EQUIPMENT ID NUMBER(S) / TEST PACK NO.: EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
1 Seal weld threaded nipples from headers to root valves at (5) A ABC/QC 1/1/2006 DEF-1/01/05 Not Complete.
locations (hydrocarbon service) per SAES-L-109, Section 8.
2 Guides are in direct contact with piping horizontal run at three B 3/5/2006
locations (6mm gap required). Relocate guides per drawing.
3 Check valve upstream clearance is not 5 pipe diameters (30" A 1/1/2006 DEF-1/01/05 RLC-1/01/05
req'd, 20" actual), in violation of SAES-L-108. Engineering!
4 Check valve is oriented in the wrong direction (flow arrow). B 3/2/2006
Reverse check valve to assure correct flow direction.
(Note: Valve to be re-posistioned after test.)
10
11
12
13
14
15
16
Notes: 1) This Form shall be used in conjunction with the applicable Pre-Test Punch Listing Checklist. (Refer to the applicable SATIP)
2) "A" items are items required to be completed before pressure test can proceed.
3) "B" items are items that can be cleared after pressure test or during re-instatement.
Any "B" items not completed during the re-instatement will be added to the Re-instatement Punchlist Form (SATR-A-2011)
for submission to Saudi Aramco for Mechanical Completion Punchlisting.
4) ETC -- Expected Time of Completion