METHOD STATEMENT FOR

UNDERGROUND EXCAVATION AND


ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 3 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

TABLE OF CONTENTS

1 PURPOSE OF DOCUMENTS ................................................................................... 4

2 SCOPE OF WORKS ................................................................................................. 4

3 REFERENCE DOCUMENTS .................................................................................... 4

4 DEFINITIONS............................................................................................................ 5

5 ABBREVIATIONS ..................................................................................................... 5

6 RESPONSIBLE PERSONS....................................................................................... 5

7 PLANT EQUIPMENTS & TOOLS .............................................................................. 6

8 MANPOWER REQUIREMENTS ............................................................................... 6

9 PERMIT REQUIREMENTS & COORDINATORS ..................................................... 6

10 MATERIALS .............................................................................................................. 7

11 SEQUENCE OF ACTIVITIES .................................................................................... 7

12 ATTACHMENTS ( DRAWINGS ETC) ..................................................................... 20

13 TRA - TASK RISK ASSESSMENT .......................................................................... 21


METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 4 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

1 PURPOSE OF DOCUMENTS
The purpose of this method statement is to define the work sequence, Manpower
and Equipment resources, procedures for carrying out scope of work. This Method
Statement is intended for ADNOC Refinery Waste Heat Recovery Project

2 SCOPE OF WORKS
1. PTW
2. Survey & Cable Detection
3. Pavement Concrete Cutting & Breaking (If Needed)
4. Excavation (Manual & Mechanical)
5. Trench Wall Protection Installation
6. Dewatering System Installation (If needed)
7. Placing of Sand Bedding
8. Back Filling
9. Road (Asphalt) Restoration

3 REFERENCE DOCUMENTS
2.1 Project Specifications
 5636-DGS-CU-003 Site Preparation
 SO6044-ESOB-BED-4000-001 Project HSE Plan
 6143-HSE-HU-003 Permit to work procedure

2.2 Reference Drawings


 4222-EU-E-0002 Over All Plot Plan
 Key Plan- UG Piping Plan 6143-4000-PU-E-020
 IFC GRV UG Drawing 6143-4000-PU-D-2013

NOTE:
The documents listed above are the basic documents, however before starting the
work, construction team shall verify and confirm if relevant construction instructions of
suppliers and vendors (if applicable) shall be considered and incorporated, together
with a verification of the latest revision of the referred documents and the applicability of
additional documents shall be verified.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 5 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

4 DEFINITIONS

1. COMPANY : ADNOC (Abu Dhabi National Oil Company Refining)


2. CONTRACTOR : SECL (Samsung Engineering Company Limited)
3. SUBCONTRACTOR : NISCO
4. RAS : Ruwais Area Service
5. PTW : Permit To Work
6. HSE : Health, Safety and Environment

5 ABBREVIATIONS

1. PPA : Petroleum Ports Authority


2. EIA : Environment Impact Assessment
3. CEMP : Construction Environment Management Plan
4. EAD : Environment Agency Abu Dhabi
5. NOC : No Objection Certificate
6. PTW : Permit to Work
7. PPE : Personal Protective Equipment
8. HSE : Health, Safety & Environment
9. QA/QC : Quality Assurance/Quality Control

6 RESPONSIBLE PERSONS

Name Company Position Mobile Remarks


W.J. Park SECL CM 056-5447985
Anil Nair SECL HSE Manager 056-3049652
Erwin SECL Supervisor 050-5925183
Franz
SECL QC 054-7854313
Campaner
Selva Pandi TAHTAN CM 054-7028670
Muhammad QA/QC
TAHTAN 056-6243293
Ahsan Engineer
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 6 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

7 PLANT EQUIPMENTS & TOOLS

Equipment Unit Remarks


Excavator 1 As per Requirement
Dump Trucks 1 As per Requirement
Water Tanker 1 As per Requirement
Roller Compactor 1 As per Requirement
Plate Compactor 1 As per Requirement
Dewatering pumps (complete As per Requirement
1
accessories)
Concrete Cutter 1 As per Requirement
Compressor w/ Jack As per Requirement
1
Hammer
Generator Set 1 As per Requirement
Mobile Tower Light 1 As per Requirement

