SITE OBSERVATION REPORT (SOR)

Refurbishment of Sila Port


Marine and Landside Package
Reference No.: 10154-SOR-0021 Date: 10-02-2021
Form No.: GN-10-FM-003-10 Rev. No.: 0 Issue No.: 1 Issue Date: 11-May-2015 System: QMS
Mr. Muhammad Azhar Saeed
Contractor : Project Manager Project No : 10154
Al Jaber Energy Services LLC
SOR No. : 10154-SOR-021
Department / Discipline : Landside Subcontractor
Issued George Sadek
by : QA/QC Engineer

Doc. Ref. 6102-202-RU-ADPORTS-


Activity :Storm water Manhole (Protective Coating)
Number: 00020_001

Description:

Not Following approved ITP & Poor workmanship

During our inspection, it has been noticed that Surface


preparation activities for road gullies/manholes RG-02 to RG-
08 are complete without raising inspection request on
rectification works also; quality of concrete repair is not
acceptable.

Recommendations:

Subcontractor is hereby instructed to strictly comply with the project requirements.

292

Signature

Form No.: FM-ADP-13-Rev-0 Page 1 of 4


SITE OBSERVATION REPORT (SOR)

Refurbishment of Sila Port


Marine and Landside Package
Reference No.: 10154-SOR-0021 Date: 10-02-2021
Form No.: GN-10-FM-003-10 Rev. No.: 0 Issue No.: 1 Issue Date: 11-May-2015 System: QMS
Attachment

Form No.: FM-ADP-13-Rev-0 Page 3 of 4


AD Ports Contract No.: 6102-202
Refurbishment of Sila port Marine
and Landside Package

09 Feb 2021
SURVEILLANCE REPORT TRN-324

REPORT NUMBER: REV. NO: 01


6102-201-RU-ADPORTS-00020
DATE & TIME OF INSPECTION: 08.02.2021 ITP NO: 6102-202-V8-7700-00002

DISCIPLINE:

Civil Struct. Architectural Mech Piping Elect. Systems Other

OBSERVATIONS:
Employer observed that surface preparation activities for road gullies/manholes RG-02 to RG-08 are
complete without raising inspection request on rectification works also; quality of concrete repair is
not acceptable.
.

Requirements: Contractor shall ensure rectification shall conform to approve MS for Concrete
Repair and surface preparation carried out correctly. Submit inspection request to ADPORTS
(Quality Engineer) for verification of works.
REPORT BY (AD Ports): DATE:
Godfrey Cruz Abrera 08-02-2021

COMPLIANT NON-COMPLIANT NCR NUMBER (Where Non-Compliant):

REVIEWED BY: DATE:


08-02-2021

CN-F03 Surveillance Report (Rev.1/May 2017)