You are on page 1of 3

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Controlgear SATIP-P-116-02 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 RECEIVING INSPECTION

MV Controlgear - Indoor
Notify SA PID by RFI on initial receipt of each listed
1.1 Material Receiving SAIC-P-3824 SAIC-P-3824 I W accessory by type and/or manufacturer.
Visual Inspection

Power Circuit Breaker


Notify SA PID by RFI on initial receipt of each listed
1.2 Material Receiving SAIC-P-3825 SAIC-P-3825 I W accessory by type and/or manufacturer.
Visual Inspection

2.0 INSTALLATION

Hold point for substantial completion of building and


Indoor Pre-Installation
2.1
Visual Inspection
SAIC-P-3003 SAIC-P-3003 H H electrical room civil / structural / architectural finish work
(i.e., no construction dust or fumes).

Installation & Identification


2.2 Visual Inspection SAIC-P-3829 SAIC-P-3829 H H See SATIP-P-111-01 Grounding and Bonding
MV Controlgear Metal Enclosed

See SATIP-P-104-05 A/G Conduit


SATIP-P-104-03 Cable Tray
Conduit, and/or Cable Tray
SATIP-P-104-07 B/G Conduit
2.3 Installation & Identification See Remarks See Remarks
SATIP-P-111-01 Grounding and Bonding
Visual Inspection
SATIP-P-116-10 Medium Voltage Cablebus
(Maximum 15 kV)

See SATIP-P-104-01 LV Cable and Wire


SATIP-J-902-01 Metallic Instrument Cable
Cable Pulling SATIP-P-116-10 Medium Voltage Cablebus
2.4 See Remarks See Remarks
Visual Inspection (Maximum 15 kV)
SATIP-P-104-02 Medium Voltage Cable and Conductors
(up to 35 kV)

See SATIP-P-104-01 LV Cable and Wire


SATIP-J-902-01 Metallic Instrument Cable
Cable Gland Installation,
SATIP-P-116-10 Medium Voltage Cablebus
2.5 Cable Dressing, Identification, SAIC-P-3214 SAIC-P-3214 H W (Maximum 15 kV)
& Termination Visual Inspection
SATIP-P-104-02 Medium Voltage Cable and Conductors
(up to 35 kV)

Page 1 of 3
03/09/2022 3:39 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Controlgear SATIP-P-116-02 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

3.0 PRE-COMMISSIONING

See SATIP-P-104-01 LV Cable and Wire


Cable Continuity, SATIP-J-902-01 Metallic Instrument Cable
Insulation Resistance, and SATIP-P-116-10 Medium Voltage Cablebus
3.1
Insulation Withstand Testing
SATR-P-3208 SATR-P-3208 I W (Maximum 15 kV)
(Installed Cablebus or Cable) SATIP-P-104-02 Medium Voltage Cable and Conductors
(up to 35 kV) As applicable.

MV Controlgear
3.2
Pre-Energized and Functional Testing
SATR-P-3812 SATR-P-3812 I W In accordance with manufacturer's instructions.

Power Cable / Bus Termination See SATIP-P-104-01 LV Cable and Wire


3.3
Torque Testing
SATR-P-3209 SATR-P-3209 I W SATIP-P-116-12 MV Cablebus as applicable.

Protection Relay and


Circuit Beaker Trip Unit
Coordinate activity with other relevant witnessing parties.
3.4 Testing and Setting SATR-P-3801 SATR-P-3801 I W (Facility Proponent)
for Energization Certificate
Protection Relays

Pre-energization Functional Testing


and Visual Inspection Review all required quality documents prior to functional
3.5
for Energization Certificate
SAIC-P-3829 SAIC-P-3829 I W testing/energization.
MV Controlgear - Indoor

Pre-energization Functional Testing


and Visual Inspection Review all required quality documents prior to functional
3.6
for Energization Certificate
SAIC-P-3830 SAIC-P-3830 I W testing/energization.
MV Power Circuit Breaker

Quality Document Review Energization Review EIL and all quality documents prior to
3.7
and Energization Certificate
EIL
Certificate
RH RH energization.

Page 2 of 3
03/09/2022 3:39 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Controlgear SATIP-P-116-02 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Energized MV Controlgear
3.8 Remote Control, Indication, See Remarks See Remarks H W See SATIP-J-900-01 Instrument loop checking
and Alarm Testing

Energized MV Controlgear Review FEIL and all associated Quality Records.


3.9 Quality Document Review and FEIL PMCC/MCC RH RH
Mechanical Completion Certificate Hold point prior to certified completion of the MV system.

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

Controlgear accessories include storage cabinets, lifting devices, portable charging motor or hand crank (for stored-energy power C/Bs), test plugs, portable test kits for C/B trip units and protection
6
relays, overload relay heating elements, termination hardware, terminal blocks, cable and wire markers, CT's, PT's, CPT's, fuses, nameplates, and warning labels.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 3 of 3
03/09/2022 3:39 PM

You might also like