8 MANPOWER REQUIREMENTS

EASEMENT Remarks
Designation GREEN ZONE
AREA

Foreman 01 (Man-Days) N/A

Labor 4-6 (Man-Days) N/A

Helpers 6-8 ( Man-Days) N/A

9 PERMIT REQUIREMENTS & COORDINATORS


PERMITS PERFORMERS DESCIPLINE MOBILE PERIOD
Start: Jan
COLD Imran Supervisor (TAH) 054-7028682
01, 2020
End: Jan
HOT Erwin Supervisor (SAM) 050-5925183
30, 2020
Easement Adnan Supervisor (TAH) 050-7028684
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 7 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

10 MATERIALS
 Dune Sand – for bedding
 Concrete – for pavement restoration
 Gatch – for temporary access road

11 SEQUENCE OF ACTIVITIES

11-1.Preliminary Works

 Mobilization of Equipment
 Cable detection
 Protection of Existing Under and Above Ground utilities
 Manual Trial Excavation
 Placing of hard barricades

11-2. 98”GRV Road Closure Location

Road crossing
#5

#1 #4 #2 #3
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 8 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

11-3. Traffic Re-routing

Location Road Detour Remark


1 Required RSI approval is required.
2 Required RSI approval is required.
3 Required RSI approval is required.
4 Not required N/A
5 Not required N/A

11-3-1. Traffic Re-routing (Location #1) October 2019 ~ December 2019

Avenue C

Avenue B

11-3-2. Traffic Re-routing (Location #2) January 2020 ~ February 2020


METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 9 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

Avenue B

Avenue C

11-3-3. Traffic Re-routing (Location #3) March 2020 ~ April 2020


METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 10 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

Avenue B

Avenue C

*For Traffic Control:


 Project Sign Board
 Traffic Sign Boards
 Barricades (Plastic – 2 rows)
 Lighting Device during Night Time
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 11 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

11-4. Schedule of Works

Location Construction period Remark


1 January 2020 ~ February 2020
2 March 2020 ~ April 2020
3 May 2020 ~ June 2020
4 July 2020 ~ August 2020

11-5 Main Works:

11-5-1 Excavation work:

 Inform the Control room (Client) / Construction Manager, Permit to work


activity to start the work at Brown field that includes Road Closure Certificate.
 Existing U/G & A/G pipelines will be protected by placing hard barricades.
 Survey works follows by establishing the course of the excavation to be made by
putting stake outs & necessary required elevation based on the approved
drawings.
 Shifting & relocation of Concrete Barriers that are in the path of trench
excavation.
 The existing facilities shall be identified by cable detector, test pits with
Reference U/G Utility drawings.
 Upon placing the necessary survey markings & stakeouts, hard barricades will
put in place along the road. Put all the required markings & signage for the Road
Closure information including the information of the work to be done. Refer to
the re-routed traffic scheme above.
 Start the cutting of the road by using concrete/asphalt cutting machine. After
cutting 20 linear meters, start the breaking of concrete/asphalt. Consequently
after breaking 20 linear meter of concrete/asphalt pavement, the debris will be
started to remove immediately and cleaned out from the work / construction site.
 Manual Trial excavation will be done up to 2.0 meter deep every 20 meter
segments. Excavation will be carried out with proper care to avoid damaging
unforeseen existing underground facilities not detected during the cable
detection work.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 12 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

 Every 1m deep reaching by manual trial excavation, the Company will be


informed to conduct site inspection prior to start the mechanical excavation.
 When & if there is cave-in of the wall of the trench due to soft soil & or of
dewatering works, stop the excavation work and put trench wall protection. Refer
to the drawing for the trench wall protection.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 13 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

 The excavated materials will be placed minimum 1.5 meters away from the
trench. The spoilage or the excess materials that is no longer needed for back
filling will be disposed in the designated disposal area. In road closure area
excavated soil excess materials will be removed immediately from the road.
 Proper hard barricades will be placed around the excavated area and put
necessary signage and warnings day & night.
 Upon reaching the required elevation, raise a final inspection in order to start the
next activity.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 14 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

11-5-2 Dewatering Plan (Utilization of Well Point System & Direct Suction Pump)

 When water encounters during the course of excavation, put in place the
dewatering system and dispose the water in the Company approved designated
disposal area. Refer to the drawing above.
 During the manual trial excavation and upon reaching to the ground water table,
the Well Point Dewatering System will be put in place.
 The sequence of the excavation will continue using mechanical excavation up to
the required depth.
 If the well point dewatering system is not enough to contain the water, a ditch will
be excavated at the edge of the trench for the direct water pump suction as
shown in the drawing above.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 15 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

