SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
2.2 Structural Attachments & Access See Remarks See Remarks Refer to SATIP-M-001-01
3.0 INSTALLATION
Cathodic Protection (if required for tank Refer to SATIP X-600-02 or J-500-01
3.5 See Remarks See Remarks
bottom an/or internal shell) (Internal CP) as applicable
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
3.9 Grouting (if required) See Remarks See Remarks Refer to SATIP-Q-010-01
3.15 Block valves installation See Remarks See Remarks Refer to SATIP-L-108-01
3.18 Structural Attachments & Access See Remarks See Remarks Refer to SATIP-M-001-01
4.0 PRE-COMMISSIONING
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.1 Tank Closure Inspection SATR-D-2003 SATR-D-2003 H H Use similar checklist to SATR-D-2003
Instrumentation and electrical pre- Refer to the respective SATIPs for Electrical &
4.2 See Remarks See Remarks
commissioning Instrumentation
Punch Listing/Final Inspection of Tank
4.3 SAIC-D-2021 SAIC-D-2021 H S Use SATR-A-2011
Installation
SA-6133 SA-6133
4.4 MCC Punchlisting H
(FEIL) (FEIL)
Refer to SATIP-A-004-06
4.5 Tightness test or Service test See Remarks See Remarks W W API 650 Appendix J exists for Small Tanks
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
###
###