You are on page 1of 7

METHOD STATEMENT FOR DELTA/M/S/Cable Jointing and

PROJECT: DOC NO.:


Construction of 115/13.8kV CABLE JOINTING AND Termination-01
Al Uqair Substation A&B TERMINATION
CN#: 44000011574 REV. NO.: 00

CLIENT: NATIONAL GRID SA DATE: March 25, 2019

METHOD OF STATEMENT FOR


CABLE JOINTING AND TERMINATION
METHOD STATEMENT FOR DELTA/M/S/Cable Jointing and
PROJECT: DOC NO.:
Construction of 115/13.8kV CABLE JOINTING AND Termination-01

CN#:44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00

CLIENT: NATIONAL GRID SA DATE: March 25, 2019

TABLE OF CONTENTS
1.0 PURPOSE ........................................................................................................................................................................ 3
2.0 SCOPE ............................................................................................................................................................................. 3
3.0 REFERENCES ................................................................................................................................................................... 3
4.0 TOOLS AND EQUIPMENT’S ............................................................................................................................................. 3
5.0 RESPONSIBILITIES OF KEY PERSONNEL .......................................................................................................................... 3
5.1. Project Manager ........................................................................................................................................................ 3
5.2. Site Manager.............................................................................................................................................................. 4
5.3. Safety Engineer .......................................................................................................................................................... 4
5.4. Safety Officer ............................................................................................................................................................. 4
5.5. QA/QC Engineer......................................................................................................................................................... 4
5.6. Site Engineer .............................................................................................................................................................. 5
5.7. Site Foreman .............................................................................................................................................................. 5
6.0 WORK PROCEDURE ........................................................................................................................................................ 5
6.1. Preparation ................................................................................................................................................................ 5
6.2. Cable Preparation ...................................................................................................................................................... 5
6.3. Cable Jointing............................................................................................................................................................. 6
6.3.1. Sliding Silicon Sleeves into Final Position ......................................................................................................... 6
6.3.2. Screen Connection and Housing ....................................................................................................................... 6
6.3.3. Fill in the compound .......................................................................................................................................... 6
7.0 SAFETY ............................................................................................................................................................................ 7

DELTA COMPANY Page 2 of 7 METHOD STATEMENT


METHOD STATEMENT FOR DELTA/M/S/Cable Jointing and
PROJECT: DOC NO.:
Construction of 115/13.8kV CABLE JOINTING AND Termination-01

CN#:44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00

CLIENT: NATIONAL GRID SA DATE: March 25, 2019

1.0 PURPOSE

The purpose of this method statement is to make 110KV Cable jointing (1x1200sq.mm). (Inter
connecting of the single circuit)

2.0 SCOPE

This Method Statement describes the activities and performance of associated quality control
activities related to cable jointing confirming to relevant specifications, documents and local
regulations.

3.0 REFERENCES

General Specification-Cable Jointing.

4.0 TOOLS AND EQUIPMENT’S

 Portable electric Hacksaw and Grinder


 Hand Tool Set
 Heating Mats
 Alignment Rails
 Propane Gas with Torch and Regulator
 Adjustable jack for Cable support
 Chain Block (Pulley)
 Materials for jointing (Compounds, PP housing, sealing tape, shrink sleeves, cap etc...) all are
supplied from approved NG distributer (PFISTERER).

While using all equipment’s, necessary HSE plan and regulation to be adopted as per standards to
give more priority to the safety.

5.0 RESPONSIBILITIES OF KEY PERSONNEL

5.1. Project Manager

The Project manager will be responsible for the timely performance of all excavation works with
compliance with the contract drawings, project specifications and HSE plan. He must mobilize the
appropriate equipment and work force to do the job as required.

DELTA COMPANY Page 3 of 7 METHOD STATEMENT


METHOD STATEMENT FOR DELTA/M/S/Cable Jointing and
PROJECT: DOC NO.:
Construction of 115/13.8kV CABLE JOINTING AND Termination-01

CN#:44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00

CLIENT: NATIONAL GRID SA DATE: March 25, 2019

5.2. Site Manager

The Construction will monitor the acclivities He must take note existing shortfall and problems and
discuss the same with the Project Manager. Corrective solutions must be identified and applied to
compensate for the shortfalls.

