Professional Documents
Culture Documents
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY SUB-
REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CONTRACT CNTRCTR
ARAMCO
OR
3.6 Verification Centrifugal pump on the skid See Remarks See Remarks See SATIP-G-005-01
3.7 Verification of skid tank See Remarks See Remarks See SATIP-D-109-01
3.8 Verification of filter dryer for chiller See Remarks See Remarks See SATIP-D-001-01
3.9 Verification of Skid condenser cooler See Remarks See Remarks See SATIP-E-004-01
3.10 Verification of plate Heat exchanger See Remarks See Remarks See SATIP-E-014-01
3.11 Verification of Fin Fan coolers See Remarks See Remarks See SATIP-E-007-01
Verification of Piping installation &
3.12 See Remarks See Remarks See SATIP-L-350-01
connections
3.13 Grouting See Remarks See Remarks See SATIP-Q-010-01
3.14 Mechanical Pressure Testing See Remarks See Remarks See SATIP-A-004-03
3.15 Structural Component Installation See Remarks See Remarks See SATIP-M-001-01
Page 1 of 2
Rev 003
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-HTC-SK-
Skid Mounted Unit Installation 1-Dec-18 MECHANICAL
001
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY SUB-
REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CONTRACT CNTRCTR
ARAMCO
OR
3.16 Relief Valve Installation See Remarks See Remarks See SATIP- J-600-01
3.17 MOV's & Control Valves See Remarks See Remarks See SATIP-J-700-01
3.18 Instrumentation & Electrical Systems See Remarks See Remarks See SATIP-P-515-01 & SATIP-J-902-03
3.19 Instrument Piping & Tubing See Remarks See Remarks See SATIP-J-003-01
3.21 Painting & Color Coding See Remarks See Remarks Refer to applicable SATIP-H-series
4.0 PRE-COMMISSIONING
SAIC-HTC-SK- SAIC-HTC-SK-
4.1 Final Inspection & Walk-thru H S SATR-A-2011
2005 2005
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3 is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
Page 2 of 2