Professional Documents
Culture Documents
1 Scope definition /
2 Objective /
7 Pre-requisite approvals/permits /
9 Preparation /
15 Testing/inspection plan /
Checked by : Reviewed by :
INSTALLATION OF TELECOMMUNICATION
SYSTEM
Revision : 00
Consultant
Approved by Tan Jin Soon (Sepakat Setia
Perunding)
Construction
Reviewed by Ivan Lim Kien Aun
Manager
Sathyan A/L
Prepared by Project Manager
Anbalakan
RWTP
RASAU WATER TREATMENT PLANT
Table of Contents
1.0 SCOPE OF WORKS ................................................................................................................... 2
1.1 General Description .............................................................................................................. 2
1.2 Reference ............................................................................................................................... 2
1.3 Materials ................................................................................................................................. 2
1.4 Plant and Equipment ............................................................................................................ 2
1.5 Manpower............................................................................................................................... 4
1.6 Work Procedures .................................................................................................................. 5
1.6.1 Sequence of Work ................................................................................................................ 5
1.6.2 Installation of Fiber Cabling & Equipment ......................................................................... 6
1.6.3 Installation of Network Switch ............................................................................................. 8
1.6.4 Installation of Access Point (AP) ...................................................................................... 12
1.6.5 Testing & Commissioning ................................................................................................. 16
2.0 SAFETY AND HEALTH REQUIREMENTS ............................................................................. 17
2.1 Job Safety & Health Analysis ............................................................................................. 17
2.2 Information to Personnel .................................................................................................... 17
2.3 Emergency Arrangements ................................................................................................. 17
2.4 Permit Requirements .......................................................................................................... 18
2.5 Housekeeping ...................................................................................................................... 18
3.0 ENVIRONMENTAL ISSUES..................................................................................................... 19
3.1 Environmental Aspects, Impacts & Control Measures ................................................... 19
3.2 Air Quality and Noise Level................................................................................................ 19
3.3 Water Quality ....................................................................................................................... 19
3.4 Waste Management ............................................................................................................. 19
4.0 QUALITY ASSURANCE & QUALITY CONTROL ................................................................... 20
4.1 Contractual Requirements ................................................................................................. 20
4.2 Inspection and Testing ....................................................................................................... 20
5.0 APPENDICES ................................................................................................................................. 21
5.1 Job Safety Analysis................................................................................................................... 22
5.2 Emergency Response Flow Chart ........................................................................................... 23
5.3 Environmental Aspect & Impact Register ............................................................................... 27
5.4 Inspection & Test Plan .............................................................................................................. 28
5.5 QAQC .......................................................................................................................................... 29
1.2 Reference
1) Item 1.1.9.5 – Method Statement, Tender Document Vol 2: Need Statement &
Specifications
1.3 Materials
1.3.1 Materials for Audio Visual System installation include the following:
Item Materials
1. Wall Plug & Screw, Anchor bolt & Nut (M6, M8)
2. Female Type Connector
3. Cable Gland
4. Cable Marker
5. Silicon Sealant
7. Electrician Knife
8. Hacksaw Blade
9. Measuring Tape
10. Flat File
11. Safety Hats, Gloves and Goggles
1.5 Manpower
Item Designation Responsibilities
1. Project Manager Responsible for overall commercial, contractual
and technical performances associated with
specific
projects. Responsible to the Project Manager.
2. Construction Manager Planning, coordinating, scheduling and monitoring
of site activities.
3. Project Engineer Responsible for overall operation including liaison
with service provider.
4. Site Supervisor Supervising site construction activities
5. SHE Officer To control and ensure the Safety, Health and
Environmental is adhere at site.
6. SHE Supervisor Supervising site construction activities, organize
toolbox meeting and prepare all relevant permit
before start work.
7. Environment Manager To monitor and control environmental issue onsite
to ensure compliance to the regulation.
8. Environment Officer Control and ensure all site activities comply with
environmental plans and requirement.
9. Machineries Operator To operate the machineries.
10. Surveyor/Chainman Setting out works.
11. Traffic controller To control ingress and egress of construction traffic
at site.
12. General Worker & Conduct general works at site.
Observers
13. Flagmen To provide high visible to public traffic to slow down
when a crossing the working area.
14. Flagman & Traffic Control To control traffic and avoid public enter to the
workplace
15. Traffic management officer Make sure activity at site adhere to Traffic
Management Plan
Submission to Consultant
for Approval
Approval
Yes
Proceed to Conduit/Trunking
Installation
Installation of Equipment
Result
Fail
Pass
Handover
Optical Distribution Frame is designed for terminating and managing the optical fibre from
outside plant and equipment in the building.
