SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Cranes, Hoists, and Elevators SATIP-P-113-04 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Cable & Conduit Seal To be Reviewed and Approved Prior to Electrical Work at
1.1
Installation Procedure
SAIC-P-3004 SAIC-P-3004 RH R Jobsite.

2.0 RECEIVING INSPECTION

Storage, Handling, and Preservation


2.1 Electrical Equipment SAIC-P-3002 SAIC-P-3002 I S Weekly Inspection by Contractor QA/QC
Visual Inspection

Storage, Handling, and Preservation


2.2 Electronic Equipment SAIC-T-5001 SAIC-T-5001 I S Weekly Inspection by Contractor QA/QC
Visual Inspection

Storage, Handling, and Preservation


2.3 LV Motor SAIC-P-3407 SAIC-P-3407 I S Weekly Inspection by Contractor QA/QC
Visual Inspection

Storage, Handling, and Preservation


2.4 LV Motor Space Heater Testing SATR-P-3406 SATR-P-3406 I S Weekly Inspection by Contractor QA/QC
Visual Inspection

SATIP-P-104-12 Receptacles
SATIP-P-123-01 Lighting
SATIP-P-116-04 LV Controlgear
SATIP-P-116-07 LV Panelboard
Crane Electrical Equipment
SATIP-P-116-14 VSD's
2.5 Material Receiving See Remarks See Remarks
SATIP-P-113-01 LV Induction Motors
Visual Inspection
SATIP-P-104-01 LV Cable
SATIP-P-111-01 Grounding and Bonding
SATIP-P-104-04 Boxes and Wireways
as applicable

Page 1 of 4
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Cranes, Hoists, and Elevators SATIP-P-113-04 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Accessories include busbars, collectors, slip rings, post


Crane Equipment and Accessories
insulators, collector cable, festoon track and cable, cable
2.6 Material Receiving SAIC-P-3424 SAIC-P-3424 H W reels, cable pendants, RF control system, and electric
Visual Inspection
brakes.

3.0 INSTALLATION

Also see SATIP-P-104-12 Receptacles


SATIP-P-123-01 Lighting
SATIP-P-116-04 LV Controlgear
Electrical Equipment
SATIP-P-116-07 LV Panelboard
3.1 Installation & Identification SAIC-P-3425 SAIC-P-3425 H W SATIP-P-116-14 VSD's
Visual Inspection
SATIP-P-113-01 LV Induction Motors
SATIP-P-111-01 Grounding and Bonding
SATIP-P-104-04 Boxes and Wireways

Also see SATIP-P-104-05 A/G Conduit


Conduit/Cable Tray Installation and SATIP-P-104-03 Cable Tray
3.2 Identification SAIC-P-3425 SAIC-P-3425 H W SATIP-P-104-07 B/G Conduit
Visual Inspection SATIP-P-111-01 Grounding & Bonding
as applicable.

Collector / Festoon / Pendant


3.3 Cable Installation SAIC-P-3425 SAIC-P-3425 H W
Visual Inspection

Cable Pulling
3.4
Visual Inspection
SAIC-P-3207 SAIC-P-3207 H W

See SATIP-P-111-01 Grounding & Bonding


Cable Gland, Cable Dressing, SATIP-J-902-01 Metallic Instrumentation and Control
3.5 Cable Identification & Termination SAIC-P-3207 SAIC-P-3207 H W Cables
Visual Inspection SA PID to be notified on start of this activity for each
system.

4.0 PRE-COMMISSIONING

Page 2 of 4
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Cranes, Hoists, and Elevators SATIP-P-113-04 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

See SATIP-J-902-01 Instrumentation Cable


Busbar / Cable Continuity
4.1
& Insulation Testing
SAIC-P-3203 SAIC-P-3203 H W SA PID to be notified on start of this activity for each
system.

4.2 Power Cable Torque Testing SATR-P-3205 SATR-P-3205 H W SA PID to be notified on start of this activity for each
system.

Crane Specific Testing


4.3
Pre-Energization Testing
SATR-P-3414 SATR-P-3414 H W Per manufacturer's instructions.

Hoist Specific
4.4
Pre-Energization Testing
SATR-P-3415 SATR-P-3415 H W Per manufacturer's instructions.

Elevator Specific Testing


4.5
Pre-Energization Testing
SATR-P-3416 SATR-P-3416 H W Per manufacturer's instructions.

Cable / Conduit See SATIP-J-902-01 Metallic Inst. and Control Cable


4.6 Hazardous Location Sealing SAIC-P-3209 SAIC-P-3209 H H
(where applicable) Hold point prior to motor energization.

Pre-energization
In accordance with manufacturer's instructions.
4.7 Visual Inspection SAIC-P-3425 EIL H H Hold point prior to energization.
(for Energization Certificate)

See SATIP-P-111-01 Grounding & Bonding


LV. Motor Pre-energization SATIP-P-111-02 Sensitive Eqpt Grounding
Energization
4.8 Quality Document Review EIL
Certificate
RH RH
and Energization Certificate In accordance with manufacturer's instructions

Energized Crane
4.9
Functional Testing
SATR-P-3414 SATR-P-3414 H W Per manufacturer's instructions.

Page 3 of 4
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Cranes, Hoists, and Elevators SATIP-P-113-04 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Energized Hoist
4.10
Functional Testing
SATR-P-3415 SATR-P-3415 H W Per manufacturer's instructions.

Energized Elevator
4.11
Functional Testing
SATR-P-3416 SATR-P-3416 H W Per manufacturer's instructions.

See SATIP-J-900-01 Instrument Loop Checking for


Remote Control, Indication,
4.12
and Alarm Testing
See Remarks See Remarks H W additional inspection and test requirements for signal and
control loops.

4.13 Final Visual Inspection See Remarks EIL H W Review EIL and all associated Quality Records

Quality Document Review and


4.14
Mechanical Completion Certificate
FEIL PMCC/MCC RH RH Review FEIL and all associated Quality Records

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 4 of 4