PROJECT REFERENCE:
(WHERE APPLICABLE)
APPROVALS
Rev. Issue
No. Date Pages Revision Description By Check Approve
1 OF 35
PROJECT: COIMBATORE-MCN-AUGMENTATION DOC NO: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
TITLE: CABLE SCHEDULE (PHASE III) REV NO: 04
LOCATION: COIMBATORE ISSUE DATE: 26-Oct-2021
1 OBJECTIVE
To prepare Cable Schedule and Summary for Coimbatore
2 BASIS
Equipment Tag Numbering
SMPS-1 For First Floor Server Hall Tag No. 10070-AG2-CMBR-ED-001 PHASE-1
SMPS-2 For First Floor Server Hall Tag No. 10070-AG2-CMBR-ED-002
SMPS-3 For First Floor Server Hall Tag No. 10070-AG2-CMBR-ED-003
SMPS-1 For Second Floor Server Hall Tag No. 10070-AG2-CMBR-ED-201
SMPS-2 For Second Floor Server Hall Tag No. 10070-AG2-CMBR-ED-202
PHASE-3
SMPS-3 For Second Floor Server Hall Tag No. 10070-AG2-CMBR-ED-203
Section- 1/ 2/ 3
Associated SMPS number
3 REFERENCE DOCUMENTS:
1. For Lighting cables and receptacles, refer Lighting and Power Layout Drg. No:
10070-E68-IN-TN-CMBR-GVRD-NB-0001-503, 10070-E68-IN-TN-CMBR-GVRD-NB-0001-504, 10070-E68-IN-TN-CMBR-GVRD-NB-0001-505,
10070-E68-IN-TN-CMBR-GVRD-NB-0001-506.
2. For Earthing cables, refer Earthing Layout Drg. No:
10070-E61-IN-TN-CMBR-GVRD-NB-0001-503, 10070-E61-IN-TN-CMBR-GVRD-NB-0001-504, 10070-E61-IN-TN-CMBR-GVRD-NB-0001-505
10070-E61-IN-TN-CMBR-GVRD-NB-0001-506
3. Design margin of 20% on cable length has been considered for termination, wastage, etc
and overall of 10% extra length has been considered for each type of cable for procurement.
4. Nyvin cable between UPS to battery, Battery to Battery Isolator shall be in UPS vendor's scope
5. For 29 mtr,19.5 mtr,17 mtr actual cable length (cable length at site) of SMPS outgoing for (4kW),(6kW),(7kW) server load,
1Rx1Cx95mm², cable shall be considered. If it is exceeding the above cable lengths specified with respect to rack kW
rating, parallel runs of actual cable lengths from SMPS to server, cable of 1Cx95 Sq.mm shall be considered accordingly.
6. It is assumed that presently the site shall continue to run on 1W+1S DGs till the actual site load increases to a level when
third DG needs to be introduced. In initial stage (1W+1S) D.G.Set shall run in AMF Mode & in future after addition of third
D.G. Sets, the D.G.Set shall run in synchronisation mode.
7 .In future after addititon of third D.G.Set, cable schedule needs to be updated for change from AMF to Synchronisation
mode .As DG-3 is Future DG so all DG3 related cables need not to be considered & are striked out.
8. This document is revised due to FCR 732 & updated D.G.Set cables in line with vendor drawings.
9. This cable schedule is revised as Rev 2 for RTU Schedule.
10. This cable schedule is revised with updation of proposed 1x1250kVA Transformer, 11kV HT ICOG Panel & Second Floor New Server Rack Hall.
Also please note that future DG Set-3, 1x625kVA DG Cables are summerised but cable quantities are not considered as it is future DG.
Hold List:
1. D.G.Set Cables are under hold, D.G.Set Vendor Drawings are awaited .
2. New Main LT Panel Termination details, Vendor Scheme Drawings awaited
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
EXISTING TRANSFORMER
1 11kV, 2P Structure 500kVA 500kVA EXISTING CABLE
10070-AG2-CMBR-ET-001
Transformer
UPSDB-2
10070-AG2-CMBR-ET-001-C1 (Marshalling Box) 3Cx2.5 1.1 kV, YWY 1 73 73 2 230V, AC, 1ph Auxiliary Power Supply
6 Tag No. 10070-AG2-CMBR-ED-217
Tag No.10070-AG2-CMBR-ET-001
TB-XX TB-5,6
Transformer
11kV ICOG PANEL
(Marshalling Box) Trip Signal
Tag No. 10070-AG2-CMBR-ESS-002
Tag No.10070-AG2-CMBR-ET-001
Teminal No. TB-31 to 35 Terminal No. X-49 to X-50 2C- WTI Trip
7 10070-AG2-CMBR-ESS-002-C4 Teminal No. TB-32 to 35 Terminal No. X-55 to X-56 12Cx1.5 1.1 kV, YWY 1 18 30 2 2C- OTI Trip
Teminal No. TB-33 to 35 Terminal No. X-45 to X-46 2C- Buchholz / Relay Trip
Teminal No. TB-34 to 35 Terminal No. X-57 to X-58 2C- PRV Trip
4C-Spare
Transformer
11kV ICOG PANEL
(Marshalling Box) Alarm Signal
Tag No. 10070-AG2-CMBR-ESS-002
Tag No.10070-AG2-CMBR-ET-001
Teminal No. TB-21 to 25 Terminal No. X-47 to X-48 2C- WTI Alarm
8 10070-AG2-CMBR-ESS-002-C5 Teminal No. TB-22 to 25 Terminal No. X-51 to X-52 12Cx1.5 1.1 kV, YWY 1 18 30 2 2C- OTI Alarm
Teminal No. TB-23 to 25 Terminal No. X-53 to X-54 2C- MOG Alarm
Teminal No. TB-24 to 25 Terminal No. X-43 to X-44 2C- Buchholz / Relay Alarm
4C-Spare
Transformer MLTP I/C 1 (Transformer)
(Marshalling Box) Tag No.10070-AG2-CMBR-ES-001
9 10070-AG2-CMBR-ESS-002-C3 Tag No.10070-AG2-CMBR-ET-001 Feeder No. 4FB 4Cx2.5 1.1 kV, YWY 1 28 27.6 2
Teminal No. TB-14 to 16 Terminal No. XC1-34 to XC1-26 2C- 51N Relay
2C- Spare
Transformer MLTP I/C 1 (Transformer)
LV Busduct 1600Amps, 3 phase +100% Outdoor Type with Canopy = 11 M
10 10070-AG2-CMBR-ES-001- P1 (LV Cable Box) Tag No.10070-AG2-CMBR-ES-001 1250 kVA 11
(Outdoor / Indoor Type) neutral Indoor Type = 1.43 M
Tag No.10070-AG2-CMBR-ET-001 Feeder No. 4FB
MLTP
UACDB-1
10070-AG2-CMBR-ES-001-C1 Tag No.10070-AG2-CMBR-ES-001 3Cx2.5 1.1 kV, YWY 1 54 54 2
Tag No.10070-AG2-CMBR-EKE-001
Feeder No. 7FA 1ph AC Control Supply from UPS-1 to MLTP Panel
11
(Ground Floor)
TB-XX XA-1,2
3 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
MLTP
UACDB-2
10070-AG2-CMBR-ES-001-C2 Tag No.10070-AG2-CMBR-ES-001 3Cx2.5 1.1 kV, YWY 1 54 54 2
Tag No.10070-AG2-CMBR-EKE-002 1ph AC Control Supply from UPS-2 to MLTP Panel
12 Feeder No. 7FA
(Ground Floor)
TB-XX XA-5,6
MLTP
11kV ICOG PANEL Annunciator Panel
Tag No. 10070-AG2-CMBR-ESS-002 Tag No.10070-AG2-CMBR-ES-001
4 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
EXISTING TRANSFORMER
UPS DB -1 240V SINGLE PHASE SUPPLY TO
8 10070-AG2-CMBR-ET-001-P1
10070-AG2-CMBR-EKL-001
MARSHALING BOX 3Cx2.5 1.1 kV, YWY
10070-AG2-CMBR-ET-001
TRANSFORMER MARSHALLING BOX
NEW MAIN LT PANEL (I/C-2)
1.1 kV, Cu. Flex Cable
16 10070-AG2-CMBR-ES-001-P4-P15 New DG Isolator panel near DG-1 FEEDER - 2F-B 625KVA 1Cx300 12 54 648 24 POWER CABLE
TAG NO : 10070-AG2-CMBR-ES-001 (BLACK)
220Volts, 1Ph Supply for DG AMF Panel ( for
NEW MAIN LT PANEL, (16A MCB mounted inside Illumination, Battery Charger, Space heater )
17 DG 1/ C1 DG 1 (AMF Panel) 4Cx2.5 1.1 kV, YWY 1 54 54 2
feeder) D.G.Set -1, Aux feeder 2F-A (63Amps) * Arrangement for 1ph supply for canopy light to be
made at site
2C- 220Volts, 1Ph Supply for DG AMF
Terminal No: - R, N Terminal No: 3T - 5, 6
2C- Spare
NEW MAIN LT PANEL (I/C-1)
18 DG 1/ C2 FEEDER - 4F-B DG 1 (AMF Panel) 4Cx1.5 1.1 kV, YWY 1 54 54 2 MLTP - Transformer incomer
TAG NO : 10070-AG2-CMBR-ES-001
Terminal No: XV1 - 1, 2, 3, 4 Terminal No: 3T - 1, 2, 3, 4 110V AC PT Supply for MAINS Sensing
NEW MAIN LT PANEL (I/C-1)
19 DG 1/ C3 FEEDER - 4F-B DG 1(AMF Panel) 4Cx1.5 1.1 kV, YWY 1 54 54 2 MLTP - Transformer incomer
TAG NO : 10070-AG2-CMBR-ES-001
Terminal No: X1 - 29, 30 Terminal No: 1 X - 5, 6 2C- Transformer incomer ON and in Service
2C- Spare
NEW MAIN LT PANEL (I/C-1)
20 DG 1/ C4 FEEDER - 4F-B DG 1 (AMF Panel) 7Cx1.5 1.1 kV, YWY 1 54 54 2 MLTP - Trafo. Incomer (I/C-1) close & Trip from AMF
TAG NO : 10070-AG2-CMBR-ES-001
Terminal No: X1 - 3, 4 Terminal No: 1T - 7, 8 2C- Close from AMF
Terminal No: X1 - 17, 18 Terminal No: 1T - 5, 6 2C- Trip from AMF
3C- Spare
NEW MAIN LT PANEL (I/C-2)
14 DG 1/ C5 FEEDER - 2F-B DG 1 (AMF Panel) 7Cx1.5 1.1 kV, YWY 1 54 54 2 MLTP - D.G.-1 Incomer (I/C-2)
TAG NO : 10070-AG2-CMBR-ES-001
2C- Spare
2C- Spare
New MLTP
19 DG1/C1 DG-1 Isolator panel 4Cx2.5 1.1 kV, YWY 1 55.0 m 55 2
Bus Coupler Feeder 5F-B
Terminal No. XV3-25,26,27,28 Terminal No. 1T-1,2,3,4 4C-415 V AC BUS-1 SUPPLY TO PCC CONTROLLER
5 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
6 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
Terminal No. X3-3,4 Terminal No. L17,18 2C- B/C ACB CLOSE COMMAND
Terminal No. X3-15,16 Terminal No. L19,20 2C- B/C ACB TRIP COMMAND
7 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
Terminal No. XV3-31,32,33,34 Terminal No. 1T-1,2,3,4 4C-415 V AC BUS-2 SUPPLY TO PCC CONTROLLER
New MLTP I/C 3 (DG-2)
2 DG2/C2 DG-2 Isolator panel 4Cx2.5 1.1 kV, YWY 2 65.0 m 130 4
Feeder 7F-B
Terminal No. XV4-1,2,3,4 Terminal No. 1T-9,10,11,12 4C-3PH,4W,110 PT SUPPLY FOR METERING
4C-CT SUPPLY FOR METERING
Terminal No. XC4-34,35,36,37 Terminal No. 1T-13,14,15,16
4C-SPARE
New MLTP I/C 3 (DG-2)
3 DG2/C3 DG-2 Isolator panel
Feeder 7F-B
7Cx1.5 1.1 kV, YWY 1 65 65 2
Terminal No. 1T23,24 Terminal No. X4-3,4 2C-DG-2 ACB CLOSE COMMAND
Terminal No. 1X11,12 Terminal No. X4-9,10 2C-DG-2 ACB TRIP COMMAND
1C-SPARE
New MLTP I/C 3 (DG-2)
4 DG2/C4
Feeder 7F-B
DG-2 Isolator panel 7Cx1.5 1.1 kV, YWY 1 0 2 Presently DGS are operating in 1W+1S Configuration
Terminal No. X4-41,42 Terminal No. 1X7,8 2C-NIC ON FEEDBACK
Terminal No. X4-17,18 Terminal No. 1X5,6 2C-ACB NO CONTACT
3C-SPARE
5 DG2/P1 DG-2 Isolator panel DG-2 ALT. (DG-2 PCC3.3 Controller.) 4Cx2.5 1.1 kV, YWY 1 15.0 m 15 2
Terminal No. 1T-5,6,7,8 Terminal No. TB7-L1,L2,L3,N 4C-415 V AC SUPPLY FOR PCC BUS PT.
