SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 8 COS 06/30/2014

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Cross Country Above Ground Pipeline SATIP-L-450-03 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD Construc LSTK Others
RECORD tion QC QA/QC PID (TBD)

1.0 DOCUMENT REVIEW

Welding Procedure Specification


1.1
(WPS & PQR) Refer to SATIP-W-012-01

1.2 Welder Qualification/Certification


Refer to SATIP-W-012-01

1.3 Pressure Test Package Refer to SATIP-A-004-03

Positive Material Identification Program


1.4 and Testing Procedure for Pressure- SAIC-L-2004 SAIC-L-2004 RH RH RH
Retaining Alloy Materials

1.5 Thrust Boring Procedure SAIC-L-2109 SAIC-L-2109 RH RH RH


Flanged Joint Gasket Verification & Bolt
1.6 SAIC-L-2002 SAIC-L-2002 RH RH RH
Tightening Procedure
Procedure for Piping Material
1.7 SAIC-L-2110 SAIC-L-2110 RH RH RH
Traceability for Pipeline Installation
Approval by SAPMT. Interface with Plants shall
1.8 Final Pipeline Route & Profile See Remarks See Remarks RH RH RH
utilize tie-in point using Plant Survey & Benchmarks
For Review & Approval by SAPMT per
1.9 Pipe Handling Procedure See Remarks See Remarks RH RH RH
SAES-L-450, Para. 8.1

2.0 MATERIAL RECEIVING

Visual inspection & Material verification S.Aramco to be notified for the arrival of the first
2.1 of Pipe, Fittings, preformed bends (Cold SAIC-L-2112 SAIC-L-2112 H W W batch of delivered materials, then random inspection
& Hot Bends) thereafter.

2.2 Valves Refer to SAES-L-108-001

3.0 INSTALLATION

3.1 Shop Fabrication Refer to SATIP-L-350-08

Pipeline Route, Profile & Right of Way


3.2 Refer to SATIP-L-450-01
Preparation

Saudi Aramco: Company General Use


SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Cross Country Above Ground Pipeline SATIP-L-450-03 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD Construc LSTK Others
RECORD tion QC QA/QC PID (TBD)

3.3 Stringing & Pipe Laying SAIC-L-2113 SAIC-L-2113 W W S

Welding & associated Special Process, Refer to SATIP-W-012-01 & NDE SATIPs as they
3.4
NDE, PWHT, HT, PMI, Repairs, etc are referenced

3.5 Verification of NDE Application Refer to the SATIP for the applicable NDE Method

3.6 Field Bending SAIC-L-2114 SAIC-L-2114 H H W

Pipeline Inspection prior to Welding of


3.7 SAIC-L-2115 SAIC-L-2115 H H W
Temperature Tie-In Weld Joint

3.8 Above ground anchors & Pipe Supports SAIC-L-2116 SAIC-L-2116 W W S

3.9 Concrete Placement Refer to SATIP-Q-001-02

3.10 Pile Driving Refer to Civil SATIP (to be determined)

3.11 Culvert Crossing SAIC-L-2118 SAIC-L-2118 W W W

3.12 Camel/Road Crossing W W W Refer to SATIP-Q-006-02 for Civil Requirements

3.13 Thrust Boring SAIC-L-2120 SAIC-L-2120 W W W

3.14 Pipeline and Power Line Crossing SAIC-L-2121 SAIC-L-2121 W W W See also SAES-B-064

3.15 Trenching & Backfilling Refer to SATIP-L-450-01

Thermal Expansion Relief Valve (for


3.16 Refer to SATIP-J-600-01
liquid service)
Pipeline Appurtenances Installation
3.17 SAIC-L-2122 SAIC-L-2122 W W S
(Including Surge Relief)

Sectionalizing Valves & Jump-


3.18 SAIC-L-2123 SAIC-L-2123 W W W
overs(Valve Stations)- (When required)

Sectionalizing Valve's electrical &


3.19 Refer to SATIP-J-700-01
Instrument requirements

Saudi Aramco: Company General Use


SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Cross Country Above Ground Pipeline SATIP-L-450-03 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD Construc LSTK Others
RECORD tion QC QA/QC PID (TBD)

3.20 Scraper trap Installation Refer to SATIP-L-420-01

Saudi Aramco: Company General Use


SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Cross Country Above Ground Pipeline SATIP-L-450-03 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD Construc LSTK Others
RECORD tion QC QA/QC PID (TBD)

3.21 Internal Coating of Field Welds Refer to applicable SATIP-H series

3.22 External Coating of Field Welds Refer to applicable SATIP-H series

3.23 Pre-Test Punchlisting-PIPELINES SAIC-L-2139 SAIC-L-2139 H H H Use SATR-A-2007

Pipeline Internal
3.24 SAIC-L-2017 SAIC-L-2017 H H W Use SATR-A-2008
Cleaning/Flushing/Scraping

Pressure Testing
3.25 a) Strength test Refer to SATIP-A-004-03
b) Tightness test

Refer also to SAES-L-108-001 for special lay-up


3.26 Lay-up SATR-A-2009 SATR-A-2009 H H H
requirements for Pipeline Valves (13Cr or 400SS)

3.27 Cathodic Protection Refer to applicable SATIP-X series

Flange Joint Inspection (Gasket Use SATR-L-2001 - See Note 1, General Notes,
3.28 SAIC-L-2014 SAIC-L-2014 H H W
Verification & Bolt Tightening) plus minimum of 10% for witness by S. Aramco

3.29 Pipeline Markers SAIC-L-2125 SAIC-L-2125 W W S

Pipelines Leak Detection System


3.30 (Except flowlines, trunklines, and test SAIC-L-2127 SAIC-L-2127 W W W
lines) per SAES-Z-003

4.0 PRE-COMMISSIONING

4.1 Caliper/Internal Gauging SAIC-L-2128 SAIC-L-2128 H H H Use SATR-L-2009

4.2 Pipeline Re-instatement/Final Inspection SAIC-L-2129 SAIC-L-2129 H H W Use SATR-A-2011

Final Inspection for Mech. Completion


4.3 SATR-A-6133 SATR-A-6133 H Use GI-2.710 & Applicable forms as agreed on
(MCC)
Refer to SATIP-A-004-05 for witnessing by
4.4 Tightness Testing
Commissioning Team

Saudi Aramco: Company General Use


SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Cross Country Above Ground Pipeline SATIP-L-450-03 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD Construc LSTK Others
RECORD tion QC QA/QC PID (TBD)

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3 organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use