SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 3 COS 06/30/2008

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Cable Tray, Fittings, and Accessories SATIP-P-104-03 Electrical


PROJECT TITLE: CONTRACT No. CONTRACTOR/SUBCONTRACTOR

Yanbu Export Refinery Project EPC-3 6600024370 Daelim Saudi Arabia Co. Ltd.

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD Sub SAUDI
DAELIM
Contractor ARAMCO

1.0 DOCUMENT REVIEW

Not Applicable
RECEIVING
2.0
INSPECTION
Cable Tray
2.1 Storage, Handling, and Preservation SAIC-P-3301 SAIC-P-3301 W W S Weekly Inspection by Contractor QC
Visual Inspection

Cable Tray
2.2 Material Receiving SAIC-P-3302 SAIC-P-3302 H H W
Visual Inspection Metallic Tray Systems

Cable Tray
See GENERAL NOTES for typical accessories.
Accessories
2.3 Material Receiving SAIC-P-3302 SAIC-P-3302 H H W Notify SA by RFI on receipt of each listed accessory (by
Visual Inspection for Metallic Tray
type or manufacturer).
Accessories

Cable Tray
See GENERAL NOTES for typical accessories.
Accessories
2.4 Material Receiving SAIC-P-3005 SAIC-P-3005 H H W Notify SA by RFI on receipt of each listed accessory (by
Visual Inspection for Channel and Strut
type or manufacturer).
Materials

Cable Tray See GENERAL NOTES for typical accessories.


Accessories
2.5
Material Receiving
SAIC-P-3306 SAIC-P-3306 H H W Notify SA by RFI on receipt of each listed accessory (by
Visual Inspection for Firewall Barriers type or manufacturer).

Jobsite type-testing of cable tray load rating. Required on


Metallic Cable Tray
absence of factory / third party test reports and
2.6 Jobsite Acceptance Test SATR-P-3301 SATR-P-3301 H H H manufacturer's nameplate identification. Hold point prior to
NEMA VE1 Static Loading
cable tray installation.

Page 1 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 3 COS 06/30/2008

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Cable Tray, Fittings, and Accessories SATIP-P-104-03 Electrical


PROJECT TITLE: CONTRACT No. CONTRACTOR/SUBCONTRACTOR

Yanbu Export Refinery Project EPC-3 6600024370 Daelim Saudi Arabia Co. Ltd.

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD Sub SAUDI
DAELIM
Contractor ARAMCO

1.0
3.0 DOCUMENT REVIEW
INSTALLATION

Cable Tray Installation


and Identification Numbering Hold point prior to cable pulling. SA PID to be notified on
3.1 Visual Inspection SAIC-P-3307 SAIC-P-3307 H H W start of tray installation for each process system or plant
(Before Cable Pulling) for Metallic Tray area.
Systems

Cable Tray Installation


Hold point prior to cable pulling. SA PID to be notified on
and Identification Numbering
3.2
Visual Inspection
SAIC-P-3309 SAIC-P-3309 H H W start of tray installation for each process system or plant
area.
(Before Cable Pulling) for Fire Barrier

4.0 PRE-COMMISSIONING

Cable Tray See SATIP-P-111-01 Grounding and Bonding


Visual Inspection Hold point prior to tray cover installation. SA PID to be
4.1
(Before Cover Installation) for Metallic
SAIC-P-3307 SAIC-P-3307 H H W notified on start of inspection for each process system or
Tray Systems plant area.

See SATIP-P-111-01 Grounding and Bonding


Cable Tray
Hold point prior to tray cover installation. SA PID to be
4.2 Visual Inspection SAIC-P-3309 SAIC-P-3309 H H W notified on start of inspection for each process system or
(Before Cover Installation) for Fire Barrier
plant area.

Cable Tray
Hold point prior to fireproofing. SA PID to be notified on
Final Visual Inspection
4.3
(Before Fireproofing) for Metallic Tray
SAIC-P-3307 SAIC-P-3307 H H W start of final inspection for each process system or plant
area.
Systems

Cable Tray Hold point prior to fireproofing. SA PID to be notified on


4.4 Final Visual Inspection SAIC-P-3309 SAIC-P-3309 H H W start of final inspection for each process system or plant
(Before Fireproofing) for Fire Barrier area.

Page 2 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 3 COS 06/30/2008

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Cable Tray, Fittings, and Accessories SATIP-P-104-03 Electrical


PROJECT TITLE: CONTRACT No. CONTRACTOR/SUBCONTRACTOR

Yanbu Export Refinery Project EPC-3 6600024370 Daelim Saudi Arabia Co. Ltd.

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD Sub SAUDI
DAELIM
Contractor ARAMCO

1.0 DOCUMENT REVIEW


GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of
1
Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

Cable tray accessories include bulk mechanical fasteners, splice plates, end plates, drop-out plates, barrier plates, hinged joints, expansion joints, covers, clips, clamps, straps, banding materials, and
6 banding tools. Channel and strut materials include all mechanical fasteners, anchors, threaded rods, fittings, and brackets required to provide full-load-rated supplemental supports. Fire barrier materials
include fire rated mortar, intumescent sealing, fire-rated silicone foam, and component thru-wall barriers.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 3 of 3