Fibre termination box (FTB) is used for the distribution connection of cable and fibre optic
communication devices. It leads out the optic signal from drop cable to pigtails by splicing in
the box. It can be used for protective connection of cable and layout pigtails, and fibre optic
terminations of optic access network.
All the FTBs are located at the telephone riser by referring to the schematic diagram 1.0 and
2.0.
Fibre wall socket is the termination point for the internal fibre drop cable and act as a
connection point to the subscriber premises equipment. The outlet designed to house up to
two SC simplex type connectors and each FWS is located at +300mm from finish floor level.
i. Set the device on a flat surface which is strong enough to support the entire weight of
the device with all fittings.
ii. Remove the adhesive backing papers from the rubber feet.
iii. Turnover the device and attach the supplied rubber feet to the recessed areas on the
bottom at each corner of the device.
Feet
Bottom of Device
Notch
i. Check the efficiency of the grounding system and the stability of the rack.
ii. Secure the supplied rack-mounting brackets to each side of the device with supplied
screws, as illustrated in the following figure.
Connect an Ethernet port of the switch to the computer by RJ45 cable as the following figure
shows.
RJ45
Cable
SFP/SFP+
Module to
SFP/SFP+ Slot
CLI (Command Line Interface) enables you to manage the switch, thus you can load the CLI
after connecting the PCs or Terminals to the console port on the switch via a cable (an RJ45
console cable is provided, while micro-USB cable is not provided).
Connect the console (RJ45) port of the device with your computer by the console cable as
the following figure shows.
Connect the console (USB) port of the device with your computer by the USB cable
(not provided) as the following figure shows.
The AP can be mounted to the ceiling, the wall, or in a junction box, using the screws in the
package.
All the Structure Cabling/Fiber Optic must use Optical Loss Test Sets (OLTS) for the fibre
testing. Optical loss test sets (OLTS) incorporate a stable source and a meter.
Measurements are made with a two-stage process:
i. First the source power is measured (referenced), then light is put through the device
to be tested, and a second measurement is made. The difference in the
measurements is the device loss.
ii. While the OLTS require two persons to properly test a system (one at each end),
there are automated OLTS units that communicate with each other and allow one
user to change the operating parameters of both units from one end to test the fibre
at different wavelengths. Single-mode is optimized for 1310 nm and 1550 nm
wavelengths.
2.3.5 The organization chart, list of emergency contact person and relevant authorities
with their contact numbers shall be showed in the Notice Board.
2.3.6 In the event of emergency, the site management staffs must evaluate the
situation and commence the necessary procedures as follow:
• Raise the alarm
• Stop works
• Remain composed.
• Make sure notifications of emergency or evacuation are in place for all
workers surrounding the vicinity.
• Make sure all workers are assembled at designated assembly point.
• Make sure first aid kits are prepared at assembly point.
• All workers are told not to leave the assembly point until clear sign is issued.
• Headcount shall be conducted
• First aiders shall attend to the injured workers
• Prepare assessment reports for the losses.
2.5 Housekeeping
Housekeeping is an essential part of SHE for the daily routine. Housekeeping
would include the following items:
• Maintain the access way to all working area.
• Proper material arrangement.
• Park the machineries in orderly manner.
• No littering around the site.
5.0 APPENDICES
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSI
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING BLE
STEPS Y OF MEASURES/ REQ PERSON
Pro Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
babi erity ROL
PxS PXS
lity (S)
(P) Sco Lev Sco Lev
re el re el
1. Mobilizing & Unstable/ soft ground, Supervisor to check 2 3 6 M 3 Put steel plate at the OSHA ‘94 1 3 3 L Engineer /
materials to work uneven access surrounding and prepare soft ground access FMA Supervisor /
area (apply safe access area (BOWEC) Traffic
throughout the 1986 Officer/
whole job Safety
sequence below) personnel
Slip, trip, fall into -Access way clear from 1 3 3 L 4 - OSHA ‘94 - - - - Engineer /
existing drain/manhole obstruction. FMA Supervisor /
-Cover openings with (BOWEC) Safety
sturdy materials. 1986 personnel
2. Transportation Unsafe access / Poor -Use dedicated access for 1 3 3 L 4 - OSHA ‘94 - - - - Engineer /
machinery & access machineries. FMA Supervisor /
material to the -Materials must place (BOWEC) Safety
site away from access way. 1986 personnel
-Inspection of ladder or
scaffold access before
use.
