Professional Documents
Culture Documents
Visual inspection & Material verification S.Aramco to be notified for the arrival of the first
2.1 of Pipe, Fittings, preformed bends (Cold SAIC-L-2112 SAIC-L-2112 H W W batch of delivered materials, then random inspection
& Hot Bends) thereafter.
3.0 INSTALLATION
Welding & associated Special Process, Refer to SATIP-W-012-01 & NDE SATIPs as they
3.4
NDE, PWHT, HT, PMI, Repairs, etc are referenced
3.5 Verification of NDE Application Refer to the SATIP for the applicable NDE Method
3.14 Pipeline and Power Line Crossing SAIC-L-2121 SAIC-L-2121 W W W See also SAES-B-064
Pipeline Internal
3.24 SAIC-L-2017 SAIC-L-2017 H H W Use SATR-A-2008
Cleaning/Flushing/Scraping
Pressure Testing
3.25 a) Strength test Refer to SATIP-A-004-03
b) Tightness test
Flange Joint Inspection (Gasket Use SATR-L-2001 - See Note 1, General Notes,
3.28 SAIC-L-2014 SAIC-L-2014 H H W
Verification & Bolt Tightening) plus minimum of 10% for witness by S. Aramco
4.0 PRE-COMMISSIONING
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3 organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection