Professional Documents
Culture Documents
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
1 OF 11
IRAQ GATES CONTRACTING COMPANY
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
2 OF 11
IRAQ GATES CONTRACTING COMPANY
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
1 Purpose
To mitigate the issue of voltage variation and power demand in future, it is proposed to destruct the
existing 4 x 12MVA incoming transformers, TMM 1.1 A/B and TMM 1.2 A/B and install replacement 4 x
15MVA transformers complete with on load automatic tap changer and all ancillary equipment.
2 References
3 Definitions/Abbreviations
3.1 DEFINITIONS:
3.2 ABBREVATIONS:
3 OF 11
IRAQ GATES CONTRACTING COMPANY
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
Electrical engineer
Overall vision for the work and coordination with all departments and client to check the work are
executed according to SOW, client specifications by applying of all HSE and quality requirements.
Overall vision for the work and coordination with all department and client to check the work are
executed according to SOW, client specifications by applying of all HSE and quality requirements.
Site Supervisor
Follow-up execution of work activities in daily base by coordination with HSE supervisor, logistic
team and QC inspector.
Preparation & reviewing of Method Statement and JHA/ Risk Assessment with HSE Advisor.
Reporting to mechanical engineer.
HSE Advisor
Preparation & reviewing of Method Statement and JHA/ Risk Assessment with Mechanical
Supervisor.
Coordinate with HSE supervisor for providing of all HSE requirements as per site conditions.
Follow-up with client.
Reporting to Mechanical engineer.
Workers
Performing of all activities as per approved method statement and according to HSE and Quality
requirements.
Reporting to site supervisor.
5 Scope of work
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
b. Equipment’s shall be tested and calibrated, for each device should have valid BGC inspection
certificate.
f. Print and fill all the applicable CSSS for this task before and during the execution of the work.
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
1. Coordinate with Operations & Electrical Maintenance team to perform isolation for TMM1.1A feeder and
incomer and ensure LOTO system is applied, all primary and secondary cables to be proved DEAD
before works begin – EPTW must be issued prior to any work on TMM1.1A being carried out.
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
Disconnecting of 3.3KV and 33KV power cables from transformer TMM1.1A and existing SWGRs
(HS1, MS1.1A) sides
Transformer lifting method statement will be detailed and submitted separately by lifting team
Ensure orientation of 33kV and 3.3kV terminations for new transformer as per approved layout
Lifting plan shall be prepared for destructing and installation of NERs – to be submitted separately
Cable glanding and termination for LV power and control cables at transformer, DBs, new/old
MS1.1A and HS1 using power and hand tools
Cable glanding and termination for 3.3kV cables from transformer, NER and SWGR side by using
power and hand tools and MV certified and approved Cable Jointers
Cable glanding and termination for 33kV cables from transformer and SWGR side by using power
and hand tools and MV certified and approved Cable Jointers
Reconnect of earthing cables
Cable Jointer Certificates to be attached to Method Statement
7 OF 11
IRAQ GATES CONTRACTING COMPANY
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
EQUIPMENT
Electrical Hand tools
Power tools
Crane
Hiab
9 Required Training
CSE training
8 OF 11
IRAQ GATES CONTRACTING COMPANY
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
10 HSE
10.1 HSE Requirements
1- Continuous gas test monitoring is required for CSE work.
2- EPTW and/or PTW need to be in pace along with all required documents (JHA,
MOS, Gas Test certificate, TBT sheet, hot work checklist, etc.)
3- Ensure sufficient supervision on the activities.
4- Equipment and tools need to be inspected and tagged as required and in good
condition.
5- Personnel will comply with all PPE requirements.
6- Ensure using the appropriate tools.
7- Barricade each activity area c/w Safety Signs.
8- Housekeeping.
CSSS Inspections will be carried out using the CSSS Check sheets. Check sheets used will
be relevant to the tasks being conducted and will be decided by the HSE Site Supervisor.
Completed check sheets to be filed by the KAZ HSE Lead.
Task Risk Identification Cards will be completed as part of the Permit to Work. These will be
used to drive and record the toolbox talks.
10.4 PPE
All personnel are required to wear standard PPE at all times on the worksite which will
consist of:
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
Personnel will also wear necessary PPE as identified by the JHA or changing site conditions.
PPE must be inspected by the users prior to every use and discarded if found to be
unserviceable. Additional stocks of PPE will be maintained at the KAZ IGCC Camp and may
be obtained through the KAZ HSE Lead.
All incidents requiring treatment will be reported to the KAZ HSE Lead for investigation and
reporting through the appropriate procedures.
First aider will check the contents of the first aid kit on a weekly basis and record the check on
the enclosed check sheet.
Upon hearing the plant alarm all personnel are to evacuate to the safest KAZ Plant
Emergency Muster point and assemble for a headcount.
Fire on the worksite – Raise the alarm by calling EROC on 07809 213 970, attempt to fight
the fire if trained and comfortable, if the fire is too large and intense muster at the worksite
muster point for a head count then evacuate to the safest KAZ Plant Emergency Muster Point.
All personnel are to be made aware of the emergency arrangements upon initial arrival at
site. Emergency drills will be conducted at the worksite as scheduled by the KAZ HSE Lead.
11 Attachment
7100-IGCC-N003-ISGP-G00000-EA-4816-00035 Rev.01R
Doc.No.IGCC-BGC-ELE-MOS-1779 Doc. EXT
11 OF 11