Page 1 of 5
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSI
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING BLE
STEPS Y OF MEASURES/ REQ PERSON
Pro Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
babi erity ROL
PxS PXS
lity (S)
(P) Sco Lev Sco Lev
re el re el
3. Unloading Moving load - Use safety tag line to 2 4 8 M 3,4 -Stack materials OSHA ‘94 1 4 4 L Engineer /
machinery & control suspended load. properly before lift. FMA Lifting
material using -Barricade the lifting/work (BOWEC) Supervisor /
crane/lorry crane area and display warning 1986 Rigger/
signage. Safety
personnel
Defective lifting gears -Inspection of lifting gears 2 4 8 M 3,4 -Remove any OSHA ‘94 1 4 4 L Engineer /
before use. defection lifting gear FMA Lifting
-Colour coding tag for from site. (BOWEC) Supervisor /
inspected lifting gears. 1986 Rigger/
-Operator and rigger to Safety
ensure the lifting gears are personnel
in good condition.
Improper crane -Follow approved permit to 2 4 8 M 3,4 -All crane outriggers OSHA ‘94 1 4 4 L Engineer /
positioning work. must be fully FMA Lifting
-Follow approved Lifting extended. (BOWEC) Supervisor /
Plan. -Use steel plates for 1986 Rigger/
-Check ground condition crane outriggers. Safety
before park, crane / lorry personnel
crane.
4. Installation of Falling from height -Use of safety harness for 2 4 8 M 3,4 -Approved PTW for OSHA ‘94 1 4 4 L Engineer /
Field Devices, all work with fall of 3 working at height. FMA Supervisor /
Switches, meters or more. -Monitoring and (BOWEC) Safety
Page 2 of 5
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSI
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING BLE
STEPS Y OF MEASURES/ REQ PERSON
Pro Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
babi erity ROL
PxS PXS
lity (S)
(P) Sco Lev Sco Lev
re el re el
Unsafe access -Ensure access scaffold 2 3 6 M 3 -Ensure that the OSHA ‘94 1 3 3 L Engineer/Sc
scaffolding/working with inspection tag before foundation of the FMA affolder/Sup
platform use. scaffold access is on (BOWEC) ervisor/
-Ensure the scaffolding is the firm ground. 1986 Safety
erected as per design. personnel
Defective power tools -Check all equipment are 2 2 4 L 4 - OSHA ‘94 - - - - Engineer /
in good condition. FMA Supervisor /
-Check all hoses / (BOWEC) Safety
connectors are in good 1986 personnel
condition.
Page 3 of 5
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIER ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPONSI
SEQUENCE / IDENTIFICATION MEASURES ARCH CONTROL OTHER RATING BLE
STEPS Y OF MEASURES/ REQ PERSON
Pro Sev Risk Rating CONT OPPORTUNITIES (O)
Hazard & Risk P S Risk Rating
babi erity ROL
PxS PXS
lity (S)
(P) Sco Lev Sco Lev
re el re el
Clean up the Poor electrical -Use industrial plugs / 2 3 6 M 3 -All electrical wire OSHA ‘94 1 3 3 L Engineer/Su
flush box that connection cable. must hang up & do not FMA pervisor/
wrapped with -Electrical equipment / expose water. (BOWEC) Safety
masking tape wiring to be inspected / -Check all cables 1986 personnel
(cont.) connected by electrician. before connection.
-Display signages. Work
briefing prior to work start.
6. Test and Falling from height -Use of safety harness for 2 4 8 M 3,4 -Approved PTW for OSHA ‘94 1 4 4 L Engineer /
commissioning all work with fall of 3 working at height. FMA Supervisor /
meters or more. -Monitoring and (BOWEC) Safety
-Use of industrial type supervision. 1986 personnel
ladder. -Provide secured
-Installation of edge anchorage point for
protection. worker to hook the
-Buddy system for working body harness.
using ladder.
Electric shock -Use industrial plugs / 2 3 6 M 3 -Work briefing prior to OSHA ‘94 1 3 3 L Manager /
cable. work start. FMA Engineer /
-Electrical equipment / -Check all cables (BOWEC) Supervisor /
wiring to be inspected / before connection. 1986 Electrician /
connected by electrician. -Cable hangs / not Safety
-Display signages. trailing on ground / in Personnel
water.
