SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) REV 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Low Voltage Switchgear and Switchboards SATIP-P-116-03 30-Apr-13 Electrical


PROJECT TITLE: CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Review of EIL and all associated Quality


Energization Full review of documentation by Contractor QC and review
1.1 Records including Energization Package EIL
Certificate
R R with approval by SA PID.
Prior to Energized Equipment

2.0 RECEIVING INSPECTION

Weekly inspection by the contractor QC.


Switchgear / Switchboard
Storage, Handling, & Preservation
2.1
Visual Inspection and Testing
SAIC-P-3002 SAIC-P-3002 W S SA PID shall review Contractor's Equipment / Materials
Storage, Handling and Preservation Procedure.
Electrical Equipment
(Schedule-Q, Atta. IV, Sec. 6)

Weekly inspection by the contractor QC.


Switchgear / Switchboard
2.2 Storage, Handling, & Preservation SATR-P-3806 SATR-P-3806 W S SA PID shall review Contractor's Equipment / Materials
Visual Inspection and Testing Storage, Handling and Preservation Procedure.
(Schedule-Q, Atta. IV, Sec. 6)

LV Switchgear - Indoor/Outdoor
2.3 Equipment Material Receiving SAIC-P-3833 SAIC-P-3833 H W See GENERAL NOTES for typical accessories.
Visual Inspection

LV Switchboard
2.4 Material Receiving SAIC-P-3834 SAIC-P-3834 H W See GENERAL NOTES for typical accessories.
Visual Inspection

LV Power Circuit Breaker


Notify SA PID by RFI on initial receipt of each listed
2.5 Material Receiving SAIC-P-3835 SAIC-P-3835 H W equipment (by type and/or manufacturer).
Visual Inspection

See GENERAL NOTES for typical accessories.


LV Switchgear / Switchboard
2.6 Accessories Material Receiving SAIC-P-3837 SAIC-P-3837 H W Notify SA PID by RFI on initial receipt of each listed
Visual Inspection
accessory (by type and/or manufacturer).

3.0 INSTALLATION

Page 1 of 4
03/09/2022 3:39 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) REV 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Low Voltage Switchgear and Switchboards SATIP-P-116-03 30-Apr-13 Electrical


PROJECT TITLE: CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

LV Switchgear / Switchboard Hold point for substantial completion of building and


3.1 Pre-Installation SAIC-P-3003 SAIC-P-3003 H H electrical room civil / structural / architectural / HVAC finish
Visual Inspection work (i.e., no construction dust or fumes).

LV Switchgear
3.2 Installation & Identification SAIC-P-3840 SAIC-P-3840 H W See SATIP-P-111-01 Grounding and Bonding
Visual Inspection

LV Switchboard
3.3 Installation & Identification SAIC-P-3841 SAIC-P-3841 H W See SATIP-P-111-01 Grounding and Bonding
Visual Inspection

See SATIP-P-104-05 A/G Industrial Conduit


SATIP-P-104-03 Cable Tray
Conduit, and/or Cable Tray
SATIP-P-104-07 B/G Conduit
3.4 Installation & Identification See Remarks See Remarks H W SATIP-P-111-01 Grounding and Bonding
Visual Inspection
SATIP-P-116-12 LV Cablebus
As applicable.

Cable Pulling
3.5
Visual Inspection
SAIC-P-3207 SAIC-P-3207 H W Notify SA PID by RFI upon start of the activity

Cable Gland Installation,


3.6 Cable Dressing, Identification, SAIC-P-3207 SAIC-P-3207 H W See SATIP-P-111-01 Grounding and Bonding
& Termination Visual Inspection

4.0 PRE-COMMISSIONING

Cable Continuity
4.1 and Insulation Testing SATR-P-3203 SATR-P-3203 H W SATIP-P-116-12 LV Cablebus
(Installed Cable)

Power Cable
4.2
Torque Testing
SATR-P-3205 SATR-P-3205 H W SATIP-P-116-12 LV Cablebus

LV Switchgear Functional Testing


for Energization Certificate LV Switchgear Functional Testing
4.3
Protection Relay and Circuit Beaker
SATR-P-3816 SATR-P-3816 H H In accordance with manufacturer's instructions.
Trip Unit Testing and Setting

Page 2 of 4
03/09/2022 3:39 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) REV 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Low Voltage Switchgear and Switchboards SATIP-P-116-03 30-Apr-13 Electrical


PROJECT TITLE: CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

LV Power Circuit Breaker


LV Switchgear Functional Testing
4.4 Calibration and Setting SATR-P-3817 SATR-P-3817 H W In accordance with manufacturer's instructions.
for Energization Certificate

LV Switchgear
Pre-energization Functional Testing
4.5
and Visual Inspection
SAIC-P-3840 SAIC-P-3840 H H Notify SA PID by RFI upon start of the activity
for Energization Certificate

LV Switchboard
Pre-energization Functional Testing
4.6
and Visual Inspection
SAIC-P-3841 SAIC-P-3841 H H Notify SA PID by RFI upon start of the activity
for Energization Certificate

LV Switchgear Functional Testing


Pre-energization Functional Testing LV Switchgear Functional Testing
4.7
and Visual Inspection
SATR-P-3816 SATR-P-3816 H H In accordance with manufacturer's instructions.
for Energization Certificate

LV Power CB Functional Testing


Pre-energization Functional Testing LV Switchgear Functional Testing
4.8
and Visual Inspection
SATR-P-3817 SATR-P-3817 H W In accordance with manufacturer's instructions.
for Energization Certificate

Switchgear / Switchboard
Pre-energization Energization
4.9
Quality Document Review
EIL
Certificate
R R Review EIL and all associated Quality Records.
and Energization Certificate

Pre-Energized Switchgear / Switchboard LV Switchgear Functional Testing


4.10
Functional Testing
SATR-P-3816 SATR-P-3816 H H In accordance with manufacturer's instructions.

Pre-Energized Switchgear / Switchboard See See


4.11
remote indication and alarm testing Remarks Remarks
H H See SATIP-J-900-01 Instrument loop checking

Pre-Energized LV Switchgear
4.12
Final Visual Inspection
EIL SAIC-P-3840 H H Notify SA PID for final inspection prior to energization.

Pre-Energized LV Switchboard
4.13
Final Visual Inspection
EIL SAIC-P-3841 H H Notify SA PID for final inspection prior to energization.

Page 3 of 4
03/09/2022 3:39 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) REV 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Low Voltage Switchgear and Switchboards SATIP-P-116-03 30-Apr-13 Electrical


PROJECT TITLE: CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Pre-Energized Switchgear / Switchboard


PMCC
4.14 Quality Document Review and FEIL
MCC
H RH Review FEIL and all Quality Records.
Mechanical Completion Certificate

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1
of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
Switchgear / Switchboard accessories include storage cabinets, lifting devices, portable charging motor or hand crank (for stored-energy power C/Bs), test plugs, portable test kits for C/B trip units and
6
protection relays, termination hardware, terminal blocks, wiring and wire markers, CT's, PT's, CPT's, fuses, nameplates, and warning labels.

LEGEND
H Hold Point for QC Inspection or Testst R Review of Documents
W Witness Inspection/Test RH Review and Approval of Document
S Surveillance I 100% Contractor Inspection

Page 4 of 4
03/09/2022 3:39 PM

You might also like