P-01

N&S Date: 2 December 2022


Weather Condition:
DPR - Summary Sheet Clear

Client: SHELL PAKISTAN LTD.

Contractor: NASEEM & SON.

Project: Maintenance of C-01 Base Oil Tank at CFP Tank Farm Area LOBP

Prev. Today’s
Description Of Work Progress Progress Total Remarks 

Permit issuance and Isolation. 100% - 100% Yesterday


i. 3 plates of 2nd shell blasting done and 1st coat applied.
Cleaning of Tank 50% - 50%
Today
i. 3rd shell started 2 plates of 3rd & 2 plates of 4th shell
blasting done and 1st coat applied today
Installation of net Screen 100% 100% ii. Tomorrows Grit blasting & Painting will be continued
Grit Blasting of tank & application of
Primer 35% 5% 40%
Welding of patch plates and doublers - -
Power Brushing of Welding Seam of
bottom plates 100%
Inspection (VBT) of Bottom By Third Party 80% 20% 100%
Closing of expansion joint by sika -
Application of mid coat & Final coat of
paint -
Supply of gasket stud for Box up -
Removal of scaffolding -
 Housekeeping & De-mobilization

Progress
Pictures

Equipment Deployed Staff Labour


Deployed Deployed
Mobile Crane 0 Project Manager 0 Rescuers 4

Site Office 0 Construction Manager 0 Fabricator 0

Warehouse 0 Planning & Co-ordination Engr 0 Fitter 0

Paint Store 0 Manager HR / Admin 0 Grit blaster/Painter 3

Vehicles 0 Mechanical Engineer 1 Welder 0

Grinders 0 Trainee 0 Mechanical Tech 0

Compressor 1 Foreman / In-charge Rigger / Scaffold 2

Scaffolding with Planks 1 Supervisor 1 Helper 5

Drill Machines 2 Safety In-charge 1 Cook 0

Vacuum Machine 0 Fire Watcher 1 Driver 0

Hopper 1 Store Keeper 1 Office Boy 0

Hand Tools 10 Accountant/Site Admin 0 Painter 3


_______________________ -
Representative
Representative
Abdul Hadi
Ali RAZA Shell Pakistan Ltd.