Page 4 of 5
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
Page 5 of 5
Rev. No:01 / Date: 18 JAN 2023
RWTP
RASAU WATER TREATMENT PLANT
Fire Emergency
Identifier alert
Major Minor
Emergency
terminates
Debriefing by Conduct
Emergency investigation Finish
commander
Risk: 1. Recommend to conduct work at night or during off peak hours to minimize traffic
- Public complaint disruption.
- Heavy traffic congestion 2. Maintain most number of lanes wherever possible.
3. Reduce number of lanes (only when unavoidable and when all other alternatives
Road closure, lane diversion and
Traffic congestion N 3 2 6 NO Opportunities: have been exhausted) to be design to facillitate contra flow options.
reduction
- NA 4. Provide sufficient warning signs and flagmen at all work areas to facillitate better
traffic flow.
5. Maintain traffic management devices and temporary/ warning signs to ensure
maximum effectiveness in terms of traffic management.
Risk:
1. Inspection by weekly and maintenance of machinery to be conducted regularly to
Legal action by authorities
ensure machines are in good working condition with no leakage.
Oil spillage/ leakage Land contamination A 2 2 4 YES
2. Manually excavate the contaminated area and put into a suitable container and
Opportunities:
must be stored at scheduled waste storage for proper disposal.
- NA
Risk:
- Legal action by authorities
Generation of scheduled waste Immediately clear any spillage on the ground. Scheduled waste will be stored at
Land contamination N 2 2 4 YES
(including disposal of waste) scheduled waste storage area and disposed by licensed contractor.
Opportunities:
- NA
Risk:
Public complaint
1.Mobilisation /
Demobilization (loading/ Opportunities:
unloading of machinery) 1. The machinery will be maintained in good working order to ensure that exhaust
- Regular maintenance of
Generation of black smoke Air pollution N 2 2 4 YES emission is controlled.
machinery
2. Allow only machinery that is in good condition to enter the site.
- Increase life span of machinery
Risk: 1. Speed limits (15km/ hr) and traffic volume restriction within the site area will be
- Public complaint implemented to reduce the dust dispersion.
2. Dampen all access. Water bowser need to standby for watering all the time.
Generation of dust Air pollution N 2 2 4 YES
3. Vehicles transporting earth to be installed with tailgate and covered with tarpaulin.
Opportunities: 4. To wash the construction vehicles wheels at a wash trough facility before leaving
- NA from construction site.
Risk:
Inspection by weekly and maintenance of machinery to be conducted regularly.
- Public complaint
Installation of hoarding or temporary noise barrier. All noise generating equipment
Generation of noise/ vibration noise/ vibration nuisance N 3 2 6 NO
and machinery will be shut down when not in use and work will be conducted within
Opportunities:
approved working hour.
- NA
Risk:
- Public complaint 1. Wash trough to be provided at the site exit with water jet and operator.
Dirtying of public road Public nuissance/ public complaint N 3 2 6 YES 2. Temporary drainage will be constructed to channel surface runoff to silt trap.
Opportunities: 3. Water bowser need to be standy for watering purposes.
- NA
Appendix A
Risk:
- Public complaints Maintenance of machinery to be conducted regulalry and work will be conducted
Generation of noise/ vibration Noise nuissance N 2 2 4 Yes within approved working hour. Installation of hoarding or temporary noise barrier. All
Opportunities: noise generating equipment and machinery will be shut down when not in use.
- NA
Risk:
2. Bracket installation and - Legal action by authorities All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste
Land contamination N 2 1 2 No Construction Waste Management Plan. Open burning is strictly prohibited. Waste
termination (including disposal of waste)
Opportunities: will be disposed at the approved disposal site.
- NA
Risk:
- Public complaint
- Legal action by authorities
Generation of dust Air pollution N 2 2 4 Yes Dampen the work area to reduce dust dispersion
Opportunities:
- NA
Risk:
- Public complaints Maintenance of machinery to be conducted regulalry and work will be conducted
Generation of noise/ vibration Noise nuissance N 2 2 4 Yes within approved working hour. Installation of hoarding or temporary noise barrier. All
Opportunities: noise generating equipment and machinery will be shut down when not in use.
- NA
Risk:
3. Installation of Fibre - Public complaint
Cabling, Network Switch, - Legal action by authorities
Generation of dust Air pollution N 2 2 4 Yes Dampen the work area to reduce dust dispersion
and Access Point
Opportunities:
- NA
Risk:
-Legal action by authorities All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste
Land contamination N 2 2 4 Yes Construction Waste Management Plan. Open burning is strictly prohibited. Waste
(including disposal of waste)
Opportunities: will be disposed at the approved disposal site.
