SAUDI ARAMCO ID/PID FORM REV 1 - 010109 ((Standards Cutoff-March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Very High Voltage (above 69 kV) Cable SATIP-P-104-11 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Cable Termination and Splicing


To be reviewed and approved prior to VHV electrical work
1.1 Special Work Procedure SAIC-P-3219 SAIC-P-3219 RH RH at job site
Document Review

Cable Splicer Certification and Job Clearance Cards (JCC's) to be issued prior to
1.2
Project Job Clearance Cards
SAIC-P-3219 SAIC-P-3219 RH RH commencement of VHV cable termination work.

Vendor Installation Manual- To be reviewed and approved prior to electrical work at


1.3
Cable Laying Method
See Remarks See Remarks RH RH job site
RECEIVING
2.0
INSPECTION
Storage, Handling, and Preservation
2.1
Visual Inspection
SAIC-P-3201 SAIC-P-3201 H W Weekly Inspection.

Cable Material Receiving


2.2
Visual Inspection
SAIC-P-3220 SAIC-P-3220 H H

Continuity and Insulation Continuity (Volt-Ohm Meter) and Insulation (Megger)


2.3
Testing (On Cable Reel)
SATR-P-3215 SATR-P-3215 H W Testing.

Cable accessories include cable pulling lubricant, hot and


VHV Cable Accessories cold shrink insulation tubing; electrical tape; cable straps
2.4 Material Receiving SAIC-P-3221 SAIC-P-3221 H W and ties; cable markers, crimp wire connectors; VHV
Visual Inspection cable termination kits; bulk electrical nuts, bolts and
washers; crimping tools & dies.

3.0 INSTALLATION

Direct Buried
Cable Trench See SATIP-P-104-07 for below grade conduit and duct
3.1
Visual Inspection
SAIC-P-3333 SAIC-P-3333 H H bank installation.
(Before Cable Laying)
Cable laying method shall be in compliance with
Cable Pulling
3.2
Visual Inspection
SAIC-P-3222 SAIC-P-3222 H W manufacturer's instructions.
See also SATIP-P-111-01 Grounding and Bonding
Below Grade Cable Laying
SA PID hold point for all direct buried VHV cables prior to
3.3 Visual Inspection For VHV Cable, SAIC-P-3222 SAIC-P-3222 H H backfilling of cable.
Identification, and Backfilling

Page 1 of 2
03/09/2022 3:36 PM
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 ((Standards Cutoff-March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Very High Voltage (above 69 kV) Cable SATIP-P-104-11 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Below Grade
3.4 Warning Device Installation SAIC-P-3333 SAIC-P-3333 H W
Visual Inspection
Cable dressing and termination work shall not proceed
until cable route and cable dressing in raceway or trench
Cable Dressing, Cable Identification, and
3.5
Termination Visual Inspection
SAIC-P-3222 SAIC-P-3222 H H has been inspected.
SA PID shall be notified on start of this activity for each
VHV circuit.

4.0 PRE-COMMISSIONING
Cable Continuity
Continuity (Volt-Ohm Meter) and
4.1 and Insulation Testing SATR-P-3216 SATR-P-3216 H W Insulation (Megger) Test.
(Installed Cable)
Hi-Pot cable insulation and jacket test in accordance with
VHV High-Potential cable manufacturer's instructions. If direct buried, perform
4.2
Withstand Testing
SATR-P-3218 SATR-P-3218 H H conductor insulation test before backfilling, and jacket test
after backfilling.
Cable Termination
4.3
Torque Testing
SATR-P-3217 SATR-P-3217 H W Hydraulic and mechanical crimping / bolting

Final Visual Inspection


4.4
(before energization certificate)
SAIC-P-3222 EIL H H Hold Point for Energization of Each VHV Circuit.

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3
is not present.

4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 2 of 2