You are on page 1of 12

SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018) Rev. 2018.05.

00 31-May-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

SHOP FABRICATED STORAGE TANK INSTALLATION


(UL-142 or API SPEC 12F & 12P)
SATIP-D-109-01 15-Jul-18 Mechanical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Review of Tank Data Sheet & Safety


1.1 SAIC-D-2014 SAIC-D-2014 RH RH
Instruction Sheet

2.0 MATERIAL RECEIVING

Appurtenances consist of Nozzles & manways,


External Visual Insp & Verification of
Venting Devices, Temperature Instruments, Level
2.1 Metallic Tank and its external SAIC-D-2015 SAIC-D-2015 W W
Gauging Systems, Sample Connections, and
Appurtenances*
Stairways/Ladders/Platforms

2.2 Structural Attachments & Access See Remarks See Remarks Refer to SATIP-M-001-01

Fabricated Piping Spool Inspection (if


2.3 See Remarks See Remarks Refer to SATIP-L-350-01
applicable) at nozzles.

2.4 Storage, Handling & Tank Preservation SAIC-D-2005 SAIC-D-2005 W S

Refer to respective SATIPs for Electrical & Instr:


Verification & Visual inspection of vendor
2.5 See Remarks See Remarks ( SATIP-P-113-01, P-515-01, J-100-01, J-200-
supplied electrical & instrumentation
01, J-300-01, J-902-03)

3.0 INSTALLATION

3.1 Concrete Placement See Remarks See Remarks Refer to SATIP-Q-001-02

Trench Preparation and backfilling for


3.2 See Remarks See Remarks Refer to SATIP-S-070-01 & SATIP-A-114-01
Buried Tanks

3.3 Grounding See Remarks See Remarks Refer to SATIP-P-111-01

3.4 Pre-Installation Inspection SAIC-D-2006 SAIC-D-2006 H W

Cathodic Protection (if required for tank Refer to SATIP X-600-02 or J-500-01
3.5 See Remarks See Remarks
bottom an/or internal shell) (Internal CP) as applicable

3.6 Inspection of FRP tank installation SAIC-D-2017 SAIC-D-2017 H H

Inspection of Under-Tank Leak detection


3.7 SAIC-D-2018 SAIC-D-2018 H H
& Sub-grade Protection (if required)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018) Rev. 2018.05.00 31-May-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

SHOP FABRICATED STORAGE TANK INSTALLATION


(UL-142 or API SPEC 12F & 12P)
SATIP-D-109-01 15-Jul-18 Mechanical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Inspection of Above Ground Small Metallic


3.8 Tank Installation Tank SAIC-D-2019 SAIC-D-2019 H W Use similar report to SATR-D-2001 or SATR-D-2002
Erection (above ground)

3.9 Grouting (if required) See Remarks See Remarks Refer to SATIP-Q-010-01

Refer to respective SATIPs for Electrical & Instr:


Hook-up of vendor supplied electrical &
3.10 See Remarks See Remarks ( SATIP-P-113-01, P-515-01, J-100-01, J-200-
instrumentation
01, J-300-01, J-902-03)

3.11 Piping Installation See Remarks See Remarks Refer to SATIP-L350-01

3.12 Tank Trim installation SAIC-D-2020 SAIC-D-2020 H W

Pressure Testing of API Tanks Refer to SATIP-A-004-06 (New)


A) Pre-Test Inspections A & B) SAIC-A-2026
3.13 See Remarks See Remarks
API 650 Appendix J exists for Small Tanks
B) Settlement Verification

Refer to the respective SATIPs for Electrical &


Verification & Visual inspection of vendor
3.14 See Remarks See Remarks Instrumentation: ( SATIP-P-113-01, P-515-01, J-100-
supplied electrical & instrumentation
01, J-200-01, J-300-01, J-400-01, J-902-03)

3.15 Block valves installation See Remarks See Remarks Refer to SATIP-L-108-01

Relief/Vacuum Valve installation


3.16 See Remarks See Remarks Refer to SATIP-J-600-01
inspection
See Note 1 of the General Notes and minimum of
3.17 Flange Joint Inspection SAIC-L-2014 SAIC-L-2014 W W
10%, thereafter.

3.18 Structural Attachments & Access See Remarks See Remarks Refer to SATIP-M-001-01

External Coating, Color coding & Refer to SATIP-H-002-03 OR H-002-05 as applicable


3.19 See Remarks See Remarks
Identification for field painting.
Refer to SATIP-N-001-01 or SATIP-N-001-02,
3.20 Insulation See Remarks See Remarks
whichever is applicable

Internal Visual Inspection of Small Metallic


3.21 SAIC-D-2016 SAIC-D-2016 W W
Tank and its internal components

4.0 PRE-COMMISSIONING

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018) Rev. 2018.05.00 31-May-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

SHOP FABRICATED STORAGE TANK INSTALLATION


(UL-142 or API SPEC 12F & 12P)
SATIP-D-109-01 15-Jul-18 Mechanical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

4.1 Tank Closure Inspection SATR-D-2003 SATR-D-2003 H H Use similar checklist to SATR-D-2003

Instrumentation and electrical pre- Refer to the respective SATIPs for Electrical &
4.2 See Remarks See Remarks
commissioning Instrumentation
Punch Listing/Final Inspection of Tank
4.3 SAIC-D-2021 SAIC-D-2021 H S Use SATR-A-2011
Installation
SA-6133 SA-6133
4.4 MCC Punchlisting H
(FEIL) (FEIL)
Refer to SATIP-A-004-06
4.5 Tightness test or Service test See Remarks See Remarks W W API 650 Appendix J exists for Small Tanks

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018) Rev. 2018.05.00 31-May-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

SHOP FABRICATED STORAGE TANK INSTALLATION


(UL-142 or API SPEC 12F & 12P)
SATIP-D-109-01 15-Jul-18 Mechanical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.05.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


15-Jul-18 15-Jul-18

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 15-July-2018 - REV. 2018.05.00 (Standards Cutoff -May 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.05.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


15-Jul-18 15-Jul-18

Saudi Aramco: Company General Use

You might also like