6 DG2/P2 Sync Logic Panel DG-2 Isolator panel 4Cx2.5 1.1 kV, YWY 1 60 60 2
Terminal No. T5,6 Terminal No. T1,2 2C-230 V AC SUPPLY FOR DG-2 ISOLATOR PANEL
7 DG2/P3 Sync Logic Panel DG-2 Isolator panel 4Cx2.5 1.1 kV, YWY 1 60 60 2
24V DC SUPPLY FROM
Terminal No. S3,4 Terminal No. 1Z5,6
DG-2 BATT ISOLATOR PANEL
8 DG2/P4 DG-2 BATT DG-2 Isolator panel 4Cx2.5 1.1 kV, YWY BY DG VENDOR
Terminal No. 1Z1,2 24V DC SUPPLY FOR DC CONTROL CKT.
9 DG2/P5 DG-2 BATT DG-2 ALT. (DG-2 PCC3.3 Controller.) 4Cx2.5 1.1 kV, YWY BY DG VENDOR
Terminal No. 1Z11,12 24V DC SUPPLY TO DG PCC
10 DG2/C5 Sync. Panel DG-2 Isolator Panel 4Cx1.5 1.1 kV, YWY 1 60 60 2
Terminal No. P-47,48, Terminal No. 1T-17,18,19 3C-KW SIGNAL TO Sync.PANEL
(Spare terminal for shield is required) 1C-SPARE
11 DG2/C6 Sync Logic Panel DG-2 Isolator panel 5Cx1.5 1.1 kV, YWY 1 60 60 2
2C - DG2 START/STOP COMMAND TO DG-2
Terminal No. L5,6 Terminal No. 1Z7,8
ISOLATOR PANEL
2C - DG2 LOAD DEMAND STOP COMMAND TO DG-2
Terminal No.L7,8 Terminal No. 1Z9,10
ISOLATOR PANEL
1C-SPARE
12 DG2/C7 Sync Logic Panel DG-2 Isolator panel 12Cx1.5 1.1 kV, YWY 1 60 60 2
Terminal No. S-39,40 Terminal No. 1X21,22 2C-NIC CLOSING CONTACT
2C - DG-2 AUTO / MANUAL F/B FROM ISOLATOR
Terminal No. P5,6 Terminal No. 1X23,24
PANEL
Terminal No. P7,8 Terminal No. 1X25,26 2C - DG-2 RUNNING F/B FROM ISOLATOR PANEL
Terminal No. S21,22 Terminal No. 1X27,28 2C - DG-2 CSD SIGNAL FROM ISOLATOR PANEL
Terminal No. S25,26 Terminal No. 1X29,30 2C-ACB NO CONTACT
2C-SPARE
13 DG2/C8 DG-2 Isolator panel DG-2 PCC3.3 Controller. 12Cx1.5 1.1 kV, YWY 1 15 15 2
Terminal No. 1Z-13,14 Terminal No. TB1-10,11 2C-REMOTE ENGINE START SIGNAL
Terminal No. 1Z-17,18 Terminal No. TB1-15,16 2C-EMERGENCY STOP
Terminal No. 1Z-19,20 Terminal No. TB5-1,2 2C-ACB CLOSE COMMAND
Terminal No. 1Z-21,22 Terminal No. TB5-4,5 2C-ACB TRIP COMMAND
Terminal No. 1Z-23,24 Terminal No. TB8-1,5 2C-ACB FAULT RESET
2C-SPARE
14 DG2/C9 DG-2 Isolator panel DG-2 PCC3.3 Controller. 7Cx1.5 1.1 kV, YWY 1 15 15 2
Terminal No. 1Z-25,26 Terminal No. TB8-8,13 2C-CUSTOMER FAULT
Terminal No. 1Z-29,32 Terminal No. TB10-7,2 2C-ACB CLOSE FEED BACK
Terminal No. 1Z-33,34 Terminal No. TB1-4,5 2C-GENSET RUNNING SIGNAL
1C-SPARE
15 DG2/C10 DG-2 Isolator panel DG-2 PCC3.3 Controller. 7Cx1.5 1.1 kV, YWY 1 15 15 2
Terminal No. 1Z-27,28 Terminal No. TB10-14,17 2C-LOAD DEMAND STOP
Terminal No. 1Z-35,36 Terminal No. TB1-8,9 2C-COMMON SHUT DOWN
Terminal No. 1Z-31.32 Terminal No. TB10-10,2 2C-CB TRIPPED STATUS
1C-SPARE
8 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
16 DG2/C11 DG-2 Isolator Panel FUEL TANK 4Cx1.5 1.1 kV, YWY BY DG VENDOR
Terminal No. 1Z-37,38 2C-Contact for Fuel level High status
Terminal No. 1Z-39,40 2C-Contact for Fuel level Low status
17 DG2/C12 METER BOX DG-2 Isolator panel 12Cx2.5 1.1 kV, YWY BY DG VENDOR
Terminal No. Terminal No. 1T25,26,27,28 4C- CT & 3PH,4W SUPPLY FOR KWH METER
Terminal No. Terminal No. 1T29,30,31,32 4C- 110 PT SUPPLY FOR KWH METER
4C-SPARE
Earthing cable from Neutral contactor (at LT panel end)
18 DG 2/ E1 DG 2 (625KVA) neutral contactor at LT panel end Earth Pit No. - DG2- Neutral Earth Pit-1 1Cx120 1.1 kV, YY, FRLS 1 80 80 2
to Earth pit.
19 DG 2/ E2 DG 2 (625KVA) neutral contactor at LT panel end Earth Pit No. - DG2- Neutral Earth Pit-2 1Cx120 1.1 kV, YY, FRLS 1 80 80 2
Actual length shall be verified at site.
9 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
34 DG3/C8 DG-3 Isolator panel DG-3 PCC3.3 Controller. 12Cx1.5 1.1 kV, YWY 0 0 0
Terminal No. 1Z-13,14 Terminal No. TB1-10,11 2C-REMOTE ENGINE START SIGNAL
Terminal No. 1Z-17,18 Terminal No. TB1-15,16 2C-EMERGENCY STOP
Terminal No. 1Z-19,20 Terminal No. TB5-1,2 2C-ACB CLOSE COMMAND
Terminal No. 1Z-21,22 Terminal No. TB5-4,5 2C-ACB TRIP COMMAND
Terminal No. 1Z-23,24 Terminal No. TB8-1,5 2C-ACB FAULT RESET
2C-SPARE
35 DG3/C9 DG-3 Isolator panel DG-3 PCC3.3 Controller. 7Cx1.5 1.1 kV, YWY 0 0 0
Terminal No. 1Z-25,26 Terminal No. TB8-8,13 2C-CUSTOMER FAULT
Terminal No. 1Z-29,32 Terminal No. TB10-7,2 2C-ACB CLOSE FEED BACK
Terminal No. 1Z-33,34 Terminal No. TB1-4,5 2C-GENSET RUNNING SIGNAL
1C-SPARE
36 DG3/C10 DG-3 Isolator panel DG-3 PCC3.3 Controller. 7Cx1.5 1.1 kV, YWY 0 0 0
Terminal No. 1Z-27,28 Terminal No. TB10-14,17 2C-LOAD DEMAND STOP
Terminal No. 1Z-35,36 Terminal No. TB1-8,9 2C-COMMON SHUT DOWN
Terminal No. 1Z-31.32 Terminal No. TB10-10,2 2C-CB TRIPPED STATUS
1C-SPARE
37 DG3/C11 DG-3 Isolator Panel FUEL TANK 4Cx1.5 1.1 kV, YWY 0 0 0
Terminal No. 1Z-37,38 2C-Contact for Fuel level High status
Terminal No. 1Z-39,40 2C-Contact for Fuel level Low status
38 DG3/C12 METER BOX DG-3 Isolator panel 12Cx2.5 1.1 kV, YWY 0 0 0
Terminal No. 1T25,26,27,28 4C- CT & 3PH,4W SUPPLY FOR KWH METER
Terminal No. 1T29,30,31,32 4C- 110 PT SUPPLY FOR KWH METER
4C-SPARE
New MLTP I/C 4 (DG-3)
39 SYNC./ PLC / C9 PLC panel 4Cx1.5 1.1 kV, YWY 0 0 0
Feeder 9F-B
2C-REF 615 RELAY TRIP FROM MLTP TO DG-3
Terminal No. X5-25,26 (REF 615 X100-13,14) Terminal No. P-25,26
CONTROLLER
2C-SPARE
New MLTP I/C 4 (DG-3)
40 SYNC./ PLC / C10 Sync Logic Panel 7Cx1.5 1.1 kV, YWY 0 0 0
Feeder 9F-B
Terminal No. X5-15,16 Terminal No. S41,42 2C-NIC ON/OFF COMMAND
Terminal No. X5-39,40 Terminal No. S35,36 2C-NIC ON FEEDBACK
1C-SPARE
New MLTP O/G Feeder
41 SYNC./ PLC / P1 Sync Logic Panel 4Cx35 1.1 kV, A2XFY 1 20 20 2
Feeder 1F-C
Terminal No. T1,T2 4C-230 V AC SUPPLY FOR DG AUX CKT.
