Professional Documents
Culture Documents
PERMISSION TO PROCEED SHALL NOT CONSTITUTE ACCEPRANCE OR APPROVAL OF DESIGN DETAILS, CALCULATIONS,
ANALYSIS, TEST METHOD, OR MATERIALS DEVELOPED OR SELECTED BY CONTRACTOR AND SHALL NOT RELIEVE
CONTRACTOR FROM FULL COMPLIANCE WITH CONTRACT TECHNICAL SPECIFICATIONS AND DRAWINGS.
SEB___________________________ DATE__________________
[PROJECT DETAIL]
LIMBANG TOWN 275/33/11kV SUBSTATION
Method Statement
for
Project Information –
PROJECT TITLE: LIMBANG TOWN 275/33/11kV SUBSTATION
List of Content
Contents
1 TITLE ............................................................................................................................................................................... 3
2 REFERENCE ..................................................................................................................................................................... 3
3.2 MATERIALS..................................................................................................................................................................... 3
1 TITLE
Method statement for Compound Stone Topping.
2 REFERENCE
Drawing / Documents
3 SCOPE OF WORK
This Method Statement is to outline the work methodology for compound stone topping carried out in
Limbang Town 275/33/11kV Substation. The aim of this method statement is to ensure that all the
activities within the site boundary are carried out in accordance with specification and smoothly.
The procedures developed herein however, do not in any way supersede the procedures as specified
in the Contract drawings and specification. Any revised procedure shall be approved by Employer prior
to actual work on site.
3.1 MACHINERY AND EQUIPMENT
Item Materials
1 Gravel 16mm to 40mm
Doc No.: PLS160199-LBT-C-MST-CR-0002
METHOD STATEMENT FOR
COMPOUND STONE Pages Page 4 of 13
TOPPING Revision 0.2
1) Source for crushed stone for compound stone topping material and carry out testing for the
material by third party on the suitability of material.
2) All relevant underground cabling works shall be completed before laying of gravel topping
GROUND PREPARATION
1) The ground shall be prepared and compacted to level as per IFC drawing prior to lay compound
stone topping.
2) All compaction shall be carried out with 0.5t plate compactor. Once the formation base has been
prepared, it is closed to all construction traffic.
1) Lime stone gravel with 16mm to 40mm size shall be used as compound stone topping material.
The material shall be sent for quality testing before used.
2) The level of compound stone topping shall be joint surveyed by client and approved by QAQC
engineer.
3) Survey and setting out pegging for ground level and gravel topping level shall be done by qualified
surveyor and properly marked.
4) 200mm thick compound stone topping to be lay by excavator according to the designed level.
5) If there is any case excavation works to be carried out at the completed area, canvas shall be used
within the area to prevent the soil debris/dirt contaminate the gravel.
Doc No.: PLS160199-LBT-C-MST-CR-0002
METHOD STATEMENT FOR
COMPOUND STONE Pages Page 5 of 13
TOPPING Revision 0.2
- Organisation Chart
Project Manager
Ashwin Kumar
Licensed Surveyor
WLS Survey Services
Construction
Safety & Health
Manager
Officer
Bernard Hon Shau
Elvis
Wei
Site Supervisor
Lancai Ak Badan
6 SAFETY FORMS
6.1 TOOL BOX TALK FORM
Controlled by: (KEC / Subcon. Supervisor) Conducted by: (Subcon. Supervisor / worker)
(Name & Sign) (Name & Sign)
Emergency Vehicle & Driver Number: Verified by (KEC Supervisor):
1. (Name and Sign)
2. Project:
Do you feel / suffer any of the following ailment today? (Adakah anda merasa / menderita mana-mana penyakit berikut hari ini?)
1. Fits 2. body pain 3.Mental Depression 4.Headache 5. Cough chest pain 6.Nausea / Dizziness
7. Any infection 8.High Fever 9. Breathlessness 10. Influenza 11. Any Other
Declaration:
I / We hereby declare that information furnished by me / us is true and correct. I / We, am / are not under the influence of alcohol and
other debilitating substance and fit for work today.
(Saya / Kami mengaku bahawa maklumat yang diberikan oleh saya / kami adalah benar dan betul. Saya / Kami, saya / tidak berada di
bawah pengaruh alkohol dan bahan melemahkan lain dan sesuai untuk bekerja hari ini)
Full Name Fit for job Sign. Full Name Fit for job Sign.
today (Y/N) today (Y/N)
1. 9.
