SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Cable & Conduit Seal To be Reviewed and Approved Prior to Electrical Work at
1.1
Installation Procedure
SAIC-P-3004 SAIC-P-3004 RH R Jobsite.
SATIP-P-104-12 Receptacles
SATIP-P-123-01 Lighting
SATIP-P-116-04 LV Controlgear
SATIP-P-116-07 LV Panelboard
Crane Electrical Equipment
SATIP-P-116-14 VSD's
2.5 Material Receiving See Remarks See Remarks
SATIP-P-113-01 LV Induction Motors
Visual Inspection
SATIP-P-104-01 LV Cable
SATIP-P-111-01 Grounding and Bonding
SATIP-P-104-04 Boxes and Wireways
as applicable
Page 1 of 4
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
3.0 INSTALLATION
Cable Pulling
3.4
Visual Inspection
SAIC-P-3207 SAIC-P-3207 H W
4.0 PRE-COMMISSIONING
Page 2 of 4
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.2 Power Cable Torque Testing SATR-P-3205 SATR-P-3205 H W SA PID to be notified on start of this activity for each
system.
Hoist Specific
4.4
Pre-Energization Testing
SATR-P-3415 SATR-P-3415 H W Per manufacturer's instructions.
Pre-energization
In accordance with manufacturer's instructions.
4.7 Visual Inspection SAIC-P-3425 EIL H H Hold point prior to energization.
(for Energization Certificate)
Energized Crane
4.9
Functional Testing
SATR-P-3414 SATR-P-3414 H W Per manufacturer's instructions.
Page 3 of 4
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Energized Hoist
4.10
Functional Testing
SATR-P-3415 SATR-P-3415 H W Per manufacturer's instructions.
Energized Elevator
4.11
Functional Testing
SATR-P-3416 SATR-P-3416 H W Per manufacturer's instructions.
4.13 Final Visual Inspection See Remarks EIL H W Review EIL and all associated Quality Records
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
Page 4 of 4