SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Welding Procedure
1.1 Specifications/Welding Procedure SAIC-W-2058 SAIC-W-2058 RH RH
Qualification Record (WPS/WPQR)
Recv Insp & Verification of Welding SA shall verify & inspect the first batch of delivered
2.1 Consumables - (Properties, Type, SAIC-W-2064 SAIC-W-2064 H W consumables, then random inspection thereafter.
Approved source, storage, etc.)
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-W-2065
Verify Welding Equipment Calibration,
2.2 SAIC-W-2065 SATR-W-2009 H W
Welding Machines & Electrode Ovens Refer to Note 1 of the General Notes
SATR-W-2011
3.0 INSTALLATION
3.2 Welding of Strip Linings See SATIP N0: W-016-01 (As Applicable)
SAIC-W-2066
Control of Welding Consumables-Storage,
3.5 SAIC-W-2066 SATR-W-2009 H S
Handling, Issue, Conditioning
SATR-W-2010
SAIC-W-2068
3.7 Pre-Welding Inspection SAIC-W-2068 H W Refer to Note 1 of the General Notes
SATR-W-2006
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Selection of Weld Joints for NDE SAIC-W-2071 a) SA participates in the selection process.
3.10 SAIC-W-2071 H W
(Vessels) SATR-W-2007 b) Modify SATRs as needed
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of
1
Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
###
###