MMC-GAMUDA KVMRT (T) SDN BHD

PROJEK MASS RAPID TRANSIT LALUAN 2 :


SG. BULOH-SERDANG-PUTRAJAYA
UNDERGROUND WORKS

PARTIAL ACCEPTANCE TEST (PAT) PROCEDURE


FOR EARTHING AND BONDING

Reference No. : SSP-MGKT-UNGW-OVPR-PRO-00236


Revision : 00
Date : 20th MARCH 2020
Action Name & Position Signature
Turnkey Contractor’s Supervision (TCS)
Reviewed By:

Reviewed By
DDC / SIC:
MMC GAMUDA KVMRT (T) SDN. BHD.

Approved By Goh Chee Young


Deputy Project Director

James Whorlow
Reviewed By General Manager – QA/QC, Risk & SA 13.04.20

Reviewed by Chris Fenton


General Manager – SHE

Reviewed By Ian Donohue


General Manager – M&E

Paul Leong Kim Peow (Senior


Reviewed By
Manager – M&E)
Muhammad Farid Khosim /
Prepared by Nabilah Suhailah
Senior Engineer / Engineer – M&E

MMC GAMUDA KVMRT (T) SDN. BHD. Page 1 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
PARTIAL ACCEPTANCE TEST (PAT)
PROCEDURE FOR EARTHING & BONDING

AMENDMENT HISTORY
REVISION
DETAILS OF AMENDMENT
NO.
00 First Issue

MMC GAMUDA KVMRT (T) SDN. BHD. Page 2 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
PARTIAL ACCEPTANCE TEST (PAT)
PROCEDURE FOR EARTHING & BONDING

TABLE OF CONTENTS
1. PRELIMINARIES ..................................................................................................................................... 4
1.1. Purpose ......................................................................................................................................... 4
1.2. Scope ............................................................................................................................................. 4
1.3. References .................................................................................................................................... 4
1.4. Definitions ..................................................................................................................................... 5
2. MANPOWER AND EQUIPMENT............................................................................................................. 6
2.1 Manpower..................................................................................................................................... 6
2.2 Equipment ..................................................................................................................................... 6
3. TEST SETUP AND PROCEDURE .............................................................................................................. 6
3.1 Test Setup ..................................................................................................................................... 6
3.2 Test Procedure .............................................................................................................................. 6
3.3 Test Result ..................................................................................................................................... 7
3.4 Post-Test Procedure ...................................................................................................................... 7
4. NECESSARY TEST REQUIREMENTS ........................................................................................................ 7
4.1 QAQC Documentation .................................................................................................................. 7
4.2 Safety ............................................................................................................................................ 7
4.3 Communication ............................................................................................................................. 7
4.4 Test and Commissioning Spares ................................................................................................... 7
5. PARTIAL ACCEPTANCE TEST (PAT) - INSPECTION RECORD SHEET (PATIR) ........................................... 8

MMC GAMUDA KVMRT (T) SDN. BHD. Page 3 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
PARTIAL ACCEPTANCE TEST (PAT)
PROCEDURE FOR EARTHING & BONDING

1. PRELIMINARIES
1.1. Purpose
The test procedure describes how the PAT (Partial Acceptance Test) will be conducted for earthing and
bonding to ensure that the equipment / system operates satisfactorily as per the functional and safety
requirements stipulated in the Contract Documents and Approved Drawings.
The test procedure describes the following:
• Test resources, equipment, setup, procedures and requirement/ criteria of the PAT to ensure the
M&E equipment performs in an efficient, safe, reliable manner and to ensure the M&E equipment is
ready to be integrated with the rest of the system.
• PAT Inspection Record

1.2. Scope
The scope of this PAT covers the following:

• The Earthing Cable/Tapes will be tested using standard Multimeter and will be recorded in PAT
Inspection Record.

1.3. References
Material and Workmanship Specification
• SSP-MRTC-GENE-OVPR-SCP-03501 – General
• SSP-MRTC-GENE-OVPR-SCP-03528 – Earthing System
Project Quality Plan
• SSP-MGKT-UNGW-OVPR-PLN-00013

Project Safety & Health Plan


• SSP-MGKT-UNGW-OVPR-PLN-00014

Environmental Management Plan


• SSP-MGKT-UNGW-OVPR-PLN-00009

Project Emergency Preparedness & Response Plan


• SSP-MGKT-UNGW-OVPR-PLN-00007

Project Management Plan – (Inspection Plan)


• (PMP) MGKT-QSHE-PRO-0019
• (PMP) MGKT-QSHE-PRO-0020

Method Statement
I. Installation Earthing System for Station and Ancillary Buildings
SSP-MGKT-UNGW-OVPR-MST-00528

Inspection Test Plan

MMC GAMUDA KVMRT (T) SDN. BHD. Page 4 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
PARTIAL ACCEPTANCE TEST (PAT)
PROCEDURE FOR EARTHING & BONDING

SSP-MGKT-UNGW-OVPR-PLN-00537

1.4. Definitions
PICO - Post Installation Checkout
M&E - Mechanical and Electrical Building Services
PAT - Partial Acceptance Test
SAT - Site Acceptance Test
T&C - Testing and Commissioning
TCS - Turnkey Contractor Supervision

