MMC GAMUDA KVMRT (T) SDN. BHD.
James Whorlow
Reviewed By General Manager – QA/QC, Risk & SA 13.04.20
AMENDMENT HISTORY
REVISION
DETAILS OF AMENDMENT
NO.
00 First Issue
TABLE OF CONTENTS
1. PRELIMINARIES ..................................................................................................................................... 4
1.1. Purpose ......................................................................................................................................... 4
1.2. Scope ............................................................................................................................................. 4
1.3. References .................................................................................................................................... 4
1.4. Definitions ..................................................................................................................................... 5
2. MANPOWER AND EQUIPMENT............................................................................................................. 6
2.1 Manpower..................................................................................................................................... 6
2.2 Equipment ..................................................................................................................................... 6
3. TEST SETUP AND PROCEDURE .............................................................................................................. 6
3.1 Test Setup ..................................................................................................................................... 6
3.2 Test Procedure .............................................................................................................................. 6
3.3 Test Result ..................................................................................................................................... 7
3.4 Post-Test Procedure ...................................................................................................................... 7
4. NECESSARY TEST REQUIREMENTS ........................................................................................................ 7
4.1 QAQC Documentation .................................................................................................................. 7
4.2 Safety ............................................................................................................................................ 7
4.3 Communication ............................................................................................................................. 7
4.4 Test and Commissioning Spares ................................................................................................... 7
5. PARTIAL ACCEPTANCE TEST (PAT) - INSPECTION RECORD SHEET (PATIR) ........................................... 8
1. PRELIMINARIES
1.1. Purpose
The test procedure describes how the PAT (Partial Acceptance Test) will be conducted for earthing and
bonding to ensure that the equipment / system operates satisfactorily as per the functional and safety
requirements stipulated in the Contract Documents and Approved Drawings.
The test procedure describes the following:
• Test resources, equipment, setup, procedures and requirement/ criteria of the PAT to ensure the
M&E equipment performs in an efficient, safe, reliable manner and to ensure the M&E equipment is
ready to be integrated with the rest of the system.
• PAT Inspection Record
1.2. Scope
The scope of this PAT covers the following:
• The Earthing Cable/Tapes will be tested using standard Multimeter and will be recorded in PAT
Inspection Record.
1.3. References
Material and Workmanship Specification
• SSP-MRTC-GENE-OVPR-SCP-03501 – General
• SSP-MRTC-GENE-OVPR-SCP-03528 – Earthing System
Project Quality Plan
• SSP-MGKT-UNGW-OVPR-PLN-00013
Method Statement
I. Installation Earthing System for Station and Ancillary Buildings
SSP-MGKT-UNGW-OVPR-MST-00528
SSP-MGKT-UNGW-OVPR-PLN-00537
1.4. Definitions
PICO - Post Installation Checkout
M&E - Mechanical and Electrical Building Services
PAT - Partial Acceptance Test
SAT - Site Acceptance Test
T&C - Testing and Commissioning
TCS - Turnkey Contractor Supervision
2.2 Equipment
Equipment Function
Multimeter Tester (Fluke 1630 or Equivalent) To provide field measurement
with valid calibration certificate
1. Connect one of the multimeter test leads to the earthing / bonding conductor using a suitable
earth clamp
1. Connect one of the multimeter test leads to the earthing / bonding conductor using a suitable
earth clamp
4. A conductive path is formed and the multimeter (buzzer mode) will beep / read to zero or nearly to
zero
5. Repeat this test for the full length of the earthing / bonding conductor.
4.2 Safety
If the working environment falls withing the following conditions, the following safety cautions
need to be followed
4.3 Communication
• Dependent on the location / area the cables is located in, radio communication may be
required
Shop Drawings
# Reference No Revision No
MRI
# Reference No Description
Calibration Certificate
# Equipment Expiry Date
PrePAT Requirements/Checklist
# Check Item Results
1 10mm² bare copper cables and 25x3mm copper tape are isolated from
earth bar during continuity test
2 2.5 mm² earth bonding to i.e. landing valves, pipes, tunnel lighting
fittings, tunnel socket panels are isolated during continuity test.
3 During each test, respective 70mm² cable shall be connected to the
10mm² bare copper cable and 25mm x 3mm copper tape. All other
70mm² cable to be isolated.
Responsibilities
Subcontractor
# Check Item Name Signature Contact No Email
1 T&C Engineer
F1.319235: M&E T&C PAT Earthing and Bonding (version 5.6) Page 1 of 2
# Check Item Name Signature Contact No Email
2 T&C Manager
3 Wireman
4 SHE
5 Others
F1.319235: M&E T&C PAT Earthing and Bonding (version 5.6) Page 2 of 2