SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO
Not Applicable
Diesel-Generator
Material Receiving
2.5
Visual Inspection for Diesel-Generator
SAIC-P-3422 SAIC-P-3422 H W
Enclosure
Diesel-Generator
Material Receiving
2.6
Visual Inspection for Diesel-Generator
SAIC-P-3421 SAIC-P-3421 H W
Set
Diesel-Generator
Accessories
2.7
Material Receiving
SAIC-P-3103 SAIC-P-3103 H W
Visual Inspection for VRLA Battery
Page 1 of 5
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO
Diesel-Generator
Accessories
2.8
Material Receiving
SAIC-P-3112 SAIC-P-3112 H W
Visual Inspection for Battery Charger
Diesel-Generator
Accessories
2.9 Material Receiving SAIC-P-3422 SAIC-P-3422 H W
Visual Inspection for Generator Load Test
Set
Diesel-Generator
Accessories
2.10 Material Receiving SAIC-P-3422 SAIC-P-3422 H W
Visual Inspection for Voltage Regulator /
Control Panel
Diesel-Generator
Accessories
2.11 Material Receiving SAIC-P-3422 SAIC-P-3422 H W
Visual Inspection for Generator Circuit
Breaker
3.0 INSTALLATION
Diesel-Generator
3.1 Installation & Identification SAIC-P-3423 SAIC-P-3423 H W Also see SATIP-P-104-04 Boxes and Enclosures and
Visual Inspection for D-G Set Installation
Page 2 of 5
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
Cable Continuity
See SATIP-J-902-01 Instrumentation Cable
4.1 and Insulation Testing SATR-P-3203 SATR-P-3203 H W SATIP-P-104-01: Low Voltage (600V to 1kV) Cable
(Installed Cable)
4.3 Storage Battery Testing for VRLA Battery SATR-P-3104 SATR-P-3104 H W In accordance with battery manufacturer's instructions.
Page 3 of 5
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO
Pre-energization
Visual Inspection and Testing
4.7
(for Energization Certificate) for D-G Set
SAIC-P-3423 SAIC-P-3423 H H In accordance with D-G Set manufacturer's instructions.
Installation and Pre-Commissioning
Pre-energization
Visual Inspection and Testing
4.8
(for Energization Certificate) for Insulation
SATR-P-3413 SATR-P-3143 H H In accordance with D-G Set manufacturer's instructions.
Resistance and Functional Testing
Energized Diesel-Generator
Visual Inspection and
4.11
Functional Testing for Insulation
SATR-P-3413 SATR-P-3413 H H In accordance with D-G Set manufacturer's instructions.
Resistance and Functional Testing
Diesel-Generator
4.12 See Remarks See Remarks SATIP-J-900-01 Instrument Loop Checking
Remote Indication and Alarm Testing
Page 4 of 5
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
Page 5 of 5
03/09/2022 3:38 PM