MMC GAMUDA KVMRT (T) SDN. BHD. Page 5 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
MMC-GAMUDA KVMRT (T) SDN BHD

2. MANPOWER AND EQUIPMENT


2.1 Manpower

Designation Roles and Responsibilities


T&C Manager/ Engineer To plan and arrange for test activities
Wireman To carry out the tests
Skilled/ General Workers To assist wireman
TCS To inspect and verify the tests

2.2 Equipment
Equipment Function
Multimeter Tester (Fluke 1630 or Equivalent) To provide field measurement
with valid calibration certificate

3. TEST SETUP AND PROCEDURE


3.1 Test Setup
1. All earthing and bonding conductors have been correctly installed and terminated as per the
drawings.
2. Set the multimeter to the correct ohms range
3. Check the multimeter reads zero when the multimeter leads are connected together

3.2 Test Procedure


EARTHING / BONDING TEST TO EARTH

1. Connect one of the multimeter test leads to the earthing / bonding conductor using a suitable
earth clamp

2. Connect the other multimeter test lead to the earth terminal


3. The multimeter should be reading less than 1 ohms

Earthing / Bonding Continuity Test

1. Connect one of the multimeter test leads to the earthing / bonding conductor using a suitable
earth clamp

2. Connect the other multimeter test lead to a parallel running cable


3. Temporary connect the other end of the parallel running cable to the earthing / bonding conductor
further down its length

MMC GAMUDA KVMRT (T) SDN. BHD. Page 6 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
PARTIAL ACCEPTANCE TEST (PAT)
PROCEDURE FOR EARTHING & BONDING

4. A conductive path is formed and the multimeter (buzzer mode) will beep / read to zero or nearly to
zero

5. Repeat this test for the full length of the earthing / bonding conductor.

3.3 Test Result


1 If the buzzer of multimeter is active once the conductive path is formed and the resistance value is
less than 1 Ohm, the PAT is considered PASS.

3.4 Post-Test Procedure


1. In the event test failed, the following steps need to be taken
a. Test the cable/equipment for any defects
b. Replace the cable/equipment
c. Re-inspection will be done

4. NECESSARY TEST REQUIREMENTS


4.1 QAQC Documentation
• PICO Inspection Record and snags have been closed accordingly.

4.2 Safety
If the working environment falls withing the following conditions, the following safety cautions
need to be followed

Potential Hazards Hazard Control

Electric Shock The earthing installation shall be tested


independently as a system and not connected
to any equipment/systems with potential
earth faults

4.3 Communication
• Dependent on the location / area the cables is located in, radio communication may be
required

4.4 Test and Commissioning Spares


• Not Applicable

MMC GAMUDA KVMRT (T) SDN. BHD. Page 7 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
MMC-GAMUDA KVMRT (T) SDN BHD

5. PARTIAL ACCEPTANCE TEST (PAT) - INSPECTION RECORD SHEET (PATIR)

MMC GAMUDA KVMRT (T) SDN. BHD. Page 8 of 8


SSP-MGKT-UNGW-OVPR-PRO-00236, Rev00
M&E T&C PAT Earthing and Bonding
Form Reference F1.319235
Owned By Nabilah Suhailah Zahrullail (MGKT_SSP_MRT_Line2)
Date 4/7/2020 2:07:59 PM
Status Open
Project Name T&C Testing Project
Project Reference Testing for inter and intra project data
Project Address
Client Project Reference
Location T&C Testing Project

PAT Procedure No. SSP­MGKT­UNGW­OVPR­PRO­00236


MGKT RFI No
Date & Time of Inspection
Description (STN,LVL,Zone,Room)
Level
Room
Grid Line/Chainage
System
Subsystem
Equipment

Material Submission Approval


# Reference No Revision No

Shop Drawings
# Reference No Revision No

MRI
# Reference No Description

Previous Procedures ­ Test Results


# Check Item Document Status
1 FAT
2 PICO

Calibration Certificate
# Equipment Expiry Date

Pre­PAT Requirements/Checklist
# Check Item Results
1 10mm² bare copper cables and 25x3mm copper tape are isolated from
earth bar during continuity test
2 2.5 mm² earth bonding to i.e. landing valves, pipes, tunnel lighting
fittings, tunnel socket panels are isolated during continuity test.
3 During each test, respective 70mm² cable shall be connected to the
10mm² bare copper cable and 25mm x 3mm copper tape. All other
70mm² cable to be isolated.

Continuity Test Result


# Cable Tag / No. Test Results

Inspection outcome / Code allocated


Status

Responsibilities

Subcontractor
# Check Item Name Signature Contact No Email
1 T&C Engineer

F1.319235: M&E T&C PAT Earthing and Bonding (version 5.6) Page 1 of 2
# Check Item Name Signature Contact No Email
2 T&C Manager
3 Wireman
4 SHE
5 Others

MGKT, TCS & MRTC


# Check Item Name Signature Contact No Email
1 T&C Engineer
2 TCS
3 Witness 1
4 Witness 2
5 Witness 3

F1.319235: M&E T&C PAT Earthing and Bonding (version 5.6) Page 2 of 2