SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SATR NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO TEST REPORT
Pre-Test Punch List Form SATR-A-2007 TESTING MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) / TEST PACK NO.: EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

A or B Requested Verified SA Insp-Initial/Date


Item Description By
ETC complete by QC of Concurrence or
# Item (Note 4)
(Use with the applicable Pre-Test Punchlist Checklist) (Note 2 & 3) (Initail/Agency) (Initial/Date) Remarks

1 Seal weld threaded nipples from headers to root valves at (5) A ABC/QC 1/1/2006 DEF-1/01/05 Not Complete.
locations (hydrocarbon service) per SAES-L-109, Section 8.
2 Guides are in direct contact with piping horizontal run at three B 3/5/2006
locations (6mm gap required). Relocate guides per drawing.
3 Check valve upstream clearance is not 5 pipe diameters (30" A 1/1/2006 DEF-1/01/05 RLC-1/01/05
req'd, 20" actual), in violation of SAES-L-108. Engineering!
4 Check valve is oriented in the wrong direction (flow arrow). B 3/2/2006
Reverse check valve to assure correct flow direction.
(Note: Valve to be re-posistioned after test.)

5 Piping clearance to structural bracing is 15 mm in violation of A 1/3/2006 DEF-1/01/05 RLC-1/010/05


SAES-L-310, Sect 12. (50 mm spacing req'd). Engineering!
6 NOTES:
a. Above Items are samples only to show
how to use the form.
b. Indicate " No Punch items. " if there are
no punch list to be recorded.
7

10

11

12

13

14

15

16

Notes: 1) This Form shall be used in conjunction with the applicable Pre-Test Punch Listing Checklist. (Refer to the applicable SATIP)
2) "A" items are items required to be completed before pressure test can proceed.
3) "B" items are items that can be cleared after pressure test or during re-instatement.
Any "B" items not completed during the re-instatement will be added to the Re-instatement Punchlist Form (SATR-A-2011)
for submission to Saudi Aramco for Mechanical Completion Punchlisting.
4) ETC -- Expected Time of Completion

Page 1 of 1