You are on page 1of 10

SAUDI ARAMCO ID/PIEU-30-Nov-2018 - REV.2018.11.00 (Standards Cutoff - Nov 30,2018) Rev 2018.11.

00 30-Nov-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Internal FBE Coating of Field Girth Welds & Repairs SATIP-H-002-08 27-Jan-19 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Procedure for Internal FBE Coating of


1.1 SAIC-H-2057 SAIC-H-2057 H RH RH The procedure shall be approved by RSA (CSD).
Field Girth Welds & Repairs*

1.2 Coating Personnel Qualification SAIC-H-2010 SAIC-H-2010 H RH R

2.0 MATERIAL RECEIVING

Verification of FBE Powder materials and


2.1 Abrasive materials including Storage and SAIC-H-2058 SAIC-H-2058 H W W
Handling (APCS-102)

Inspection and verification of FBE Coating


2.2 SAIC-H-2013 SAIC-H-2013 H H W Use SATR-H-2004 & SATR-H-2012
application equipment

3.0 FIELD APPLICATION

Surface Preparation of Pipe Joints for SAIC-H-2059


3.1 SAIC-H-2059 H H W Use SATR-H-2011.
Field Internal Coating

Verification/Calibration of Crawler+internal Use SATR-H-2011.


3.2 SAIC-H-2059 SAIC-H-2059 H H W
mechanical blasting head on "TEST PUP" Test Set-up & Calibration each Production run

Verification/Calibration of Use SATR-H-2008, SATR-H-2009, SATR-H-2010 &


3.3 Crawler+Powder spray head on "TEST SAIC-H-2060 SAIC-H-2060 H H W SATR-H-2012
PUP" Prior to internal of production welds Test Set-up & Calibration each Production run

Internal FBE Coating Application on Field Use SATR-H-2012


3.4 SAIC-H-2060 SAIC-H-2060 H H W
Girth Welds Including Repairs Repairs (Rework criteria) is clearly identified

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-30-Nov-2018 - REV.2018.11.00 (Standards Cutoff - Nov 30,2018) Rev 2018.11.00 30-Nov-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Internal FBE Coating of Field Girth Welds & Repairs SATIP-H-002-08 27-Jan-19 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Final Inspection and Acceptance (Using


3.5 SAIC-H-2060 SAIC-H-2060 H H H Use SATR-H-2012
Video Camera)

GENERAL NOTES

1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
2
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
3
representative in attendance.
4 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND

H Hold Point for QC Inspection/ Test R Review of Documents


W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-30-Nov-2018 - REV.2018.11.00 (Standards Cutoff - Nov 30,2018)

Saudi Aramco: Company General Use


Rev 2018.11.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


27-Jan-19 1-Oct-18

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-30-Nov-2018 - REV.2018.11.00 (Standards Cutoff - Nov 30,2018)

Saudi Aramco: Company General Use


Rev 2018.11.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


27-Jan-19 1-Oct-18

Saudi Aramco: Company General Use