00 30-Apr-19
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Welding Procedure
1.1 Specifications/Welding Procedure SAIC-W-2075 SAIC-W-2075 RH RH
Qualification Record (WPS/WPQR)
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-W-2082
Welding Equipment Calibration Random witnessing by S. Aramco at each calibration
2.2 SAIC-W-2082 SATR-W-2009 H W
Verification cycle.
SATR-W-2011
Positive Material Identification of Low SAIC-L-2010 Refer to Note 1 General Notes for SA Inspection
2.3 Alloy, Stainless Steel, Nickel & Copper SAIC-L-2010 SATR-L-2012 H W responsibility, after which pre-arranged witness is agreed
Based Materials (If Required) SATR-L-2013 upon.
3.0 INSTALLATION
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-W-2088
3.10 Selection of Weld Joints for NDE (Tanks) SAIC-W-2088 H R S. Aramco reviews on weekly basis.
SATR-W-2007
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Positive Material Identification (PMI) of SAIC-L-2010 Refer to Note 1 General Notes for SA Inspection
3.16 Deposited Weld for alloyed materials SAIC-L-2010 SATR-L-2012 H W/ R responsibility, after which pre-arranged witness is agreed
within the scope of SAES-A-206. SATR-L-2013 upon.
4.0 PRE-COMMISSIONING
Final Welding Insp & Documentation Refer to Applicable SATIP for Pressure Testing. Test Pkg
SAIC-W-2008
4.1 (Database Report, Welding Summary/ SAIC-W-2008 H R Documentation (per weld) shall contain final welding &
SATR-W-2008
Record & Weld Map) per SAEP-1160 special process acceptance docs.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of
1
Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
###
###