Professional Documents
Culture Documents
Method Statement for Unloading and Erection of Pipe Spools in Pipe Rack Area
0 02.12.2021
Table of Contents
01 Scope of works 04
03 Construction procedures 05
04 Conformance criteria 07
05 Materials 07
09 Environment requirement 08
References
10 08
Attachment:
11 08
Appendix A: Sample test reports
1. Scope of work
The scope of this procedure applies specifically and only for the execution of
“Perstorp Elephant Project”. This procedure covers supervision and method used for
Unloading and Erection of Pipe Spools in Pipe Rack Area.
2. Personal Rules and responsibility
Project Manager:
Project Manager is responsible for developing and managing technology projects and
their cost, time and scope. Responsibilities include: project plan, communication plan,
allocating tasks and setting milestone.
Management of the safety control supervisors to check the site condition in the safety
concern
Report to the Site Manager in relation to the health, safety and environment protection
activities.
Workers: The Project Worker's main function is to manage the day-to-day activities of a
project or part of a service. The Project Worker will also assist the Service Manager to
develop and support a range of flexible, creative and responsive community-based
initiatives for people with dementia and their careers.
TBT/Job specific training will be given to all members before starting the activity.
Necessary work permit should be taken by TFPL from APG prior to the start-up of activity.
All equipment, tools & tackles should be having required documents like TPI, Calibration &
MTC etc.
TFPL will inspect that the road is levelled and well compacted and also free from hurdles.
If not, TFPL will inform APG to take necessary action.
Speed of the Mobile crane or Farana should not be more than 10kmph while moving.
TFPL will ensure the signalman’s presence while moving the Mobile crane or Farana.
Only certified Mobile Crane or Farana, and lifting tools & tackles will be used.
Rigger will fix the Lifting Belt on Pipe Spools by adjusting its CG.
Mobile Crane or Farana will slightly lift the Pipe Spools to take a load test.
After successful load test that Pipe Spools will be shifted to the desired location with the
help of Mobile Crane or Farana.
At erection point, lifting belt will be fixed to the Pipe Spools and guide rope will be installed
at both ends of the pipe.
Only signal man will give the signal to the Mobile Crane or Farana, operator.
Supervisor/safety person will ensure that no one comes under suspended load.
Then Pipe Spools will be lifted slightly and placed on the rack with proper locking.
De-slinging of Pipe Spools will be done with the help of boom lift, before which Pipe
Spools will be stabilized.
Same procedure will be repeated for another Pipe Spools erection also.
Before leaving the work location supervisor will ensure that all erected members are
properly stabilized.
Method 1
Dismantle upper Beam 1 & Beam 2 and placing pipe spools by following below process
1. Belt & Guide Rope to be placed at two ends of Beam 1 (as shown in sketch 1) with the
help of Boom lift (man lift) and other end of the belts to be inserted into Crane Hook.
2. With the help of crane hold the Beam1 without load on crane
3. Remove the Bolts (from the beam) with the help of tools resting on Boom Lift.
4. Remove the Beam 1 with the help of Crane and safely place at the ground.
5. Lift the Pipe spools on 1st Tire and insert into the pipe rack on both sides.
6. After placing Pipe spools tie on support structure with the help of Rope.
7. Place the Beam1 on the 1st Tier with the help of crane and boom lift and fix the beam
with bolts.
SKETCH 1
Method 2
1. Place the lifting belt and chain block on pipe spool and Crane as per sketch 2
2. Lift the spool to check the cg and balance of pipe spool at 1 meter height.
3. Lift the pipe spool to required elevation and insert the same into the pipe rack with
the help of Boom lift, Chain block & Mobile Crane or Farana.
4. Once the Pipe spool is inserted and placed on pipe rack then change the position of
belt to further insert into the pipe rack.
5. Once pipe spool is placed at desired location on pipe rack release the load from
Mobile Crane or Farana and tie the pipe spool & remove the belt with the help of
Boom lift.
SKETCH 2
4. Conformance criteria
5. Materials:
Lifting Belt, Tag Line, Hooks, De shackles., Full body harness, Other Tools & Tackles.
Boom lift
Assessment shall be done for the activity, access, illumination and work platform.
Ensure that all tools and tackles and lifting equipment has the valid third-party certificates
Ensure that Mobile Crane or Farana operator and riggers are qualified and trained
Ensure that job specific PPE with Mandatory PPE are provided to all including full body
harness
Ensure to barricades the area with warning signs board & only authorized person allow to
working area.
Do not over load the Mobile Crane or Farana, Safe working capacity (SWL).
Before start activity all equipment’s, tools tackle, crane also must be inspected by concern
person.
9. Environmental requirements
Prevent noise pollution by using environment friendly machines and equipment’ s and oils.
Follow govt. guidelines on the air pollutions. Must have PUC certificate
Ensure to collect and dispose of the oil spillage (if any) as per local govt. rules
Submitted separately.
10. References Attachment: Third party certificates of crane and tools and tackles,
submitted separately.