2. 10.
3. 11.
4. 12.
5. 13.
6. 14.
7. 15.
8. 16.
WORK PERMIT
Project:
Valid only when signed by an authorized issuer, delegated by management. This permit must be issued at site before specified work is started; it must
be closed immediately after completion of the work in the same day by end of the shift and shall not to be used for more than one day or shift.
ISSUED TO: _____________________________________ __________________________________ _____________________
NAME COMPANY/CONTRACTOR DESIGNATION
STARTS AT: ____________ Hrs. ___ / ___ / _____ (Date) EXPIRES AT: ____________ Hrs. ___ / ___ / _____ (Date)
__________________________________________________________________________________________________________
This certifies that I HAVE personally completed a safety inspection of the area where this work is to be done, as well as the surrounding area, with
specific attention to the type of work checked below. I HAVE reviewed the minimum precautions and have indicated on the reverse side of this permit
all necessary precautions taken to protect the personnel engaged in this work from accident and injury. I HAVE made sure that the assigned personnel
know the applicable safety rules, work process as per method statement and that they know what to do in case of an EMERGENCY.
Tool Box Talk with JHA conducted? (Y / N) Are First Aid Box & Stretcher available at site? (Y / N) Is Pre-activity inspection check done
and a copy available at site?
5. Crane lifts, Excavator Lift, Boom truck lift and critical rigging (Above 85% of load chart)
6. Survey / Store works (Material Lift, Material handling, loading / Un-loading)
7. Winch Machine / TSE machine Operation & Installation 8. Civil Works / Shuttering
9. Working on or around live electrical parts / Conductors / inside charged Substation
10. Electrical Work 11. LOTO / Shutdown / Live line Crossing / Road Crossing
12. Material transfer to site / Bending / Cutting / shifting Re-enforcement / Fabrication works
13. Stringing - Sagging / Clamping / Jumpering / Space ring / Insulator Hoisting / Roller hoisting / Paying out (pilot wire / Conductor / OPGW )
14. Cable Laying / Pulling 15. Handling Acid Battery / Sf6 cylinder / Hazardous Chemical handling 16. Commissioning activities
17. Maintenance / Repair Activity (if inside work area) / Housekeeping and Handling / Storage of gas cylinders
18 Access Road / Tree cutting / Painting / Biological Control activity (fogging, fumigation)
19. OTHER: ___________________________________________________________________________________________________________
Mobilization of - Workers not familiar with - Disability - Site Induction for all workers Minor
Manpower & Machinery the site rules and might - Machinery toppled - Only authorized person operate the
expose to hazard - Property damage vehicle
- Unstable ground - Hit by load - Follow speed limit at site (20KM/H)
conditions - Bodily injury - Regularly Machinery inspection
- Un-inspected machineries - Tool box talk and required PPE
- - Training and implementation of ERP
- Pre-inspect the ground conditions
- Provide Traffic Controller to control
traffic movement.
- Designated route for heavy machinery
Compound stone topping - Operator must have clear visual on the
activities zone.
- Machinery Overturn - Bodily injury/Fatality - To designate a signal man with Moderate
- Struck by machine reflective vest to assist on machinery
- Dust movement
- Inspection on the machinery before
start the works
- Daily Toolbox meeting
- Competent Operator
Doc No.: PLS160199-LBT-C-MST-CR-0002
METHOD STATEMENT FOR COMPOUND STONE TOPPING Pages Page 12 of 13
Revision 0.2
Traffic Control - Uncontrolled traffic on - Bodily Injury - Wear PPE -reflect vest, mask, ear plug
enter/exit on public road - Fatality during work.
- Silt/ debris on the road - Property Damage - Use flag in traffic control
- Noise - hearing lose - Immediate clean the road surface once
- Dust emission - cough drop of silt / debris
- Hot weather - short breath - Place signboard for aware purpose.
- Drink plenty of water
- Job rotate
FDT Test/ Sampling - Hit by machinery - Body Injury - Wear PPE Minor
- Dehydrated - Fatality - Daily Toolbox Meeting
- Heat Stress - Warning Sign