- NA
Appendix A
Risk:
- Public complaints
- Legal action by authorities All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste
Land contamination N 2 2 4 Yes Construction Waste Management Plan. Open burning is strictly prohibited. Waste
(including disposal of waste)
Opportunities: will be disposed at the approved disposal site.
- To reuse/recycle the waste for
other purposes
Signature
Risk Rating
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000031-00 Page 1
ITP FOR INSTALLATION OF TELECOMMUNICATION SYSTEM
Document No. RWTP-GB-M&E-ITP-000031-00
Revision No. 00 Rev. Date 15/03/2024
Signature
Date
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000031-00 Page 2
RWTP
RASAU WATER TREATMENT PLANT
5.5 QAQC
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 1 of 7
Rasau WTP Form detail report
1.9 Material
2. DESCRIPTION OF WORKS
D.O Copy attachment
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. DESCRIPTION OF WORKS
Test certificate copy attachment
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 2 of 7
Rasau WTP Form detail report
4. DESCRIPTION OF WORKS
Test certificate issued to the correct material delivered (refer to material tagging identification)
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. DESCRIPTION OF WORKS
Brand / Type of material as per approved submission
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. DESCRIPTION OF WORKS
Size, length & dimension as per D.O
6.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 3 of 7
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. DESCRIPTION OF WORKS
Color of material (if applicable)
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. DESCRIPTION OF WORKS
Material unloading & delivery plan (any major equipment that require)
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 4 of 7
Rasau WTP Form detail report
9. DESCRIPTION OF WORKS
Condition of material before & after unloading
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
11.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 5 of 7
Rasau WTP Form detail report
11.3 CA Representative
Pass Fail N/A
12.1 Contractor
Pass Fail N/A
12.3 CA Representative
Pass Fail N/A
If any
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 6 of 7
Rasau WTP Form detail report
Remarks: If " Final Inspection" record Fail Status, Please refer to NCR.
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 7 of 7
Rasau WTP Form detail report
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:48 AM UTC+08:00 Page 1 of 5
Rasau WTP Form detail report
1.9 Material
2. Description of works
Check layout & cable routing according to approved construction drawing.
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. Description of works
Check all material brand and type are according to Approved Equipment and Material List.
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:48 AM UTC+08:00 Page 2 of 5
Rasau WTP Form detail report
4. Description of works
Fibre Wall Socket. Please describe the number of units, brand and model in reference at note section.
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. Description of works
Socket Outlet. Please describe the number of units, brand and model in reference at note section.
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. Description of works
Equipment in item 1-4 is properly installed and wired in accordance with endorsed schematic diagram.
6.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:48 AM UTC+08:00 Page 3 of 5
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. Description of works
Labelling are done and are endorsed type in accordance with the specification.
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. Description of works
The surface wiring / conduit accessories is properly installed and arranged in a neat and tidy manner.
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:48 AM UTC+08:00 Page 4 of 5
Rasau WTP Form detail report
9. Description of works
Record the result and test result during termination works to FWS & Socket Outlet (refer to attached test
report).
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:48 AM UTC+08:00 Page 5 of 5
Rasau WTP Form detail report
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:50 AM UTC+08:00 Page 1 of 6
Rasau WTP Form detail report
1.9 Material
2. Description of works
Check layout & cable routing according to approved construction drawing.
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. Description of works
Check all material brand and type are according to Approved Equipment and Material List.
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:50 AM UTC+08:00 Page 2 of 6
Rasau WTP Form detail report
4. Description of works
Fibre Termination Box. Please describe the number of units, brand, and model on Note in the Reference
section.
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. Description of works
Optical Distribution Frame. Please describe the number of units, brand, and model on Note in the
Reference section.
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. Description of works
Equipment in item 1-4 is properly installed and wired in accordance with endorsed schematic diagram.
6.1 Contractor
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:50 AM UTC+08:00 Page 3 of 6
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. Description of works
Labelling are done and are endorsed type in accordance with the specification.
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. Description of works
Check for proper alignment of fibre run and check all fibre termination. Ensure all fibre dree up in order
and securely terminated to equipments.
8.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:50 AM UTC+08:00 Page 4 of 6
Rasau WTP Form detail report
8.3 CA Representative
Pass Fail N/A
9. Description of works
The surface wiring / conduit accessories is properly installed and arranged in a neat and tidy manner.
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:50 AM UTC+08:00 Page 5 of 6
Rasau WTP Form detail report
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 11:50 AM UTC+08:00 Page 6 of 6