Old Angeles Station Area (Area-03)


• No activity.

C5. Clark Area / Mabalacat (Area-04)


• Survey as-built of pile cap at P1114NB.
• Survey inspection of blinding for footing at Substation SS21.
• Survey inspection of pier column (2nd lift) at P1108R.
• Rebars installation for pile cap at P1108L.
• Bored pile hacking works at P1110SB.
• Working platform installation for pier head at P1113NB.
• LG#2: Oil injection & grinding of excess epoxy at installed segments.
• Scaffolding installation for portal beam at P1120 L-R.
• Formworks installation for portal beam at P1121 L-R.
• Concrete curing & surface repair works for cast-in-situ span at P1130 to P1131.
• LG#3: PT strand stressing for segments at span P1134 to P1133.
• Formworks installation for Substation SS21 footings & tie beam.
• Temporary drainage works at East Perimeter area.
• Pile excavation & formworks installation for pile cap at Main Station.
• Concrete pouring for pier column (2nd lift) at P1108R.
• Lean concrete pouring for Substation SS21 footings.

C6. Pulung Bulu, Angeles Area (Area-05)


• Formworks installation for pier column (2nd lift) at P968.
• Scaffolding erection for pier column at P967.
• Rebar installation for pier column (2nd lift) at P964.
• Sheet pile driving at Maintenance Ramp Pier 1.
• Side rebar installation for pile cap at Maintenance Ramp Abutment.

D. Production & Progress:


Item Description Total 25-Mar-24 Cumulative % Complete
1 Bored Piles 1022
1.1 Area-01 (P825 - P931, Mainline) 574 1 37 6.45%
1.2 Area-02 (P973 - P992, Mainline) 216 0 216 100.00%
1.3 Area-03 (P1001 – P1035, Mainline) 210 0 100 47.62%
1.4 Area-04 (P1105 – P1142, Mainline) 278 0 278 100.00%
1.5 Area-05 (P932 – P972, Mainline) 242 0 72 29.75%
1.6 Angeles Station 86 0 86 100.00%
1.7 Angeles SigCom 45 0 45 100.00%
1.8 Angeles GenSet 4 0 4 100.00%
1.9 Clark Station 101 0 101 100.00%
1.10 Clark SigCom 27 0 27 100.00%
1.11 Clark GenSet 4 0 4 100.00%
1.12 Sub Station 19 22 0 22 100.00%
1.13 Sub Station 21 18 0 18 100.00%
1.14 Maintenance Ramp 12 0 12 100.00%
2 Pile Caps 101
2.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
2.2 Area-02 (P973 - P992, Mainline) 46 0 35 76.09%
2.3 Area-03 (P1001 – P1035, Mainline) 35 0 5 14.29%
2.4 Area-04 (P1105 – P1142, Mainline) 63 0 49 77.78%
2.5 Area-05 (P932 – P972, Mainline) 42 0 11 26.19%
2.6 Maintenance Ramp 3 0 1 33.33%
3 Pier Columns 87
3.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
3.2 Area-02 (P973 - P992, Mainline) 46 0 31 67.39%
3.3 Area-03 (P1001 – P1035, Mainline) 35 0 0 0.00%
3.4 Area-04 (P1105 – P1142, Mainline) 63 1 48 76.19%
3.5 Area-05 (P932 – P972, Mainline) 42 0 8 19.05%
3.6 Maintenance Ramp 3 0 0 0.00%
4 Pier Heads 61
4.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
4.2 Area-02 (P973 - P992, Mainline) 46 0 19 41.30%
4.3 Area-03 (P1001 – P1035, Mainline) 35 0 0 0.00%
4.4 Area-04 (P1105 – P1142, Mainline) 63 0 39 61.90%
4.5 Area-05 (P932 – P972, Mainline) 42 0 3 7.14%
4.6 Maintenance Ramp 3 0 0 0.00%
5 SBGs Casted 1072
5.1 SBG (10.30 m) 4,420 3 805 18.21%
5.2 SBG (6.30 m) 314 0 88 28.03%
5.3 SBG (5.10 m) 408 3 179 43.87%
6 SBGs Delivered to Site 376 24 Spans
6.1 SBG (10.30 m) 4,420 0 376 8.51%
6.2 SBG (6.30 m) 314 0 0 0.00%
6.3 SBG (5.10 m) 408 0 0 0.00%
7 SBGs Erected / Installed 360 23 Spans
7.1 SBG (10.30 m) 4,420 0 360 8.14%
7.2 SBG (6.30 m) 314 0 0 0.00%
7.3 SBG (5.10 m) 408 0 0 0.00%
• Only those areas with progress are listed here.