PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS002 R0


Contract No.: SER/0153/21-22 Date Issued: 29.12.2021

Project: Perstorp Elephant Project.

Method Statement for Scaffolding Erection of Pipe Rack Area

Contractor: TRIMURTI FABRICATORS PVT LTD

PMC: Aker Powergas Solutions


Client: Perstorp Industries India Pvt. Ltd.
TFPL Job No: 50611-2041

0 9.12.2021 Issued for RAHMAT JAVID


Approval

Rev Date APG PEM Document Status Prepared By Checked Approved By


Status by

Doc Title: MS for Erection of structural Column Page 1 of 7


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS002 R0


Contract No.: SER/0153/21-22 Date Issued: 29.12.2021

Rev. Date Revision Details

0 29.12.2021 First Issue

Doc Title: MS for Erection of structural Column Page 2 of 7


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS002 R0


Contract No.: SER/0153/21-22 Date Issued: 29.12.2021

Section Title Page

01 Scope of works 4

02 Personnel rules and responsibilities 4

Construction Procedure
03 5

Conference Criteria
04 6

Plant and Equipment


05 6

Storage and Handling


06 6

07 Environmental requirements
7

Doc Title: MS for Erection of structural Column Page 3 of 7


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS002 R0


Contract No.: SER/0153/21-22 Date Issued: 29.12.2021

1. Scope of work

The scope of this procedure applies specifically and only for the execution of
“Perstorp Elephant Project”. This procedure covers supervision and method used for
Scaffolding Erection and Dismantling at Pipe Rack Area
2. Personal Rules and responsibility

 Project Manager:
      Project Manager is responsible for developing and managing technology projects and
their cost, time and scope. Responsibilities include: project plan, communication plan,
allocating tasks and setting milestone.

 Preparation of the work procedure and review

 Document and drawing control for lifting works

 Calibration and maintenance of equipment

 Notification to QA/QC for inspection and testing

 Training for Superintendents, Supervisors and Staffs

 Site Engineer: A site engineer offers advice in the planning, co-ordination and


supervision of technical aspects of construction projects. A site engineer's role is
vital to a construction project: they have a number of responsibilities including
solving technical issues, providing advice, management and preparing reports.

 Apply to approved drawings on site

 Provide for inspection/test

 Control of workers on site

 Preservation of material on site

 Supervisor: A Supervisor oversees the construction activities that take place on the


Work site. They are heavily involved in planning, organizing and controlling
Projects.
Construction Supervisors are responsible for supervising the contractors and staff
while maintaining a safe work environment.

Doc Title: MS for Erection of structural Column Page 4 of 7


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS002 R0


Contract No.: SER/0153/21-22 Date Issued: 29.12.2021

 Supervision for lifting activities

 Distribute the job to workforce

 Cooperating with worker on workplace safety and health matters.


 Safety officer: The Safety Officer is responsible for monitoring and assessing
hazardous and unsafe situations and developing measures to assure
personnel safety. The Safety Officer ensures the Site Safety and Health Plan is
prepared and implemented. The Safety Officer ensures there
are safety messages in each Incident Action Plan.

 Management of the safety control supervisors to check the site condition in the safety
concern

 Report to the Site Manager in relation to the health, safety and environment protection
activities.
Workers: The Project Worker's main function is to manage the day-to-day activities of a
project or part of a service. The Project Worker will also assist the Service Manager to
develop and support a range of flexible, creative and responsive community-based
initiatives for people with dementia and their careers.

3- Construction procedure to be followed.

 Before the work is started, a brief safety tool box talk shall be given on the scope of
work and the hazards associated with the work to all the concerned for safety
awareness.
 Display of cautionary sign boards.
 Before Start work Provide the proper PPE.
 Barricading of the work area shall be done by caution tape to avoid unauthorized
persons entering
inside the work area.
 All M.S Scaffolding & Tools tackles should be cleaned Properly & physical inspection is
must before executing the job.
 Only trained/experienced persons should be allowed to operation.
 General work permit, work at Height.
 Ensure Safety compliance, PPE's, tool box talk & statutory compliance.

Doc Title: MS for Erection of structural Column Page 5 of 7


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS002 R0


Contract No.: SER/0153/21-22 Date Issued: 29.12.2021

4- Erection and Installation of Scaffolding inside the pipe rack Crew:

 Coordinator-
 Supervisor: -
 Safety officer: -
 Scaffolder.……………… Nos.
 Supervisor……………………........... Nos.
Rigger …………………………………

5-Construction Equipment/tools used for Installation of Scaffolding Work-

 M.S Cup lock Scaffolding material.


 Tag system ( Green, Yellow, Red ).
 PP Rope
 Personal protective equipment – full body harness belt Safety helmet, Cotton Hand
Gloves, safety goggle, Safety Shoes, FBH.
 Barricading tape, sigh board.
 Proper hand tools should be used for scaffolding work activity.

6-Method statement for Installation of MS Scaffolding of pipe Rack. for hot work
activity. EX Welding, Grinding Work.

 Appropriate and sufficient arrangements have been made for the initiation of
emergency response and, where necessary, rescue of persons from pipe rack.
 Permanent supervision is provided at the site (attendant).
 All Tools to be used on site must be suitable for the work intended. the scaffolders
must ensure that the tools are inspected.
 All the Scaffolder working with scaffold shall be made available with tools carrying
 Scaffolding operation shall commence only after appropriate are secured ( Permit,
Work at height).
 All Scaffolds shall be erected, altered and Dismantled only under the competent
supervisor
 Limited workers shall be allowed to work for scaffolding work – two scaffolders and 2
helpers.

 Devise an appropriate emergency plan before the work starts. The following is an
elaboration of these basic principles and what you need to do.

Doc Title: MS for Erection of structural Column Page 6 of 7


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS002 R0


Contract No.: SER/0153/21-22 Date Issued: 29.12.2021

 safety officer registered under the Factories and Industrial Undertakings (Safety
Officers and Safety Supervisors) Regulations.
 Fall Protection. Full body harness belt, shine board, railing system. ( (Toe guard,
Mid rail, Top rail ).
 . Safety Net if required.
 Close the work permit with good housekeeping.

7- Environmental requirements:

Prevent noise pollution by using environment friendly machines and equipment’ s and oils.

Minimize the dust generation as low as practicable.

Follow govt. guidelines on the air pollutions. Must have PUC certificate

Ensure to collect and dispose of the oil spillage (if any) as per local govt. rules

Keep area clean.

This method statement should be reviewed by the site management team and a copy of it will
be circulated to those nominated for comment and the nominated staff member to be finally
approved all comments should be recorded on the approval sheet.

Doc Title: MS for Erection of structural Column Page 7 of 7