New MLTP I/C 1 (Transformer)
42 SYNC./ PLC / P2 Sync Logic Panel Feeder 4F-B 4Cx2.5 1.1 kV, YWY 1 20 20 2
Terminal No. T9,10,11 Terminal No. XV1-1,2,3,4 4C- 3PH,110AC SUPPLY FOR VMRT
43 SYNC./ PLC / P3 UPS-1 Sync Logic Panel 4Cx2.5 1.1 kV, YWY 1 45 45 2
Terminal No. T12,13 2C- 230V UPS POWER SUPPLY
2C-SPARE
44 SYNC./ PLC / P4 UPS-2 Sync Logic Panel 4Cx2.5 1.1 kV, YWY 1 45 45 2
Terminal No. T14,15 2C- 230V UPS POWER SUPPLY
2C-SPARE
45 DG1 PCC 3.3 controller SYNC./ PLC panel 4Cx1.5 1.1 kV, YWY 1 60 60 2
SYNC./ PLC Panel / C18 Terminal No. TB9-7,8,9,10,11 Terminal no. 1N-1,2,3,4,shield NET WORKING FOR KW & KVAR LOAD SHARING
46 SYNC./ PLC panel DG2 PCC 3.3 controller 4Cx1.5 1.1 kV, YWY 1 65 65 2
SYNC./ PLC Panel / C19 Terminal no. 1N-5,6,7,8,shield Terminal No. TB9-7,8,9,10,11 NET WORKING FOR KW & KVAR LOAD SHARING
47 DG2 PCC 3.3 controller DG3 PCC 3.3 controller 4Cx1.5 1.1 kV, YWY 1 30 30 2
SYNC./ PLC Panel / C20 Terminal No. TB9-7,8,9,10,11 Terminal No. TB9-7,8,9,10,11 NET WORKING FOR KW & KVAR LOAD SHARING
48 DG1 PCC 3.3 controller DG2 PCC 3.3 controller 2Cx1.5 Screen cable 1 30 30 2
SYNC./ PLC Panel / C21 Terminal No. TB3-11,12 Terminal No. TB3-11,12 Master DG networking
49 DG2 PCC 3.3 controller Future DG3 PCC 3.3 controller 2Cx1.5 Screen cable 1 30 30 2
SYNC./ PLC Panel / C22 Terminal No. TB3-11,12 Terminal No. TB3-11,12 Master DG networking
New MLTP I/C 4 (DG-3) DG-3 ACB No contact from MLTP Panel
SYNC./ PLC Panel / C11 PLC Panel 4Cx1.5 1.1 kV, YWY 1 20 20 2
Feeder 9F-B
Terminal No. S-31,32 Terminal No. X5-17,18
10 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
SMPS-1 (First Floor) For Load shedding, when future third DG is added in
50 SYNC./ PLC Panel / C12 SYNC./ PLC Panel 4Cx1.5 1.1 kV, YWY 1 35 35 2
Tag No.10070-AG2-CMBR-ED-001 system
Terminal No. L25,L26
SMPS-2 (First Floor) For Load shedding, when future third DG is added in
51 SYNC./ PLC Panel / C13 SYNC./ PLC Panel 4Cx1.5 1.1 kV, YWY 1 40 40 2
Tag No. 10070-AG2-CMBR-ED-002 system
Terminal No. L27, L28
SMPS-3 (First Floor) For Load shedding, when future third DG is added in
52 SYNC./ PLC Panel / C14 SYNC./ PLC Panel 4Cx1.5 1.1 kV, YWY 1 45 45 2
Tag No. 10070-AG2-CMBR-ED-003 system
Terminal No. L29, L30
SMPS-1 (Second Floor) For Load shedding, when future third DG is added in
53 SYNC./ PLC Panel / C15 SYNC./ PLC Panel 4Cx1.5 1.1 kV, YWY 1 45 45 2
Tag No.10070-AG2-CMBR-ED-201 system
Terminal No. L31, L32
SMPS-2 (Second Floor) For Load shedding, when future third DG is added in
54 SYNC./ PLC Panel / C16 SYNC./ PLC Panel 4Cx1.5 1.1 kV, YWY 1 48 48 2
Tag No.10070-AG2-CMBR-ED-202 system
Terminal No. L33, L34
SMPS-3 (Second Floor) For Load shedding, when future third DG is added in
55 SYNC./ PLC Panel / C17 SYNC./ PLC Panel 4Cx1.5 1.1 kV, YWY 1 50 50 2
Tag No.10070-AG2-CMBR-ED-203 system
Terminal No. L35, L36
EXISTING RCOM MLTP
NEW MAIN LT PANEL (O/G) FEEDER-10R-E (GR. FLOOR)
56 SYPE447-P2
TAG NO : 10070-AG2-CMBR-ES-001 FEED B
4Cx120 1.1 kV, 2XY 1 26 26 2
SYPE447
EXISTING RCOM MPDB, I/C-II, FEEDER NO-6F-B
NEW MAIN LT PANEL (O/G) FEEDER - 8F-B (GR. FLOOR) SYPE689
57 SYPE689-P7-P12
TAG NO : 10070-AG2-CMBR-ES-001 FEED B
4Cx300 1.1 kV, A2XFY 6 36 216 12
0.37kW
NEW MAIN LT PANEL (O/G) FEEDER - 10R-C
60 HOLD
TAG NO : 10070-AG2-CMBR-ES-001
EXHAUST FAN 3Cx2.5 1.1 kV, YWY 1 10 10 2
(GROUND FLOOR)
11 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
12 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
Pressure Switch
88 Diesel Pump Control Panel - C2 Diesel Pump Control Panel 4Cx1.5 1.1 kV, YWY 1 15 15 2 To start Diesel Pump
PS-4
Terminal No. 10TB2 to 12TB2
2C - NO contact of Pressure Switch PS-4 to start Diesel
Terminal No. By Site ((Marked terminal numbers to be validated at site w.r.t
Pump when pressure reaches to 6.5 kg/cm2
panel available at site)
2C - Spare
EXISTING MPDB, (O/G) FEEDER - 8R-B Energy Meter DB -1
89 CMBR-EM-DB-3-P1 (GR. FLOOR) ( 25TR PAC-1 First Floor FOR MSC-2 ) 4Cx35 1.1 kV, A2XFY 1 18 18 2
TAG NO. : 10070-AG2-CMBR-EC-001 CMBR-EM-DB-1-P1
13 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
NEW MPDB, (O/G) FEEDER- 2R-C LPDB CHANGEOVER SWITCH (OFF LOAD)
92 10070-AG2-CMBR-EKL-202 -P1 (2ND. FLOOR) (2ND. FLOOR) FEED-A 4Cx35 1.1 kV, A2XFY
TAG NO. : 10070-AG2-CMBR-EC-201 TAG NO. : 10070-AG2-CMBR-EKL-202
NEW MPDB, (O/G) FEEDER- 9R-C LPDB CHANGEOVER SWITCH (OFF LOAD)
105 10070-AG2-CMBR-EKL-202 -P2 (2ND. FLOOR) (2ND. FLOOR) FEED-B 4Cx35 1.1 kV, A2XFY
TAG NO. : 10070-AG2-CMBR-EC-201 TAG NO. : 10070-AG2-CMBR-EKL-202
14 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
15 OF 35
CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
PROJECT NO. 44PS8901 Title:
REV NO. : 04
LOCATION COIMBATORE
AC CABLE SCHEDULE -PHASE-III CABLE DETAILS
16 OF 35
PROJECT NO.: . 44PS8901 TITLE: CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT: COIMBATORE-MCN-AUGMENTATION REV NO. : 04
LOCATION COIMBATORE DATE : 26-Oct-2021
ANNEXURE A: SMPS DISTRIBUTION MATRIX GROUND FLOOR FOR PHASE -1 & PHASE -III
SMPS-1 First Floor (PHASE-I) SMPS -2 FIRST FLOOR (PHASE-I)
6 28
6 1 28 METRO METRO 1 1
ALU MGW-1 CORE + CORE + ALU MGW-1
B04,R06 6 B03,R06 10 B03,R06 10 B04,R06 6
(600x1000x2200) ACCESSES - 2 7 ACCESSES - 2 29 (600x1000x2200)
7 1 29 (700x1000x2200) (700x1000x2200) 1 1
IPSE 8 IPSE 30
8 1 30 B03,R05 5 1 B03,R05 5 1 1
ALU MGW -2 (600x1000x2200) (600x1000x2200) ALU MGW-2
B04,R05 6 B04,R05 6
(600x1000x2200) 9 31 (600x1000x2200)
9 1 31 1 1 1
IBR-2 IBR -2
B03,R03 7 B03,R03 7
(800x1000x2200) 10 (800x1000x2200) 32
DCN DCN
10 B04,R04 4 1 32 1 1 B04,R04 4 1
(800x1000x2200) (800x1000x2200)
11 33
11 1 33 1 1 1
IBR-1 SAR-2 SAR-2 IBR-1
B04,R03 7 B03,R02 7 B03,R02 7 B04,R03 7
(800x1000x2200) (800x1000x2200) 12 (800x1000x2200) 34 (800x1000x2200)
12 1 34 1 1 1
13 35
13 1 35 1 1 1
SAR-1 NEXUS- 2 NEXUS- 2 SAR-1
B04,R02 7 B03,R01 7 B03,R01 7 B04,R02 7
(800x1000x2200) (800x1200x2200) 14 (800x1200x2200) 36 (800x1000x2200)
14 1 36 1 1 1
VGW-6 37
15 1 37 B02,R07 5 1 15 Spare 1 1
NEXUS-1 (600x1200x2200) NEXUS- 1
B04,R01 7 B04,R01 7
(800x1200x2200) 38 (800x1200x2200)
VGW-5
16 1 38 B02,R06 5 1 16 Spare 1 1
(600x1200x2200)
VGW-4 39 VGW-8
17 Spare 1 39 B02,R05 5 1 17 Spare 1 B02,R09 5 1
(600x1200x2200) (600x1200x2200)
