You are on page 1of 10

SAUDI ARAMCO ID/PIEU -25 -Apr-2018 - REV. 2018.02.00 (Standards Cutoff -February 28, 2018) Rev. 2018.02.

00 28-Feb-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Renovation & Repair Coating for Submerged Services (APCS-113C) SATIP-H-002-11 25-Apr-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Paint & Coating Application Procedure for Use CSD approved Application Procedure for Stopac &
1.1
Immersed Service
SAIC-H-2080 SAIC-H-2080 RH RH Canusa Applications.

Coating Personnel Qualification &


Certification Card
1.2 a) Blaster SAIC-H-2010 SAIC-H-2010 RH RH
b) Paint applicator
c) Crew supervisor

MATERIAL
2.0
RECEIVING

Materials Verification, Visual inspection,


S. Aramco shall inspect the first batch of delivery of paint
2.1 Storage and Handling-APCS-113C SAIC-H-2081 SAIC-H-2081 W W materials and abrasive.
Coating Materials

2.2 Equipment Inspection SAIC-H-2026 SAIC-H-2026 H H Use SATR-H-2004

3.0 APPLICATION

3.1 Pre-Cleaning Inspection SAIC-H-2082 SAIC-H-2082 H W

Inspection of Coat and Tape Wrap


Application
a. Surface Preparation
3.2
b. Paste application
SAIC-H-2082 SAIC-H-2082 H W
c. Tape Wrap application
d. Outer wrap application

Inspection of APCS-113C tape wrap


3.3
application
SAIC-H-2082 SAIC-H-2082 H W

ACCEPTANCE (Prior
4.0
to Backfill)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -25 -Apr-2018 - REV. 2018.02.00 (Standards Cutoff -February 28, 2018) Rev. 2018.02.00 28-Feb-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Renovation & Repair Coating for Submerged Services (APCS-113C) SATIP-H-002-11 25-Apr-17 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Final Inspection prior to backfill


Use SATR-A-2008
4.1 a. Visual Inspection SAIC-H-2082 SAIC-H-2082 H H (Internal Cleanliness Report)
b. Holiday Test

4.2 Inspection of Repair for APCS-113C SAIC-H-2082 SAIC-H-2082 H H

GENERAL NOTES

1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
2
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
3
representative in attendance.
4 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND

H Hold Point for QC Inspection/ Test R Review of Documents


W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -25 -Apr-2018 - REV. 2018.02.00 (Standards Cutoff -February 28, 2018)

Saudi Aramco: Company General Use


Rev. 2018.02.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


25-Apr-17 25-Apr-18

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU -25 -Apr-2018 - REV. 2018.02.00 (Standards Cutoff -February 28, 2018)

Saudi Aramco: Company General Use


Rev. 2018.02.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


25-Apr-17 25-Apr-18

Saudi Aramco: Company General Use