Professional Documents
Culture Documents
00 30-Apr-18
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Cross Country Above Ground Pipeline SATIP-L-450-03 3-Jul-18 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
CHECKLIST ASSIGNMENTS
ITEM QUALITY
PROJECT PHASE TASK / ACTIVITY and/or REMARKS
NO. RECORD LSTK
TEST RECORD
QA/QC PID
1.0 DOCUMENT REVIEW
Visual inspection & Material verification of S.Aramco to be notified for the arrival of the first batch
2.1 Pipe, Fittings, preformed bends (Cold & SAIC-L-2112 SAIC-L-2112 W W of delivered materials, then random inspection
Hot Bends) thereafter.
3.0 INSTALLATION
INSPECTION RESPONSIBILITY
CHECKLIST ASSIGNMENTS
ITEM QUALITY
PROJECT PHASE TASK / ACTIVITY and/or REMARKS
NO. RECORD LSTK
TEST RECORD
QA/QC PID
Welding & associated Special Process, Refer to SATIP-W-012-01 & NDE SATIPs as they are
3.4
NDE, PWHT, HT, PMI, Repairs, etc referenced
3.5 Verification of NDE Application Refer to the SATIP for the applicable NDE Method
3.14 Pipeline and Power Line Crossing SAIC-L-2121 SAIC-L-2121 W W See also SAES-B-064
INSPECTION RESPONSIBILITY
CHECKLIST ASSIGNMENTS
ITEM QUALITY
PROJECT PHASE TASK / ACTIVITY and/or REMARKS
NO. RECORD LSTK
TEST RECORD
QA/QC PID
INSPECTION RESPONSIBILITY
CHECKLIST ASSIGNMENTS
ITEM QUALITY
PROJECT PHASE TASK / ACTIVITY and/or REMARKS
NO. RECORD LSTK
TEST RECORD
QA/QC PID
Pipeline Internal
3.24 SAIC-L-2017 SAIC-L-2017 H W Use SATR-A-2008
Cleaning/Flushing/Scraping
Pressure Testing
3.25 a) Strength test Refer to SATIP-A-004-03
b) Tightness test
Flange Joint Inspection (Gasket Verification Use SATR-L-2001 - See Note 1, General Notes, plus
3.28 SAIC-L-2014 SAIC-L-2014 H W
& Bolt Tightening) minimum of 10% for witness by S. Aramco
4.0 PRE-COMMISSIONING
INSPECTION RESPONSIBILITY
CHECKLIST ASSIGNMENTS
ITEM QUALITY
PROJECT PHASE TASK / ACTIVITY and/or REMARKS
NO. RECORD LSTK
TEST RECORD
QA/QC PID
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1 of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
###
###