18 40
VGW-3 VGW-7 ASBC
18 Spare 1 40 B02,R04 5 1 Spare 1 B02,R08 5 1
(600x1200x2200) (600x1200x2200)
04
VGW-2 19 41 RAN-1
19 Spare 1 41 B02,R03 5 1 Spare 1 B05,R07 5 1
(600x1200x2200) (600x1200x2200)
VGW-1 20 42 RAN-2
20 Spare 1 42 B02,R02 5 1 Spare 1 B05,R08 5 1
(600x1200x2200) (600x1200x2200)
ACI 21 43 SECAT-2
21 Spare 1 43 B02,R01 5 1 Spare 1 B05,R06 5 1
(600x1200x2200) (600x1200x2200)
22 44
22 Spare 1 44 Spare 1 Spare 1 Spare 1
Fuses Fuses
Terminal no Name of Rack Bay no & Row no KW Terminal no Name of Rack Bay no & Row no KW
(-ve Bus) (-ve Bus)
100A Fuse 100A Fuse
1 Spare 1 17 Spare 1
2 Spare 1 18 Spare 1
VGW-2 25
9 B02,R03 5 1 Spare 1
(600x1200x2200)
VGW-1 26
10 B02,R02 5 1 Spare 1
(600x1200x2200)
ACI 27
11 B02,R01 5 1 Spare 1
(600x1200x2200)
RAN-2 28
12 B05,R08 5 1 Spare 1
(600x1200x2200)
RAN-1 29
13 B05,R07 5 1 Spare 1
(600x1200x2200)
SECAT-2 30
14 B05,R06 5 1 Spare 1
(600x1200x2200)
31
15 Spare 1 Spare 1
16 32
Spare 1 Spare 1
SUM(KW) 60 16 SUM(KW) 25 16
Note:
1. Permissible Voltage drop for DC load is 2% considering actual server rack load
PROJECT NO. 44PS8901 Title: CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT: COIMBATORE-MCN-AUGMENTATION REV NO. : 04
LOCATION COIMBATORE DATE : 26-Oct-2021
Server Rack B04, R08-P1 Server Rack B04, R08-P2 SMPS 1-T4 1Cx70 1.1 kV, YY 12 1 1 2 24 FIRST FLOOR
1 TX POI -1 5.0 kW
Server Rack B04, R08-P3 to P4 Server Rack B04, R08-P5 to P6 SMPS 2-T26 1Cx70 1.1 kV, YY 23 2 1 4 92 FIRST FLOOR
Server Rack B04, R07- P1 Server Rack B04, R07- P2 SMPS 1-T5 1Cx70 1.1 kV, YY 13 1 1 2 26 FIRST FLOOR
2 TX POI -2 5.0 kW
Server Rack B04, R07- P3 to P4 Server Rack B04, R07- P5 to P6 SMPS 2-T27 1Cx70 1.1 kV, YY 23 2 1 4 92 FIRST FLOOR
Server Rack B04, R06- P1 to P2 Server Rack B04, R06- P3 to P4 SMPS 1-T6-T7 1Cx70 1.1 kV, YY 14 1 2 4 56 FIRST FLOOR
3 ALU MGW-1 6.0 kW
Server Rack B04, R06- P5 to P6 Server Rack B04, R06- P6 to P8 SMPS 2-T28-T29 1Cx70 1.1 kV, YY 23 1 2 4 92 FIRST FLOOR
Server Rack B04, R05- P1 to P2 Server Rack B04, R05- P3 to P4 SMPS 1-T8-T9 1Cx70 1.1 kV, YY 15 1 2 4 60 FIRST FLOOR
4 ALU MGW-2 6.0 kW
Server Rack B04, R05- P5 to P6 Server Rack B04, R05- P6 to P8 SMPS 2-T30-T31 1Cx70 1.1 kV, YY 22 1 2 4 88 FIRST FLOOR
Server Rack B04, R04- P1 Server Rack B04, R04- P2 SMPS 1-T10 1Cx70 1.1 kV, YY 16 1 1 2 32 FIRST FLOOR
5 DCN 4.0 kW
Server Rack B04, R04- P3 Server Rack B04, R04- P4 SMPS 2-T32 1Cx70 1.1 kV, YY 21 1 1 2 42 FIRST FLOOR
Server Rack B04, R03-P1 to P2 Server Rack B04, R03- P3 to P4 SMPS 1-T11-T12 1Cx70 1.1 kV, YY 16 1 2 4 64 FIRST FLOOR
6 IBR-1 7.0 kW
Server Rack B04, R03-P5 to P6 Server Rack B04, R03- P6 to P8 SMPS 2-T33-T34 1Cx70 1.1 kV, YY 19 1 2 4 76 FIRST FLOOR
Server Rack B04, R02- P1 to P2 Server Rack B04, R02- P3 to P4 SMPS 1-T13-T14 1Cx70 1.1 kV, YY 17 1 2 4 68 FIRST FLOOR
7 SAR-1 7.0 kW
Server Rack B04, R02-P5 to P6 Server Rack B04, R02- P6 to P8 SMPS 2-T35-T36 1Cx70 1.1 kV, YY 19 1 2 4 76 FIRST FLOOR
Server Rack B04, R01-P1 to P2 Server Rack B04, R01- P3 to P4 SMPS 1-T15-T16 1Cx70 1.1 kV, YY 18 1 2 4 72 FIRST FLOOR
8 Nexus-1 7.0 kW
Server Rack B04, R01-P5 to P6 Server Rack B04, R01- P6 to P8 SMPS 2-T37-T38 1Cx70 1.1 kV, YY 19 1 2 4 76 FIRST FLOOR
Server Rack B03, R07 - P1 to P2 Server Rack B03, R07 - P3 to P4 SMPS 2-T4-T5 1Cx70 1.1 kV, YY 12 1 2 4 48 FIRST FLOOR
9 Metro Core+Access-1 10.0 kW
Server Rack B03, R07 - P5 to P8 Server Rack B03, R07 - P9 to P12 SMPS 1-T26-T27 1Cx70 1.1 kV, YY 25 2 2 8 200 FIRST FLOOR
Server Rack B03, R06 -P1 to P2 Server Rack B03, R06 - P3 to P4 SMPS 2-T6-T7 1Cx70 1.1 kV, YY 13 1 2 4 52 FIRST FLOOR
10 Metro Core+Access-2 10.0 kW
Server Rack B03, R06 - P5 to P8 Server Rack B03, R06 - P9 to P12 SMPS 1-T28-T29 1Cx70 1.1 kV, YY 26 2 2 8 208 FIRST FLOOR
Server Rack B03, R05 - P1 Server Rack B03, R05 - P2 SMPS 2-T8 1Cx70 1.1 kV, YY 14 1 1 2 28 FIRST FLOOR
11 IPSE 5.0 kW
Server Rack B03, R05 - P3 to P4 Server Rack B03, R05 - P5 to P6 SMPS 1-T30 1Cx70 1.1 kV, YY 25 2 1 4 100 FIRST FLOOR
Server Rack B03, R03 - P1 to P2 Server Rack B03, R03 - P3 to P4 SMPS 2-T9-T10 1Cx70 1.1 kV, YY 16 1 2 4 64 FIRST FLOOR
12 IBR-2 7.0 kW
Server Rack B03, R03 - P5 to P6 Server Rack B03, R03 - P7 to P8 SMPS 1-T31-T32 1Cx70 1.1 kV, YY 23 1 2 4 92 FIRST FLOOR
Server Rack B03, R02 - P1 to P2 Server Rack B03, R02 - P3 to P4 SMPS 2-T11-T12 1Cx70 1.1 kV, YY 17 1 2 4 68 FIRST FLOOR
13 SAR-2 7.0 kW
Server Rack B03, R02 - P5 to P6 Server Rack B03, R02 - P7 to P8 SMPS 1-T33-T34 1Cx70 1.1 kV, YY 22 1 2 4 88 FIRST FLOOR
Server Rack B03, R01 - P1 to P2 Server Rack B03, R01 - P3 to P4 SMPS 2-T13-T14 1Cx70 1.1 kV, YY 18 1 2 4 72 FIRST FLOOR
14 Nexus-2 7.0 kW
Server Rack B03, R01 - P5 to P6 Server Rack B03, R01 - P7 to P8 SMPS 1-T35-T36 1Cx70 1.1 kV, YY 22 1 2 4 88 FIRST FLOOR
PROJECT NO. 44PS8901 Title: CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT: COIMBATORE-MCN-AUGMENTATION REV NO. : 04
LOCATION COIMBATORE DATE : 26-Oct-2021
Server rack B02,R09/ P1 Server rack B02,R09/ P2 SMPS 3-T3 1Cx95 1.1 kV, YY 10 1 1 2 19
17 VGW-8 Server rack B02,R09 7.0 kW
Server rack B02,R09/ P3 Server rack B02,R09/ P4 SMPS 2-T39 1Cx95 1.1 kV, YY 12 1 1 2 24
Server rack B02,R08/ P1 Server rack B02,R08/ P2 SMPS 3-T4 1Cx95 1.1 kV, YY 10 1 1 2 19
18 VGW-7 ASBC Server rack B02,R08 7.0 kW As per FCR 884
Server rack B02,R08/ P3 Server rack B02,R08/ P4 SMPS 2-T40 1Cx95 1.1 kV, YY 13 1 1 2 26
04
Server rack B02,R07/ P1 Server rack B02,R07/ P2 SMPS 3-T5 1Cx95 1.1 kV, YY 11 1 1 2 22
19 VGW-6 Server rack B02,R07 7.0 kW
Server rack B02,R07/ P3 Server rack B02,R07/ P4 SMPS 1-T37 1Cx95 1.1 kV, YY 15 1 1 2 30
Server rack B02,R06/ P1 Server rack B02,R06/ P2 SMPS 3-T6 1Cx95 1.1 kV, YY 11 1 1 2 22
20 VGW-5 Server rack B02,R06 7.0 kW
Server rack B02,R06/ P3-P4 Server rack B02,R06/ P5-P6 SMPS 1-T38 1Cx95 1.1 kV, YY 18 2 1 4 72
Server rack B02,R05/ P1 Server rack B02,R05/ P2 SMPS 3-T7 1Cx95 1.1 kV, YY 12 1 1 2 24
21 VGW-4 Server rack B02,R05 7.0 kW
Server rack B02,R05/ P3-P4 Server rack B02,R05/ P5-P6 SMPS 1-T39 1Cx95 1.1 kV, YY 19 2 1 4 77
Server rack B02,R04/ P1 Server rack B02,R04/ P2 SMPS 3-T8 1Cx95 1.1 kV, YY 13 1 1 2 26
22 VGW-3 Server rack B02,R04 7.0 kW
Server rack B02,R04/ P3-P4 Server rack B02,R04/ P5-P6 SMPS 1-T40 1Cx95 1.1 kV, YY 19 2 1 4 77