11-5-3 Dewatering Route

#5

#2 #3
#4
#1
Sedimentation Tank
Temporary flow line
Existing M/H
(Storm Drain Manhole)

 The existing Storm Drain Manhole along the Corniche Road will be used for the
disposal of water taken from the trench excavation. Refer to the drawing above.
 The usage of the Storm Drain Manhole will be scheduled accordingly in order to
avoid overflowing in the manhole.
 The schedule of the usage of Storm Drain Manhole will be based on the road
crossing excavation schedule.
 On the excavation of Road Crossing #5, dewatering of the trench will be directly
disposed in the sea as the location is adjacent to the seashore line.
 All water that is taken from the trench will be directly going to the sedimentation
tank before it will be disposed in the Existing Storm Drain Manhole along the
Corniche Road shown in the drawing above.
 Regular maintenance clean-up will be done on the sedimentation tank from silt &
sand in order to avoid contamination and clogging in the Storm Drain Manhole.
 Approval from the Ruwais Service Integration (RSI) will be needed and granted
for the usage of the Storm Drain Manhole prior to work commencement.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 16 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

11-5-4 Specification of dewatering pumps is as follows:

S/N Description Quantity (Set)


1 Direct Suction Pump 3
2 Well Point System Pump 3

Engine Driven Water Pump (Diesel)

Inlet & Outlet Diameter - 6 inches


Discharge - 30 ~ 330 cu.m/hr
Head - 34 m
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 17 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

11-5-4 Sand Bedding:

 Upon raising final inspection to check the required excavation elevation, survey
check will be confirmed by the proper authorities. When the elevation of the
trench is confirmed, sand bedding will be placed in the trench. The excavator will
evenly place the sand in the trench. The sand bedding will be compacted w/in
the designed elevation placed and compacted in specified layers.

 After the bedding compaction, again, raise a final survey inspection.

11-5-5 Final Survey (Prior to Pipe Laying):


 Final survey inspection of the sand bedding will be conducted prior to installation
& pipe laying.

11-5-6 Backfilling:

 Prior to the start of the backfilling work, the preceding activities shall be insured
with approved inspection; pipe laying, warning tape installation, protection layer
etc.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 18 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

 The backfilling shall be done using the approved materials. The backfill materials
should be screened excavated soil for up to the top of pipe. And from top of the
pipe to the ground level, screened sand materials. Refer to the drawing below.

 Backfilling work will commence upon getting clearance from the preceding
activities with the concern authorities.
 After laying the pipes, a layer of 200mm thickness shall be placed using the
approved backfill materials and it will be compacted up to 95% using plate
compactor or equivalent. Inspection will be done every 200mm layer of
compacted backfill. This procedure will be done up the top of the pipe.
 From the top of the pipe going up to the existing ground level, the backfill
materials to be used will be screened sand which is free from mixing with stone.
Water compaction will be done on the sand backfill.
 Upon reaching the required elevation of backfill, again inspection will be done on
the backfilling work.

11-5-7 Restoration of the Asphalt Road Pavement:

 After the approval of final inspection of the backfilling, 150mm sub-base


materials (Gatch) will be placed on top of the backfilling level. The gatch material
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 19 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

will be placed evenly and it will be compacted to 95% maximum dry density as
per ASTM D1557.
 The 250mm Base coarse materials will be placed after the inspection of the sub-
base materials. The base course will also be placed evenly and it will be
compacted 95% maximum dry density. Inspection will be conducted once
prepared.
 Raise inspection prior to Asphalt Pavement of the road restoration. Upon
approval of the base preparation, prime coat will be applied on the base course
in preparation for Asphalt Pavement. After 24 hours of prime coat application,
asphalt binder course will be placed.
 The asphalt binder course will be rolled & compacted. Once compacted, tact coat
will be sprayed evenly on the binder course. The asphalt wearing course will be
placed & compacted. Refer to the drawing below.
METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 20 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

12 ATTACHMENTS (DRAWINGS)

 LOCATION OF 98’’ GRV PIPELINE ROAD CROSSING:


METHOD STATEMENT FOR
UNDERGROUND EXCAVATION AND
ROAD CROSSING FOR 98” GRV PIPELINE
COMPANY Doc. No. : 6143-MS-CU-061
Class 1 Rev A Page: 21 of 21
CONTRACTOR Doc. No. : SO6044-CA0P-MTD-4000-061

13 TASK RISK ASSESSMENT:

- To be submitted separately