SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

HVAC Equipment SATIP-P-104-08 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Cable and Conduit Seal Installation To be reviewed and approved prior to electrical work at
1.1
Procedures
SAIC-P-3004 SAIC-P-3004 RH R job site
RECEIVING
2.0
INSPECTION
HVAC Equipment Material Receiving Notify SA by RFI of initial receipt of each listed item.
2.1
Visual Inspection
SAIC-P-3401 SAIC-P-3401 H W (By type or Manufacturer)

SATIP-P-113-01 LV Motor
SATIP-P-113-14 Variable Speed Drive Equipment
SATIP-P-116-07 LV Panelboard
SATIP-P-116-04 LV Controlgear
HVAC Electrical & Instrumentation
2.2 See Remarks See Remarks SATIP-J-100-01 Flow Instrumentation
Material Receiving Visual Inspection
SATIP-J-200-01 Pressure Instrumentation
SATIP-J-300-01 Liquid Level
SATIP-J-400-01 Temperature Instrumentation
SATIP-J-700-01 MOV's and CV's as applicable.

Storage, Handling, and Preservation


2.3 Visual Inspection and Testing For SAIC-P-3002 SAIC-P-3002 W S Weekly Inspection by Contractor QA/QC
Electrical Equipment

Storage, Handling, and Preservation


2.4 Visual Inspection and Testing For SAIC-T-5001 SAIC-T-5001 W S Weekly Inspection by Contractor QA/QC
Electronic Equipment

Storage, Handling, and Preservation


2.5 Visual Inspection and Testing For SAIC-P-3407 SAIC-P-3407 W S Weekly Inspection by Contractor QA/QC
LV Motor

Storage, Handling, and Preservation


2.6 Visual Inspection and Testing For LV SATR-P-3406 SATR-P-3406 W S Weekly Inspection by Contractor QA/QC
Motor and Space Heater

3.0 INSTALLATION

HVAC Equipment Installation &


3.1
Identification Visual Inspection
SAIC-P-3401 SAIC-P-3401 H W Notify SA by RFI on Installation of each HVAC system.

Page 1 of 4
03/09/2022 3:36 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

HVAC Equipment SATIP-P-104-08 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

SATIP-P-113-01 LV Motor
SATIP-P-113-14 Variable Speed Drive Equipment
SATIP-P-116-07 LV Panelboard
SATIP-P-116-04 LV Controlgear
HVAC Electrical & Instrumentation SATIP-J-100-01 Flow Instrumentation
3.2 Installation & identification Visual See Remarks See Remarks SATIP-J-200-01 Pressure Instrumentation
Inspection SATIP-J-300-01 Liquid Level
SATIP-J-400-01 Temperature Instrumentation
SATIP-J-700-01 MOV's and CV's and
SATIP-J-902-05 DCS / ESD / PLC / Scada
as applicable.

E & I Installation for


3.3 Pressurized Building SAIC-P-3406 SAIC-P-3406 H W
Visual Inspection

Fire Detection / Alarm


3.4 Equipment Installation See Remarks See Remarks SATIP-B-014-01 Fire Detection and Alarm
Visual Inspection

SATIP-P-104-03 Cable Tray


Conduit / Cable Tray
SATIP-P-104-05 A/G Conduit
3.5 Installation & Identification See Remarks See Remarks
SATIP-P-104-07 B/G Conduit
Visual Inspection
SATIP-P-111-01 Grounding & Bonding as applicable.

Conduit & Cable


See SATIP-J-902-01 Metallic Inst. and Control Cable
Hazardous Location Seal
3.6
Installation
SAIC-P-3209 SAIC-P-3209 H H
Hold point prior to motor energization.
Visual Inspection

See SATIP-J-902-01 Metallic Inst. and Control Cables


Cable Pulling / Laying
3.7
Visual Inspection
SAIC-P-3207 SAIC-P-3207 H W SA PID to be notified on start of this activity for each
HVAC system.

See SATIP-P-111-01 Grounding & Bonding


SATIP-J-902-01 Metallic Instrumentation and Control
Cable Gland Installation,
Cables
3.8 Cable Dressing, Identification, & SAIC-P-3207 SAIC-P-3207 H W
Termination Visual Inspection
SA PID to be notified on start of this activity for each
system.

4.0 PRE-COMMISSIONING

Page 2 of 4
03/09/2022 3:36 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

HVAC Equipment SATIP-P-104-08 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

SATIP-J-902-01 Instrumentation Cable


Cable Continuity
4.1 and Insulation Testing SATR-P-3203 SATR-P-3203 H W SA PID to be notified on start of this activity for each
(Installed Cable)
HVAC system.

SATIP-J-902-01 Instrumentation Cable


Cable termination
4.2 Crimp (wire pull-out) and See Remarks See Remarks
SA PID to be notified on start of this activity for each
Torque Testing
HVAC system

Power Cable Termination SA PID to be notified on start of this activity for each
4.3
Torque Testing
SATR-P-3205 SATR-P-3205 H W HVAC system.

Cable / Conduit See SATIP-J-902-01 Metallic Inst. and Control Cable


4.4 Hazardous Location Sealing SAIC-P-3209 SAIC-P-3209 H H
(where applicable) Hold point prior to motor energization.

Pre-Energization
In accordance with HVAC equipment manufacturer's
4.5 Visual Inspection and Testing SAIC-P-3401 SAIC-P-3401 H H instructions.
(for Energization Certificate)

Review EIL and all associated Quality Record


Pre-Energization
Energization See SATIP-P-111-01 Grounding & Bonding
4.6 Quality Document Review EIL
Certificate
RH RH SATIP-P-111-02 Sensitive Eqpt Grounding
and Energization Certificate
Hold point prior to energization.

Energized HVAC System


4.7 Functional Testing & Motor SATR-P-3402 SATR-P-3402 H W In accordance with motor manufacturer's instructions.
Four Hour Run Test

Review EIL and all associated Quality Record


Remote Control, Indication
4.8 See Remarks See Remarks
and Alarm Testing
SATIP-J-900-01 Instrument Loop Checking

Energized HVAC System


4.9
Final Inspection
See Remarks EIL H H Hold point prior to PMCC or MCC.

Review EIL and all associated Quality Record


Energized HVAC System
4.10 Quality Document Review FEIL PMCC/MCC RH RH Hold point prior to electrical service completion
and Mechanical Completion Certificate
certification.

Page 3 of 4
03/09/2022 3:36 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

HVAC Equipment SATIP-P-104-08 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1
of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 4 of 4