Server rack B02,R03/ P1 Server rack B02,R03/ P2 SMPS 3-T9 1Cx95 1.1 kV, YY 13 1 1 2 26
23 VGW-2 Server rack B02,R03 7.0 kW
Server rack B02,R03/ P3-P4 Server rack B02,R03/ P5-P6 SMPS 1-T41 1Cx95 1.1 kV, YY 20 2 1 4 82
Server rack B02,R02/ P1 Server rack B02,R02/ P2 SMPS 3-T10 1Cx95 1.1 kV, YY 14 1 1 2 29
24 VGW-1 Server rack B02,R02 7.0 kW
Server rack B02,R02/ P3-P4 Server rack B02,R02/ P5-P6 SMPS 1-T42 1Cx95 1.1 kV, YY 22 2 1 4 86
Server rack B02,R01/ P1 Server rack B02,R01/ P2 SMPS 3-T11 1Cx95 1.1 kV, YY 14 1 1 2 29
25 ACI Server rack B02,R01 7.0 kW
Server rack B02,R01/ P3-P4 Server rack B02,R01/ P5-P6 SMPS 1-T43 1Cx95 1.1 kV, YY 22 2 1 4 86
Server rack B05,R08/ P1-P2 Server rack B05,R08/ P3-P4 SMPS 3-T12 1Cx95 1.1 kV, YY 23 2 1 4 91
26 RAN-2 Server rack B05,R08 7.0 kW
Server rack B05,R08/ P5-P6 Server rack B05,R08/ P7-P8 SMPS 2-T42 1Cx95 1.1 kV, YY 22 2 1 4 88
Server rack B05,R07/ P1-P2 Server rack B05,R07/ P3-P4 SMPS 3-T13 1Cx95 1.1 kV, YY 22 2 1 4 86
27 RAN-1 Server rack B05,R07 7.0 kW
Server rack B05,R07/ P5-P6 Server rack B05,R07/ P7-P8 SMPS 2-T41 1Cx95 1.1 kV, YY 19 2 1 4 77
Server rack B05,R06/ P1-P2 Server rack B05,R06/ P3-P4 SMPS 3-T14 1Cx95 1.1 kV, YY 22 2 1 4 86
28 SECAT-2 Server rack B05,R06 7.0 kW
Server rack B05,R06/ P4-P5 Server rack B05,R06/ P6-P7 SMPS 2-T43 1Cx95 1.1 kV, YY 18 2 1 4 72
PROJECT NO. 44PS8901 Title: CABLE SCHEDULE (PHASE III) DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT: COIMBATORE-MCN-AUGMENTATION REV NO. : 04
LOCATION COIMBATORE DATE : 26-Oct-2021
Server rack B05,R05/ P1-P2 Server rack B05,R05/ P3-P4 SMPS 2-T23 1Cx95 1.1 kV, YY 18 2 1 4 72
29 SECAT-1 Server rack B05,R05 7.0 kW
Server rack B05,R05/ P5-P6 Server rack B05,R05/ P7-P8 SMPS 3-T19 1Cx95 1.1 kV, YY 20 2 1 4 82
Server rack B05,R01/ P1 Server rack B05,R01/ P2 SMPS 1-T24 1Cx95 1.1 kV, YY 14 1 1 2 29
FACEBOOK-1
31 Server rack B05,R01 7.0 kW
CDN-1
Server rack B05,R01/ P3-P4 Server rack B05,R01/ P5-P6 SMPS 3-T23 1Cx95 1.1 kV, YY 20 2 1 4 82
Server rack B05,R04/ P1 Server rack B05,R04/ P2 SMPS 2-T24 1Cx95 1.1 kV, YY 17 1 1 2 34
GOOGLE-2
32 Server rack B05,R04 7.0 kW
CDN-4
Server rack B05,R04/ P3-P4 Server rack B05,R04/ P5-P6 SMPS 3-T20 1Cx95 1.1 kV, YY 20 2 1 4 82
Server rack B05,R03/ P1 Server rack B05,R03/ P2 SMPS 2-T25 1Cx95 1.1 kV, YY 16 1 1 2 31
GOOGLE-1
33 Server rack B05,R03 7.0 kW
CDN-3
Server rack B05,R03/ P3-P4 Server rack B05,R03/ P5-P6 SMPS 3-T21 1Cx95 1.1 kV, YY 19 2 1 4 77
Battery Rack
Battery Rack 3-1/ P1-P2 Battery Rack 3-1/ P3-P4 SMPS 3 1Cx95 1.1 kV, YY 7 4 28
3-1
Battery Rack
Battery Rack 3-2/ P1-P2 Battery Rack 3-2/ P3-P4 SMPS 3 1Cx95 1.1 kV, YY 7 4 28
3-2
34
Battery Rack
Battery Rack 3-3/ P1-P2 Battery Rack 3-3/ P3-P4 SMPS 3 1Cx95 1.1 kV, YY 7 4 28
3-3
Battery Rack
Battery Rack 3-4/ P1-P2 Battery Rack 3-4/ P3-P4 SMPS 3 1Cx95 1.1 kV, YY 7 4 28
3-4
Note:
1. Design margin of 20% on cable length has been considered for termination, wastage etc for each cable length and overall of 10% extra length has been considered for each type of cable for procurement.
2. Permissible Voltage drop for DC load is 2% considering actual server rack load
3.As per FCR 732 there is change in Nomenclature of racks CDN-1, CDN-2, CDN-3 & CDN-4 changed to FACEBOOK-1, FACEBOOK-2, GOOGLE-1 & GOOGLE-2
PROJECT NO. DOC NO.:
44PS8901 Title: CABLE SCHEDULE 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
3 COLOCATED AG2 L2-B01,R01 7 1 18 METRO CORE-02 L2-B03,R10 6 1 3 METRO CORE-02 L2-B03,R10 6 1 18 COLOCATED AG2 L2-B01,R01 7 1
4 COLOCATED AG1 L2-B01,R02 5 1 19 METRO CORE-03 L2-B03,R11 6 1 4 METRO CORE-03 L2-B03,R11 6 1 19 COLOCATED AG1 L2-B01,R02 5 1
5 AG3-02 L2-B02,R01 8 1 20 NLD CORE TML-01 L2-B04,R01 8 1 5 NLD CORE TML-01 L2-B04,R01 8 1 20 AG3-02 L2-B02,R01 8 1
6 ICR-02 L2-B02,R02 8 1 21 NLD CORE TML-02 L2-B04,R02 8 1 6 NLD CORE TML-02 L2-B04,R02 8 1 21 ICR-02 L2-B02,R02 8 1
7 IPSE-02 L2-B02,R09 5 1 22 NLD CORE TML-03 L2-B04,R03 8 1 7 NLD CORE TML-03 L2-B04,R03 8 1 22 IPSE-02 L2-B02,R09 5 1
Fuses Fuses
Terminal no Name of Rack Bay no & Row no KW Terminal no Name of Rack Bay no & Row no KW
(-ve Bus) (-ve Bus)
100A Fuse 100A Fuse
1 Spare 16 Spare
2 Spare 17 Spare
5 1 20 ICR-01 L2-B03,R02 8 1
NLD CORE OTN DXC-02 L2-B05,R01 18
6 1 21 DCN L2-B03,R04 4 1
7 1 22 DC RACK L2-B03,R05 5 1
NLD CORE OTN DXC-03 L2-B05,R04 18
8 1 23 METRO CORE-01 L2-B03,R08 6 1
9 1 24 NLD COLLECTOR-01 L2-B04,R04 6 1
10 NLD CORE OTN DXC-01 L2-B05,R06 20 1 25 NLD COLLECTOR-02 L2-B04,R05 6 1
11 1 26 NLD COLLECTOR-03 L2-B04,R06 6 1
12 27 IP DATA L2-B04,R09 6 1
COIMBATORE 26-Oct-2021
LOCATION DATE :
A SECOND FLOOR
Server Rack L2-B01,R01 / P1 Server Rack L2-B01,R01 / P2 SMPS 1-T3 1Cx95 1.1 kV, YY 16 1 1 2 32
Server Rack L2-B01,R01 / P3-P4 Server Rack L2-B01,R01 / P5-P6 SMPS 2-T18 1Cx95 1.1 kV, YY 20 2 1 4 80
Server Rack L2-B01,R02 / P1-P2 Server Rack L2-B01,R02 / P3-P4 SMPS 1-T4 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B01,R02 / P5-P6 Server Rack L2-B01,R02 / P7-P8 SMPS 2-T19 1Cx95 1.1 kV, YY 19 1 1 2 38
Server Rack L2-B02,R01 / P1-P2 Server Rack L2-B02,R01 / P3-P4 SMPS 1-T5 1Cx95 1.1 kV, YY 15 2 1 4 60
Server Rack L2-B02,R01 / P5-P6 Server Rack L2-B02,R01 / P7-P8 SMPS 2-T20 1Cx95 1.1 kV, YY 18 2 1 4 72
Server Rack L2-B02,R02 / P1 Server Rack L2-B02,R02 / P2 SMPS 1-T6 1Cx95 1.1 kV, YY 14 1 1 2 28
Server Rack L2-B02,R02 / P3-P4 Server Rack L2-B02,R02 / P5-P6 SMPS 2-T21 1Cx95 1.1 kV, YY 16 2 1 4 64
Server Rack L2-B02,R09 / P1 Server Rack L2-B02,R09 / P2 SMPS 1-T7 1Cx95 1.1 kV, YY 19 1 1 2 38
Server Rack L2-B02,R09 / P3-P4 Server Rack L2-B02,R09 / P5-P6 SMPS 2-T22 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B02,R10 / P1 Server Rack L2-B02,R10 / P2 SMPS 1-T8 1Cx95 1.1 kV, YY 19 1 1 2 38
Server Rack L2-B02,R10 / P3-P4 Server Rack L2-B02,R10 / P5-P6 SMPS 3-T18 1Cx95 1.1 kV, YY 22 1 1 2 44
Server Rack L2-B03,R01 / P1-P2 Server Rack L2-B03,R01 / P3-P4 SMPS 1-T9 1Cx95 1.1 kV, YY 15 2 1 4 60
Server Rack L2-B03,R01 / P5-P6 Server Rack L2-B03,R01 / P7-P8 SMPS 3-T19 1Cx95 1.1 kV, YY 19 2 1 4 76
Server Rack L0-B02,R11 / P1-P2 Server Rack L0-B02,R11 / P3-P4 SMPS 1-T10 1Cx95 1.1 kV, YY 15 2 3 12 180