5.3. Safety Engineer

 Conduct the safety induction course 10 all personnel involved in the work
 monitor and supervise the risk assessment
 ensure that necessary Permit lo Work is available
 the method statement and risk assessment are understood and
 understood, complied and applied in the worksite
 ensure that all workers are provided with sufficient information regarding workplace hazards
 and planned control measures

5.4. Safety Officer

 Supervision of equipment handling, transportation and disposal of excavated materials


 Ensure that relevant work permit is secured prior to start of work
 Ensure that equipment is operational and certified
 Ensure that all drivers/operators are qualified to operate the machines/ equipment
 Regular inspection and maintenance of the equipment
 Perform other duties as Instructed by the safety engineer

5.5. QA/QC Engineer

 The QA/QC engineer will be responsible for the quality aspects of the works. He will assure that
the QA and QC plan will be implemented.
 The required (RFl’s) shall be submitted to the (Client).
 All required test for existing subgrade, and backfill materials must be done and that all
requirements are complied.
 He will proactively coordinate with the site engineer and issue appropriate internal (Site
Instructions) when he sees that performance of works deviate from the approved.

DELTA COMPANY Page 4 of 7 METHOD STATEMENT


METHOD STATEMENT FOR DELTA/M/S/Cable Jointing and
PROJECT: DOC NO.:
Construction of 115/13.8kV CABLE JOINTING AND Termination-01

CN#: 44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00

CLIENT: NATIONAL GRID SA DATE: March 25, 2019

5.6. Site Engineer

 The Site Engineer will be in charge for the supervision and implementation of all excavation
works as required in the specifications and drawing, especially in giving orders to Site supervisors.
 Site engineer is also in charge for the preparation and filing of reports.

5.7. Site Foreman

 The Site Foreman will be in charge for the supervision and implementation of various excavation
works, as instructed by the Site engineer
 The Site Foreman shall also keep record of all work schedules work production and daily safely
issues

6.0 WORK PROCEDURE

 Work should be carried out by a certified trained and competent jointer aware of all product
requirements and safety practices.
 The jointer must have learnt the correctly intended installation procedure and is responsible to
arrange the site conditions required to install.

6.1. Preparation

 Check the materials are complete and suitable for the cable to be fitted on.
 Check the relevant tools required for the following installation work are available on site.
 Check the site conditions are adequate to provide the correct working environment for the
correct and clean fitting of the product.

6.2. Cable Preparation

 Cable overlapping – Lay the cables in their final position overlapping (Using heating mats and
alignment rails, heat and straighten the cables)
 Check the prepared cable insulation is not flat sided and the eccentricity is within the acceptable
limits according to the requirement.
 Check the diameter of the prepared insulation is within the limits according to the appropriate
parts.

DELTA COMPANY Page 5 of 7 METHOD STATEMENT


METHOD STATEMENT FOR DELTA/M/S/Cable Jointing and
PROJECT: DOC NO.:
Construction of 115/13.8kV CABLE JOINTING AND Termination-01

CN#: 44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00

CLIENT: NATIONAL GRID SA DATE: March 25, 2019

6.3. Cable Jointing

 Marks on cables has been done according to the requirement and locate the silicone sleeve on
final positioning – Cutting and grinding should be done according to the requirement.
 Using gloves apply grease inside the sleeve and over the cable and place a split bucket into the
sleeve and using mounting tool place the silicon sleeve onto cable.
 Mount the (Sicon) torque control connector positioning it with a max. 2mm spacing between the
insulation shoulders on either side.
 Remove carefully temporary protection and ensure associated cable and pre-molded silicone
sleeves are without damage and clean
 Use cover plugs provided for (sicon) torque control connector shear bolts

6.3.1. Sliding Silicon Sleeves into Final Position

 Prepare mounting equipment


 Grease cable with silicon using gloves
 sleeves into final position and remove tape carefully and completely

6.3.2. Screen Connection and Housing

 Make the screen connection and PP Housing


 Apply sealing tape in tow screen seal positions
 Straighten screen wires out around circumferences of cable the silicone sleeves
 Apply sealing tape on outer sheath
 Bend back screen wires over shrink sleeves
 Fix bonding cable connection
 Ensure the incoming bonding cable are sealed against moisture at the compression sleeves as
indicated

6.3.3. Fill in the compound

Compound units Component description Level


Component A White label 1.5 KG 10 mm directly after
Component B White label 14.5 KG filling
Component A 2 Yellow stripped label 0.950 KG 10 mm directly after
Component B 2 Yellow label 9.05 KG filling
After installation sign the complete check sheet

DELTA COMPANY Page 6 of 7 METHOD STATEMENT


METHOD STATEMENT FOR DELTA/M/S/Cable Jointing and
PROJECT: DOC NO.:
Construction of 115/13.8kV CABLE JOINTING AND Termination-01

CN#: 44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00

CLIENT: NATIONAL GRID SA DATE: March 25, 2019

7.0 SAFETY

 All works shall comply with safety procedure or instruction as set in out in project Safety Plan and
Municipality rules and regulation.
 Basic Personal Protective Equipment (PPE) shall be worn by all staff or labors.
 All the work should be carried out under the supervision of Competent Person.
 Always maintain good Housekeeping.

DELTA COMPANY Page 7 of 7 METHOD STATEMENT

You might also like