Professional Documents
Culture Documents
CN#:44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00
TABLE OF CONTENTS
1.0 PURPOSE ........................................................................................................................................................................ 3
2.0 SCOPE ............................................................................................................................................................................. 3
3.0 REFERENCES ................................................................................................................................................................... 3
4.0 TOOLS AND EQUIPMENT’S ............................................................................................................................................. 3
5.0 RESPONSIBILITIES OF KEY PERSONNEL .......................................................................................................................... 3
5.1. Project Manager ........................................................................................................................................................ 3
5.2. Site Manager.............................................................................................................................................................. 4
5.3. Safety Engineer .......................................................................................................................................................... 4
5.4. Safety Officer ............................................................................................................................................................. 4
5.5. QA/QC Engineer......................................................................................................................................................... 4
5.6. Site Engineer .............................................................................................................................................................. 5
5.7. Site Foreman .............................................................................................................................................................. 5
6.0 WORK PROCEDURE ........................................................................................................................................................ 5
6.1. Preparation ................................................................................................................................................................ 5
6.2. Cable Preparation ...................................................................................................................................................... 5
6.3. Cable Jointing............................................................................................................................................................. 6
6.3.1. Sliding Silicon Sleeves into Final Position ......................................................................................................... 6
6.3.2. Screen Connection and Housing ....................................................................................................................... 6
6.3.3. Fill in the compound .......................................................................................................................................... 6
7.0 SAFETY ............................................................................................................................................................................ 7
CN#:44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00
1.0 PURPOSE
The purpose of this method statement is to make 110KV Cable jointing (1x1200sq.mm). (Inter
connecting of the single circuit)
2.0 SCOPE
This Method Statement describes the activities and performance of associated quality control
activities related to cable jointing confirming to relevant specifications, documents and local
regulations.
3.0 REFERENCES
While using all equipment’s, necessary HSE plan and regulation to be adopted as per standards to
give more priority to the safety.
The Project manager will be responsible for the timely performance of all excavation works with
compliance with the contract drawings, project specifications and HSE plan. He must mobilize the
appropriate equipment and work force to do the job as required.
CN#:44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00
The Construction will monitor the acclivities He must take note existing shortfall and problems and
discuss the same with the Project Manager. Corrective solutions must be identified and applied to
compensate for the shortfalls.
Conduct the safety induction course 10 all personnel involved in the work
monitor and supervise the risk assessment
ensure that necessary Permit lo Work is available
the method statement and risk assessment are understood and
understood, complied and applied in the worksite
ensure that all workers are provided with sufficient information regarding workplace hazards
and planned control measures
The QA/QC engineer will be responsible for the quality aspects of the works. He will assure that
the QA and QC plan will be implemented.
The required (RFl’s) shall be submitted to the (Client).
All required test for existing subgrade, and backfill materials must be done and that all
requirements are complied.
He will proactively coordinate with the site engineer and issue appropriate internal (Site
Instructions) when he sees that performance of works deviate from the approved.
CN#: 44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00
The Site Engineer will be in charge for the supervision and implementation of all excavation
works as required in the specifications and drawing, especially in giving orders to Site supervisors.
Site engineer is also in charge for the preparation and filing of reports.
The Site Foreman will be in charge for the supervision and implementation of various excavation
works, as instructed by the Site engineer
The Site Foreman shall also keep record of all work schedules work production and daily safely
issues
Work should be carried out by a certified trained and competent jointer aware of all product
requirements and safety practices.
The jointer must have learnt the correctly intended installation procedure and is responsible to
arrange the site conditions required to install.
6.1. Preparation
Check the materials are complete and suitable for the cable to be fitted on.
Check the relevant tools required for the following installation work are available on site.
Check the site conditions are adequate to provide the correct working environment for the
correct and clean fitting of the product.
Cable overlapping – Lay the cables in their final position overlapping (Using heating mats and
alignment rails, heat and straighten the cables)
Check the prepared cable insulation is not flat sided and the eccentricity is within the acceptable
limits according to the requirement.
Check the diameter of the prepared insulation is within the limits according to the appropriate
parts.
CN#: 44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00
Marks on cables has been done according to the requirement and locate the silicone sleeve on
final positioning – Cutting and grinding should be done according to the requirement.
Using gloves apply grease inside the sleeve and over the cable and place a split bucket into the
sleeve and using mounting tool place the silicon sleeve onto cable.
Mount the (Sicon) torque control connector positioning it with a max. 2mm spacing between the
insulation shoulders on either side.
Remove carefully temporary protection and ensure associated cable and pre-molded silicone
sleeves are without damage and clean
Use cover plugs provided for (sicon) torque control connector shear bolts
CN#: 44000011574
Al Uqair Substation A&B TERMINATION REV. NO.: 00
7.0 SAFETY
All works shall comply with safety procedure or instruction as set in out in project Safety Plan and
Municipality rules and regulation.
Basic Personal Protective Equipment (PPE) shall be worn by all staff or labors.
All the work should be carried out under the supervision of Competent Person.
Always maintain good Housekeeping.