Server Rack L0-B02,R11 / P5-P6 Server Rack L0-B02,R11 / P7-P8 SMPS 3-T20 1Cx95 1.1 kV, YY 19 2 3 12 228
Server Rack L2-B03,R04 / P1 Server Rack L2-B03,R04 / P2 SMPS 1-T11 1Cx95 1.1 kV, YY 14 1 1 2 28
Server Rack L2-B03,R04 / P3 Server Rack L2-B03,R04 / P4 SMPS 3-T21 1Cx95 1.1 kV, YY 18 1 1 2 36
Server Rack L2-B03,R05 / P1 Server Rack L2-B03,R05 / P2 SMPS 1-T12 1Cx95 1.1 kV, YY 13 1 1 2 26
Server Rack L2-B03,R05 / P3 Server Rack L2-B03,R05 / P4 SMPS 3-T22 1Cx95 1.1 kV, YY 17 1 1 2 34
Server Rack L2-B03,R08 / P1 Server Rack L2-B03,R08 / P2 SMPS 1-T13 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B03,R08 / P3-P4 Server Rack L2-B03,R08 / P5-P6 SMPS 3-T23 1Cx95 1.1 kV, YY 21 2 1 4 84
PROJECT NO. 44PS8901 Title: CABLE SCHEDULE DOC NO.:
10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT: SAG2-COIMBATORE-MCN-AUGMENTATION REV NO. : 04
COIMBATORE 26-Oct-2021
LOCATION DATE :
A SECOND FLOOR
Server Rack L2-B03,R10 / P1 Server Rack L2-B03,R10 / P2 SMPS 2-T3 1Cx95 1.1 kV, YY 14 1 1 2 28
Server Rack L2-B03,R10 / P3 Server Rack L2-B03,R10 / P4 SMPS 1-T18 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B03,R11 / P1 Server Rack L2-B03,R11 / P2 SMPS 2-T4 1Cx95 1.1 kV, YY 14 1 1 2 28
Server Rack L2-B03,R11 / P3 Server Rack L2-B03,R11 / P4 SMPS 1-T19 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B04,R01 / P1-P2 Server Rack L2-B04,R01 / P3-P4 SMPS 2-T5 1Cx95 1.1 kV, YY 19 2 1 4 76
Server Rack L2-B04,R01 / P5-P6 Server Rack L2-B04,R01 / P7-P8 SMPS 1-T20 1Cx95 1.1 kV, YY 17 2 1 4 68
Server Rack L0-B03,R10 / P1-P2 Server Rack L0-B03,R10 / P3-P4 SMPS 2-T6 1Cx95 1.1 kV, YY 18 2 3 12 216
Server Rack L0-B03,R10 / P5-P6 Server Rack L0-B03,R10 / P7-P8 SMPS 1-T21 1Cx95 1.1 kV, YY 18 2 3 12 216
Server Rack L2-B04,R03 / P1-P2 Server Rack L2-B04,R03 / P3-P4 SMPS 2-T7 1Cx95 pl 17 2 1 4 68
Server Rack L2-B04,R03 / P5-P6 Server Rack L2-B04,R03 / P7-P8 SMPS 1-T22 1Cx95 1.1 kV, YY 17 2 1 4 68
Server Rack L2-B04,R04 / P1-P2 Server Rack L2-B04,R04 / P3-P4 SMPS 2-T8 1Cx95 1.1 kV, YY 16 1 1 2 32
Server Rack L2-B04,R04 / P5-P6 Server Rack L2-B04,R04 / P7-P8 SMPS 3-T24 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B04,R05 / P1 Server Rack L2-B04,R05 / P2 SMPS 2-T9,10,11 1Cx95 1.1 kV, YY 16 1 1 2 32
Server Rack L2-B04,R05 / P3-P4 25/7/2021 SMPS 3-T25 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B04,R06 / P1 Server Rack L2-B04,R06 / P2 SMPS 2-T10 1Cx95 1.1 kV, YY 15 1 1 2 30
Server Rack L2-B04,R06 / P3-P4 Server Rack L2-B04,R06 / P5-P6 SMPS 3-T26 1Cx95 1.1 kV, YY 14 1 1 2 28
Server Rack L2-B04,R09 / P1 Server Rack L2-B04,R09 / P2 SMPS 2-T11 1Cx95 1.1 kV, YY 19 1 1 2 38
Server Rack L2-B04,R09 / P3-P4 Server Rack L2-B04,R09 / P5-P6 SMPS 3-T27 1Cx95 1.1 kV, YY 12 1 1 2 24
Server Rack L2-B04,R10 / P1-P2 Server Rack L2-B04,R10 / P3-P4 SMPS 2-T12 1Cx95 1.1 kV, YY 20 2 1 4 80
Server Rack L2-B04,R10 / P5 Server Rack L2-B04,R10 / P6 SMPS 3-T28 1Cx95 1.1 kV, YY 13 1 1 2 26
Server Rack L2-B04,R11 / P1 Server Rack L2-B04,R11 / P2 SMPS 3-T3 1Cx95 1.1 kV, YY 13 1 1 2 26
Server Rack L2-B04,R11 / P3-P4 Server Rack L2-B04,R11 / P5-P6 SMPS 1-T23 1Cx95 1.1 kV, YY 20 2 1 4 80
PROJECT NO. 44PS8901 Title: CABLE SCHEDULE DOC NO.:
10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT: SAG2-COIMBATORE-MCN-AUGMENTATION REV NO. : 04
COIMBATORE 26-Oct-2021
LOCATION DATE :
A SECOND FLOOR
Server Rack L0-B04,R11 / P1 Server Rack L0-B04,R11 / P2 SMPS 3-T4 1Cx95 1.1 kV, YY 14 1 3 6 84
Server Rack L0-B04,R11 / P3-P4 Server Rack L0-B04,R11 / P5-P6 SMPS 1-T24,25 1Cx95 1.1 kV, YY 20 2 3 12 240
AUX DCDB-1
Server Rack L2-B05,R01 / P1-P2 Server Rack L2-B05,R01 / P3-P4 SMPS 3-T5,6 1Cx95 1.1 kV, YY 19 2 1 4 76 DC Cable to OTN DXC rack will be
L2-B05,R01
through Aux. DCDB. First cable will
(Feed for NLD CORE OTN
24 NLD CORE OTN DXC-02 18.0 kW terminate at Aux. DCDB and from
DXC-02
DCDB vendor will lay cable to OTN
Server Rack L2-B05,R01 / P5-P6 Server Rack L2-B05,R01 / P7-P8 SMPS 1-T26,27 (L2-B05,R01)(Refer 1Cx95 1.1 kV, YY 22 2 1 4 88 DXC rack.
remark)
AUX DCDB-2
Server Rack L2-B05,R04 / P1 Server Rack L2-B05,R04 / P2 SMPS 3-T7,8 1Cx95 1.1 kV, YY 18 2 1 4 72 DC Cable to OTN DXC rack will be
L2-B05,R04
through Aux. DCDB. First cable will
(Feed for NLD CORE OTN
25 NLD CORE OTN DXC-03 18.0 kW terminate at Aux. DCDB and from
DXC-03
DCDB vendor will lay cable to OTN
Server Rack L2-B05,R04 / P3-P4 Server Rack L2-B05,R04 / P5-P6 SMPS 2-T23,24 (L2-B05,R04)(Refer 1Cx95 1.1 kV, YY 19 2 1 4 76 DXC rack.
remark)
AUX DCDB-1
Server Rack L2-B06,R01 / P1 Server Rack L2-B06,R01 / P2 SMPS 3-T9,10,11 1Cx95 1.1 kV, YY 22 3 1 6 132 DC Cable to OTN DXC rack will be
L2-B06,R01
through Aux. DCDB. First cable will
(Feed for NLD CORE OTN
26 NLD CORE OTN DXC-01 20.0 kW terminate at Aux. DCDB and from
DXC-01
DCDB vendor will lay cable to OTN
Server Rack L2-B06,R01 / P3-P4 Server Rack L2-B06,R01 / P5-P6 SMPS 2-T25,26,27 (L2-B06,R01)(Refer 1Cx95 1.1 kV, YY 24 3 1 6 144 DXC rack.
remark)
Battery Rack 1-1 - P1 to P2 Battery Rack 1-1- P3 to P4 SMPS 1 Battery Rack 1-1 1Cx95 1.1 kV, YY 8 2 1 4 32
27
Battery Rack 1-2 - P1 to P2 Battery Rack 1-2- P3 to P4 SMPS 1 Battery Rack 1-2 1Cx95 1.1 kV, YY 8 2 1 4 32
Battery Rack 1-3- P1 to P2 Battery Rack 1-3- P3 to P4 SMPS 1 Battery Rack 1-3 1Cx95 1.1 kV, YY 8 2 1 4 32
28
Battery Rack 1-4 - P1 to P2 Battery Rack 1-4- P3 to P4 SMPS 1 Battery Rack 1-4 1Cx95 1.1 kV, YY 8 2 1 4 32
Battery Rack 2-1-P1 to P2 Battery Rack 2-1- P3 to P4 SMPS 2 Battery Rack 2-1 1Cx95 1.1 kV, YY 8 2 1 4 32
29
Battery Rack 2-2-P1 to P2 Battery Rack 2-2-P3 to P4 SMPS 2 Battery Rack 2-2 1Cx95 1.1 kV, YY 8 2 1 4 32
Battery Rack 2-3-P1 to P2 Battery Rack 2-3- P3 to P4 SMPS 2 Battery Rack 2-3 1Cx95 1.1 kV, YY 8 2 1 4 32
30
Battery Rack 2-4-P1 to P2 Battery Rack 2-4-P3 to P4 SMPS 2 Battery Rack 2-4 1Cx95 1.1 kV, YY 8 2 1 4 32
Battery Rack 3-1-P1 to P2 Battery Rack 3-1- P3 to P4 SMPS 3 Battery Rack 3-1 1Cx95 1.1 kV, YY 8 2 1 4 32
31
Battery Rack 3-2-P1 to P2 Battery Rack 3-2-P3 to P4 SMPS 3 Battery Rack 3-2 1Cx95 1.1 kV, YY 8 2 1 4 32
Battery Rack 3-3-P1 to P2 Battery Rack 3-3- P3 to P4 SMPS 3 Battery Rack 3-3 1Cx95 1.1 kV, YY 8 2 1 4 32
32
Battery Rack 3-4-P1 to P2 Battery Rack 3-4-P3 to P4 SMPS 3 Battery Rack 3-4 1Cx95 1.1 kV, YY 8 2 1 4 32
Note:
1. The Cable schedule has been prepared for full saturation.
2. Permissible Voltage drop for DC load is 2% considering actual server rack load
PROJECT NO. 44PS8901 DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED REV NO. : 04
LOCATION COIMBATORE DATE : 26-Oct-2021
ANNEXURE B: UPS DISTRIBUTION MATRIX
UPSDB 1 UPSDB 2
Phase MCB No. Rating
RACK LOAD RACK LOAD
1 vEPC POD -1 5.0 vEPC POD -7 5.0
2 vEPC POD -2 5.0 vEPC POD -8 5.0
3 vEPC POD -7 5.0 vEPC POD -1 5.0
4 vEPC POD -8 5.0 vEPC POD -2 5.0
R 32 A
5 Spare Spare
6 Spare Spare
7 Spare Spare
8 Spare Spare
PHASE LOADING 20.0 20.0
1 vEPC POD -3 5.0 vEPC POD -9 5.0
2 vEPC POD -4 5.0 vEPC POD -10 5.0
3 vEPC POD -9 5.0 vEPC POD -3 5.0
4 vEPC POD -10 5.0 vEPC POD -4 5.0
Y 32 A
5 Spare Spare
6 Spare Spare
7 Spare Spare
8 Spare Spare
PHASE LOADING 20.0 20.0
1 vEPC POD -5 5.0 vEPC POD -11 5.0
2 vEPC POD -6 5.0 vEPC POD -12 5.0
3 vEPC POD -11 5.0 vEPC POD -5 5.0
4 vEPC POD -12 5.0 vEPC POD -6 5.0
B 32 A
5 Spare Spare
6 Spare Spare
7 Spare Spare
8 Spare Spare
PHASE LOADING 20.0 20.0
LOAD ON DB 60.0 60.0
PROJECT NO. 44PS8901 Title: CABLE SCHEDULE DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
26-Oct-2021
LOCATION COIMBATORE DATE :
Server Rack L2-B01 R03 / P1 UPSDB 1-R1 3Cx10 1.1 kV, Cu flex Cable 17 1 2 17
1 vEPC POD-1 L2-B01 R03 5.0 kW
Server Rack L2-B01 R03 / P2 UPSDB 2-R3 3Cx10 1.1 kV, Cu flex Cable 18 1 2 18
Server Rack L2-B01 R04 / P1 UPSDB 1-R2 3Cx10 1.1 kV, Cu flex Cable 17 1 2 17
2 vEPC POD-2 L2-B01 R04 5.0 kW
Server Rack L2-B01 R04 / P2 UPSDB 2-R4 3Cx10 1.1 kV, Cu flex Cable 17 1 2 17
Server Rack L2-B01 R05 / P1 UPSDB 1-Y1 3Cx10 1.1 kV, Cu flex Cable 16 1 2 16
3 vEPC POD-3 L2-B01 R05 5.0 kW
Server Rack L2-B01 R05 / P2 UPSDB 2-Y3 3Cx10 1.1 kV, Cu flex Cable 16 1 2 16
Server Rack L2-B01 R06 / P1 UPSDB 1-Y2 3Cx10 1.1 kV, Cu flex Cable 15 1 2 15
4 vEPC POD-4 L2-B01 R06 5.0 kW
Server Rack L2-B01 R06 / P2 UPSDB 2-Y4 3Cx10 1.1 kV, Cu flex Cable 16 1 2 16
Server Rack L2-B01 R07 / P1 UPSDB 1-B1 3Cx10 1.1 kV, Cu flex Cable 14 1 2 14
5 vEPC POD-5 L2-B01 R07 5.0 kW
Server Rack L2-B01 R07 / P2 UPSDB 2-B3 3Cx10 1.1 kV, Cu flex Cable 15 1 2 15
Server Rack L2-B01 R08 / P1 UPSDB 1-B2 3Cx10 1.1 kV, Cu flex Cable 14 1 2 14
6 vEPC POD-6 L2-B01 R08 5.0 kW
Server Rack L2-B01 R08 / P2 UPSDB 2-B4 3Cx10 1.1 kV, Cu flex Cable 14 1 2 14
Server Rack L2-B01 R09 / P1 UPSDB 1-R3 3Cx10 1.1 kV, Cu flex Cable 13 1 2 13
7 vEPC POD-7 L2-B01 R09 5.0 kW
Server Rack L2-B01 R09 / P2 UPSDB 2-R1 3Cx10 1.1 kV, Cu flex Cable 14 1 2 14
Server Rack L2-B01 R10 / P1 UPSDB 1-R4 3Cx10 1.1 kV, Cu flex Cable 13 1 2 13
8 vEPC POD-8 L2-B01 R10 5.0 kW
Server Rack L2-B01 R10 / P2 UPSDB 2-R2 3Cx10 1.1 kV, Cu flex Cable 13 1 2 13
Server Rack L2-B01 R11 / P1 UPSDB 1-Y3 3Cx10 1.1 kV, Cu flex Cable 12 1 2 12
9 vEPC POD-9 L2-B01 R11 5.0 kW
Server Rack L2-B01 R11 / P2 UPSDB 2-Y1 3Cx10 1.1 kV, Cu flex Cable 13 1 2 13
Server Rack L2-B01 R12 / P1 UPSDB 1-Y4 3Cx10 1.1 kV, Cu flex Cable 11 1 2 11
10 vEPC POD-10 L2-B01 R12 5.0 kW
Server Rack L2-B01 R12 / P2 UPSDB 2-Y2 3Cx10 1.1 kV, Cu flex Cable 12 1 2 12
Server Rack L2-B01 R13 / P1 UPSDB 1-B3 3Cx10 1.1 kV, Cu flex Cable 11 1 2 11
11 vEPC POD-11 L2-B01 R13 5.0 kW
Server Rack L2-B01 R13 / P2 UPSDB 2-B1 3Cx10 1.1 kV, Cu flex Cable 12 1 2 12
Server Rack L2-B01 R14 / P1 UPSDB 1-B4 3Cx10 1.1 kV, Cu flex Cable 10 1 2 10
12 vEPC POD-12 L2-B01 R14 5.0 kW
Server Rack L2-B01 R14 / P2 UPSDB 2-B2 3Cx10 1.1 kV, Cu flex Cable 11 1 2 11
Note:
1. Overall margin of 10% extra has been considered for AC Rack cables for procurement.
2. Permissible Voltage drop for AC load is 2% considering actual server rack load
COIMBATORE
B Electrical
7 HT Relay 1 1 L&T
12 SMPS Battery Rack Smoke Detecter - - 1 3 4 QUANTA New SMPS battery only considered
PROJECT NO. 44PS8901 TITLE: CABLE SCHEDULE DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
COIMBATORE MCN-
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT : REV NO. : 04
AUGMENTATION
LOCATION COIMBATORE Issue date: 26-Oct-2021
Annexure C: RTU anf FAS Cable Schedule
Cable Qty in
Sr.No. Description of System Type From To Cable Type From TB To TB Remarks
Mtrs
A. New MLTP Panel Ground Floor ( Qty - 1 No)
RTU Panel (First floor 1 pair *1 sq. mm. shielded , Armoured RTU
1 AC Power fail RTU-MLTP/ 1 Hardwired Main LT Panel (Ground Floor) X1-53,X1-54 48
DCN Rack L1- B04,R04) Twisted pair cable DI 1 ,12V
RTU Panel (First floor 1 pair *1 sq. mm. shielded , Armoured RTU
2 AC Incomer trip fault RTU-MLTP/ 1 Hardwired Main LT Panel (Ground Floor) X1-49,X1-50 48
DCN Rack L1- B04,R04) Twisted pair cable DI 3, 12V
Modbus integration with HT Panel Relays (RTU- HT panel - Numerical Relays (Open 1 pair *1 sq. mm. shielded , Armoured
3 Soft Integration HT panel LM (Open Space ) XM-3,4 XM-1,2 20
HT PANEL Relay) Space) Twisted pair cable
NOTE: 1) DCN/Auxillary switch, Port 1 is reserved for RTU 1 & Port 2 is reserve for RTU 2 (Future)
PROJECT NO. 44PS8901 TITLE : CABLE SCHEDULE DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT : COIMBATORE-MCN-AUGMENTATION REV NO. : 04
LOCATION COIMBATORE Issue date: 26-Oct-2021
Annexure C: RTU anf FAS Cable Schedule
Cable Qty in
Sr.No. Description of System Type From To Cable Type From TB To TB Remarks
Mtrs
J SMPS
1 SMPS CAT 6 Cable SMPS 1-1-DCN Hardwired SMPS 1 (First Floor) (10070-AG2-CMBR-ED-003) DCN Switch (First Floor L1- B04,R04) Cat6 communication cable Ports Ports 22
2 SMPS CAT 6 Cable SMPS 1-1-DCN Hardwired SMPS 1 (First Floor) (10070-AG2-CMBR-ED-003) DCN Switch (First Floor L1- B04,R04) Cat6 communication cable Ports Ports 22
3 SMPS CAT 6 Cable SMPS 2-1-DCN Hardwired SMPS 1 (Second Floor)(10070-AG2-CMBR-ED-201) DCN Switch (First Floor L2- B03,R04) Cat6 communication cable Ports Ports 25
4 SMPS CAT 6 Cable SMPS 2-1-DCN Hardwired SMPS 1 (Second Floor)(10070-AG2-CMBR-ED-201) DCN Switch (First Floor L2- B03,R04) Cat6 communication cable Ports Ports 25
5 SMPS CAT 6 Cable SMPS 2-2-DCN Hardwired SMPS 2 (Second Floor)(10070-AG2-CMBR-ED-202) DCN Switch (First Floor L2- B03,R04) Cat6 communication cable Ports Ports 25
6 SMPS CAT 6 Cable SMPS 2-2-DCN Hardwired SMPS 2 (Second Floor)(10070-AG2-CMBR-ED-202) DCN Switch (First Floor L2- B03,R04) Cat6 communication cable Ports Ports 25
7 SMPS CAT 6 Cable SMPS 2-3-DCN Hardwired SMPS 3 (Second Floor)(10070-AG2-CMBR-ED-203) DCN Switch (First Floor L2- B03,R04) Cat6 communication cable Ports Ports 25
8 SMPS CAT 6 Cable SMPS 2-3-DCN Hardwired SMPS 3 (Second Floor)(10070-AG2-CMBR-ED-203) DCN Switch (First Floor L2- B03,R04) Cat6 communication cable Ports Ports 25
To FAN Starter panel ( First Floor ) - MJB- 3 C* 2.5 sq. mm. copper conductor,
3 Hardwired Main Junction Box-1 (First Floor) FAN Starter panel (First Floor)) TBD at site TBD at site 10
FSP armoured FRLS PVC insulated cables
Battery Rack
SMPS 1 Controller (Second Floor)(10070-AG2-CMBR-ED- 1 pair *1 sq. mm. shielded , Armoured
4 Smoke Detector 2-1 Hardwired Smoke Detector 1-1 TBD at site TBD at site 7
201) Twisted pair cable
SD3-SMPS 1
Battery Rack
1 pair *1 sq. mm. shielded , Armoured
5 Smoke Detector 2-2 Hardwired Smoke Detector 1-2 Main Junction Box-1 (Second Floor Floor) TBD at site TBD at site 10
Twisted pair cable
SD4-MJB
Battery Rack
SMPS 2 Controller (Second Floor)(10070-AG2-CMBR-ED- 1 pair *1 sq. mm. shielded , Armoured
6 Smoke Detector 2-1 Hardwired Smoke Detector 2-1 TBD at site TBD at site 7
202) Twisted pair cable
SD5-SMPS 2
Battery Rack - 2
1 pair *1 sq. mm. shielded , Armoured
7 Smoke Detector 2-2 Hardwired Smoke Detector 2-2 Main Junction Box-1 (Second Floor) TBD at site TBD at site 13
Twisted pair cable
SD6-MJB
Battery Rack
SMPS 3 Controller (Second Floor)(10070-AG2-CMBR-ED- 1 pair *1 sq. mm. shielded , Armoured
8 Smoke Detector 3-1 Hardwired Smoke Detector 3-1 TBD at site TBD at site 7
203) Twisted pair cable
SD5-SMPS 3
Battery Rack - 3
Main Junction Box-1 (Second Floor near Fan Starter 1 pair *1 sq. mm. shielded , Armoured
9 Smoke Detector 3-2 Hardwired Smoke Detector 3-2 TBD at site TBD at site 19
Panel ) Twisted pair cable
SD6-MJB
To FAN Starter panel (Second Floor)- MJB- 3 C* 2.5 sq. mm. copper conductor,
10 Hardwired Main Junction Box-1 (Second Floor) FAN Starter panel TBD at site TBD at site 10
FSP armoured FRLS PVC insulated cables
PROJECT NO. 44PS8901 TITLE : CABLE SCHEDULE DOC NO.: 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED PROJECT : COIMBATORE-MCN-AUGMENTATION REV NO. : 04
LOCATION COIMBATORE Issue date: 26-Oct-2021
Annexure C: RTU anf FAS Cable Schedule
Cable Qty in
Sr.No. Description of System Type From To Cable Type From TB To TB Remarks
Mtrs
H. Battery Rack Smoke Detection
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
1 Detector 1 -1 Hardwired SMPS 1 (Second Floor) Smoke Detector 1 (mounted in Battery rack-1) conductor, armoured FRLS PVC SMPS 1-1 MCB-36 2,5 8
SMPS 1 - SD1 insulated cables
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
2 Detector 1-2 Hardwired SMPS 1 (Second Floor) Smoke Detector 2 (mounted in Battery rack-1) conductor, armoured FRLS PVC SMPS 1-2 MCB-37 2,5 8
SMPS 1 - SD2 insulated cables
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
3 Detector 2-1 25/7/2021 SMPS 2 (Second Floor) Smoke Detector 3 (mounted in Battery rack-2) conductor, armoured FRLS PVC SMPS 2-1 MCB-36 2,5 8
SMPS 2 - SD3 insulated cables
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
