Professional Documents
Culture Documents
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A. Document Review
Schedule Q,
A1 Review documents for Material Receiving
Att. IV, Sec.3.1
Schedule Q,
A2 Identification procedure reviewed and implemented
Att. IV, Sec.3.2
B. General Requirements
Schedule Q,
B1 Documentation for traceability reviewed and implemented
Att. IV, Sec.3.3
C. Material Inspection
Check that the equipment to be installed has the approved type of SAES-P-100
C1
enclosure. (NEC 110.2) 5.2
Check for broken or damaged parts and contamination by foreign SAES-P-100
C2
materials. (NEC 110.12C) 5.2
Check for secure mounting and adequate ventilation space for SAES-P-100
C3
equipment. (NEC 110.13) 5.2
Page 1 of 4
SAUDI ARAMCO ID/PID - 02/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General - Switchgear Room / Substation, Equipment Pre-
SAIC-P-3003 1-Oct-05 ELECT-
Installation Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
For on-shore, outdoor installations, pad-mounted electrical equipment
shall be placed on a level concrete pad, the top of which is elevated a
minimum of 100 mm above natural grade. Unless greater clearances
are specified by the NEC, the following minimum clearances shall apply:
a) A minimum working clearance of 2 meters on all sides. SAES-P-116
C11 b) A minimum working clearance of 3 meters on the sides of the Sec. 7.2.5
equipment having doors or access panels which can be opened to
expose live parts.
c) The intent of the above requirements are met by gate(s) which can be
opened to provide the required clearance.
Exception 7.2.5:
Clearance between pad-mounted electrical equipment and fences or
walls installed for the purpose of protecting the equipment from SAES-P-116
C12 unauthorized access is permitted to be reduced to a minimum of 1 meter Sec. 7.2.5
with the concurrence of the proponent, provided that the 3-meter Exception 7.2.5:
clearance is maintained for equipment doors and access panels
required to be opened for normal maintenance and/or operations.
SAES-P-116
Commentary Note 7.2.5:
Sec. 7.2.5
C13 The above clearances are minimums, NFPA 70 or equipment
Commentary
manufacturer may require greater clearances for some installations.
Note 7.2.5:
Cable shall not be used to extend the main bus of switchgear, SAES-P-116
C14
controlgear, switchboards, switchracks and panelboards. Sec. 7.3
SAES-P-116
C16 Panelboards shall not be installed within the controlgear.
Sec. 15.4
SAES-P-103
C18 Battery room walls and floor shall be made of concrete construction.
Sec. 6.2.1
Battery rooms shall be provided with enclosed and gasketed (i.e., vapor SAES-P-103
C19
tight) corrosion resistant lighting fixtures. Sec. 6.2.3
Temperature in the battery room shall be maintained at, but shall not SAES-P-103
C20
exceed, 25 deg C. Sec. 6.3.6
SAES-P-103
C21 Return air-conditioning ducts from battery rooms shall be prohibited.
Sec. 6.3.7
False ceiling shall not be permitted in battery rooms and ceiling shall be SAES-P-103
C22
finished to avoid trapped pockets of hydrogen. Sec. 6.3.9
Page 2 of 4
SAUDI ARAMCO ID/PID - 02/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General - Switchgear Room / Substation, Equipment Pre-
SAIC-P-3003 1-Oct-05 ELECT-
Installation Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Emergency interior illumination shall be provided by one of the following:
6.8.1 Self-contained, battery-powered emergency lighting units, with
integral charger, which are automatically energized upon loss of 120 SAES-P-119
C26
VAC power. Sec. 6.8
6.8.2 Uninterruptible Power Supply (UPS) system located in the
substation.
Duplex, 3-wire, 20 A, 120 VAC (NEMA 5-20R) convenience outlets shall
be provided throughout the substation building. A minimum of one outlet SAES-P-119
C27
shall be provided for each 6 m of wall space at 1 m above the floor. A Sec. 6.9
minimum of two outlets per substation shall be provided.
Substation roof drainage shall not be to the transformer yard side of the SAES-P-119
C28
substation building. Sec. 6.11
Oil containment and/or oil drainage systems shall be provided for oil SAES-P-119
C31
filled equipment containing more than 2,500 liters of oil. Sec. 7.5
REFERENCE DOCUMENTS:
1. Schedule G Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), July 1993
2. Schedule Q Quality Requirements (Pro Forma Contract), November 2003
3. SAES-P-103 UPS and DC Systems 28 April, 2004
4. SAES-P-116 Switchgear and Control Equipment, 28 January, 2004
5. SAES-P-119 Onshore Substations, 31 May, 2004
6. NFPA 70 National Electrical Code (NEC) 2002 Edition
7. SAES-P-123 Lighting 30 September, 2003
Page 3 of 4
SAUDI ARAMCO ID/PID - 02/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
General - Switchgear Room / Substation, Equipment Pre-
SAIC-P-3003 1-Oct-05 ELECT-
Installation Inspection
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer
indicates compliance with appropriate standards or performance in a specified manner.
Page 4 of 4