4 Detector 2-2 Hardwired SMPS 2 (Second Floor) Smoke Detector 4 (mounted in Battery rack-2) conductor, armoured FRLS PVC SMPS 2-2 MCB-37 2,5 8
SMPS 2 - SD4 insulated cables
Electrical SCOPE
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
5 Detector 3-1 Hardwired SMPS 3 (Second Floor) Smoke Detector 5 (mounted in Battery rack-3) conductor, armoured FRLS PVC SMPS 3-1 MCB-36 2,5 8
SMPS 3- SD5 insulated cables
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
6 Detector 3-2 Hardwired SMPS 3 (Second Floor) Smoke Detector 6 (mounted in Battery rack-3) conductor, armoured FRLS PVC SMPS 3-2 MCB-37 2,5 8
SMPS 3 - SD6 insulated cables
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
5 Detector 3-1 Hardwired SMPS 4 (Second Floor) Smoke Detector 7 (mounted in Battery rack-3) conductor, armoured FRLS PVC SMPS 4-1 MCB-36 2,5 8
SMPS 4- SD7 insulated cables
Power Supply (-48 VDC ) to Smoke 3 C* 2.5 sq. mm. copper
6 Detector 3-2 Hardwired SMPS 4 (Second Floor) Smoke Detector 8 (mounted in Battery rack-3) conductor, armoured FRLS PVC SMPS 4-2 MCB-37 2,5 8
SMPS 4 - SD8 insulated cables
Cable Qty in
Sr.No. Description of System Type From To Cable Type From TB To TB Remarks
Mtrs
1 pair *1 sq. mm. shielded , Armoured
25 Main Junction Box-1 Hardwired Rack - R08, Bay 01 (Second Floor) Main Junction Box-1 TBD at site TBD at site 10
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
26 Main Junction Box-1 Hardwired Rack - R09, Bay 01 (Second Floor) Main Junction Box-1 TBD at site TBD at site 11
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
27 Main Junction Box-1 Hardwired Rack - R10, Bay 01 (Second Floor) Main Junction Box-1 TBD at site TBD at site 12
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
28 Main Junction Box-1 Hardwired Rack - R11, Bay 01 (Second Floor) Main Junction Box-1 TBD at site TBD at site 13
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
29 Main Junction Box-1 Hardwired Rack - R12, Bay 01 (Second Floor) Main Junction Box-1 TBD at site TBD at site 14
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
30 Main Junction Box-1 Hardwired Rack - R13, Bay 01 (Second Floor) Main Junction Box-1 TBD at site TBD at site 16
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
31 Main Junction Box-1 Hardwired Rack - R14, Bay 01 (Second Floor) Main Junction Box-1 TBD at site TBD at site 17
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
32 Main Junction Box-2 Hardwired Rack - R01, Bay 02 (Second Floor) Main Junction Box-2 TBD at site TBD at site 7
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
33 Main Junction Box-2 Hardwired Rack - R02, Bay 02 (Second Floor) Main Junction Box-2 TBD at site TBD at site 8
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
34 Main Junction Box-2 Hardwired Rack - R09, Bay 02 (Second Floor) Main Junction Box-2 TBD at site TBD at site 10
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
35 Main Junction Box-2 Hardwired Rack - R10, Bay 02 (Second Floor) Main Junction Box-2 TBD at site TBD at site 11
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
36 Main Junction Box-2 Hardwired Rack - R05, Bay 02 (Second Floor) Main Junction Box-2 TBD at site TBD at site
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
37 Main Junction Box-3 Hardwired Rack - R01, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site 7
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
38 Main Junction Box-3 Hardwired Rack - R02, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site 10
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
39 Main Junction Box-3 Hardwired Rack - R03, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
40 Main Junction Box-3 Hardwired Rack - R04, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site 12
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
41 Main Junction Box-3 Hardwired Rack - R05, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site 13
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
42 Main Junction Box-3 Hardwired Rack - R08, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site 14
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
43 Main Junction Box-3 Hardwired Rack - R10, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site 16
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
44 Main Junction Box-3 Hardwired Rack - R11, Bay 03 (Second Floor) Main Junction Box-3 TBD at site TBD at site 16
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
45 Main Junction Box-4 Hardwired Rack - R01, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 7
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
46 Main Junction Box-4 Hardwired Rack - R02, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 8
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
47 Main Junction Box-4 Hardwired Rack - R03, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 10
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
48 Main Junction Box-4 Hardwired Rack - R04, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 11
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
49 Main Junction Box-4 Hardwired Rack - R05, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 12
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
50 Main Junction Box-4 Hardwired Rack - R06, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 13
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
51 Main Junction Box-4 Hardwired Rack - R10, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 11
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
52 Main Junction Box-4 Hardwired Rack - R11, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 12
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
53 Main Junction Box-4 Hardwired Rack - R12, Bay 04 (Second Floor) Main Junction Box-4 TBD at site TBD at site 13
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
54 Main Junction Box-5 Hardwired Rack - R01, Bay 05 (Second Floor) Main Junction Box-5 TBD at site TBD at site 10
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
55 Main Junction Box-5 Hardwired Rack - R04, Bay 05 (Second Floor) Main Junction Box-5 TBD at site TBD at site 11
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
56 Fan monitoring bay Hooter-1 to MJB-1 Hardwired Fan monitoring bay Hooter-1 (First floor) Main Junction Box-1 (First Floor near L1-B02) TBD at site TBD at site 4
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
57 Fan monitoring bay Hooter-2 to MJB-2 Hardwired Fan monitoring bay Hooter-2 (First floor) Main Junction Box-2 (First Floor near L1-B05) TBD at site TBD at site 4
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
58 Fan monitoring bay Hooter-1 to MJB-1 Hardwired Fan monitoring bay Hooter-1 (Second floor) Main Junction Box-1 (Second Floor near L2-B01) TBD at site TBD at site 4
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
59 Fan monitoring bay Hooter-2 to MJB-2 Hardwired Fan monitoring bay Hooter-2 (Secondt floor) Main Junction Box-2 (Second Floor near L2-B02) TBD at site TBD at site 4
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
60 Fan monitoring bay Hooter-3 to MJB-3 Hardwired Fan monitoring bay Hooter-3 (Second floor) Main Junction Box-3 (Second Floor near L2-B03) TBD at site TBD at site 4
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
61 Fan monitoring bay Hooter-4 to MJB-4 Hardwired Fan monitoring bay Hooter-4 (Second floor) Main Junction Box-4 (Second Floor near L2-B04) TBD at site TBD at site 4
Twisted pair cable
1 pair *1 sq. mm. shielded , Armoured
62 Fan monitoring bay Hooter-5 to MJB-5 Hardwired Fan monitoring bay Hooter-5 (Second floor) Main Junction Box-5 (Second Floor near L2-B05) TBD at site TBD at site 4
Twisted pair cable
Note: Fan monitoring system for vendor supplied racks is not provided
PROJECT NO. 44PS8901 CABLE SCHEDULE (PHASE III) DOC. NO 10070-E84-IN-TN-CMBR-GVRD-NB-0001-502
CLIENT RELIANCE JIO INFOCOMM LIMITED REV NO; 04
LOCATION COIMBATORE ISSUE DATE : 26-Oct-2021
PROJECT COIMBATORE-MCN-AUGMENTATION
I. POWER/ CONTROL CABLE SUMMARY
Calc. length Total length in
Sr. No. Size in Sqmm Type Remarks
in mtrs. mtrs.
A. HV CABLES
1 3Cx185 33 kV (E), Al XLPE 0m 0m
2 3Cx300 11 kV (E), Al XLPE 120 m 144 m
3 3Cx300 6.6 kV (E), Al XLPE 0m
B. DC CABLES
1 1Cx150 (RED) 1.1 kV, YY 0m 0
2 1Cx150 (BLACK) 1.1 kV, YY 0m 0
3 1Cx95 (RED) 1.1 kV, YY 3800 m 4560
4 1Cx95 (BLACK) 1.1 kV, YY 3800 m 4560
5 1Cx70 (RED) 1.1 kV, YY 0m 0
6 1Cx70 (BLACK) 1.1 kV, YY 0m 0
5 1Cx50 (RED) 1.1 kV, YY 0m 0
6 1Cx50 (BLACK) 1.1 kV, YY 0m 0
C. POWER AND CONTROL ELECTRICAL CABLES
1 1Cx240 1.1 kV, 2XFY 0m 0m
2 4Cx300 1.1 kV, A2XFY 379 m 455 m
3 4Cx185 1.1 kV, A2XFY 0m 0m
4 4Cx150 1.1 kV, A2XFY 0m 0m
5 4Cx95 1.1 kV, A2XFY 0m 0m
6 4Cx50 1.1 kV, A2XFY 0m 0m
7 4Cx35 1.1 kV, A2XFY 1408 m 1690
8 4Cx120 1.1 kV, 2XY 914 m 1097 m
9 4Cx10 1.1 kV, YWY 38 m 38 m
10 4Cx6 1.1 kV, YWY 0m 0m
11 4Cx4 1.1 kV, YWY 115 m 138 m
12 4Cx2.5 1.1 kV, YWY 1171 m 1405 m
13 4Cx1.5 1.1 kV, YWY 1454 m 1745 m
14 3Cx4 1.1 kV, YY 0m
15 3Cx2.5 1.1 kV, YY 0m 0m
16 3Cx2.5 1.1 kV, YWY 813 m 975 m
17 19Cx1.5 1.1 kV, YWY 0m 0m
18 12Cx1.5 1.1 kV, YWY 495 m 594 m
19 7Cx1.5 1.1 kV, YWY 486 m 584 m
22 7Cx1.5 1.1 kV, YY 0m 0m
23 3Cx10 1.1 kV, Cu flex Cable 0m 0m
24 3Cx10 1.1 kV, YWY 400 m 480 m
25 4Cx10 25/7/2021 0m 0m
26 2Cx10 1.1 kV, YY, FRLS 0m 0m
27 1Cx300 1.1 kV, Cu. Flex Cable 648 m 778 m
(BLACK)
28 1Cx120 1.1 kV, YY, FRLS 0m 0m