ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
I. PRELIMINARY
1
Construction
Equipment Page 2 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
Management's ability to empower construction equipment is affect the performance
of the Contractor to execute the work, to achieve quality, appropriate cost, meet schedules
and work safely.
1. Purpose
• Preventive Maintenance
• Corrective Maintenance
2. Scope Of Work
2
Construction
Equipment Page 3 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
construction tools and operational vehicle plan, and Plan for procurement and financing of
vehicle and heavy equipment
By following the procedures and plan so the contractor can working with safely
and effective.
3. Definition and Abbreviation The following words and phrases shall have the meanings
hereby assigned to them, except where the context otherwise requires;
II. ORGANIZATION
a. Organization chart
3
Construction
Equipment Page 4 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
• Update the work plan in line with the recent changes of the procedures
applicable in the company.
➢ Equipment Operation Supervisor Roles and responsibilities of equipment operation
supervisor
• To handle equipment & light vehicle hand over from CEM department to
construction team
• To supervise and manage equipment moving activities
• To supervise and manage lifting and piling activities
• To analyze equipment utilization and work load
• To monitor maintenance schedule
➢ Equipment Maintenance & Mobilization Supervisor Roles and responsibilities of
transport and mobilization supervisor :
• To manage equipment and light vehicle mobilization activities and
Documentation
• To manage equipment and light vehicle demobilization activities and
Documentation
• To manage transportation activities (bus and pool car) and documentation
• To monitor and manage maintenance activities
• To manage repair activities
➢ Equipment Moving Coordinator
❖ Roles and Responsibilities
• To coordinate and execute equipment moving request
• To coordinate and execute any escort request
➢ Lifting & Piling Coordinator
❖ Roles and Responsibilities
• To coordinate and execute lifting activities
• To coordinate and execute piling activities
• To manage lifting and piling documentation and report
➢ CEM Inspector
❖ Roles and Responsibilities
• To coordinate and execute equipment & light vehicle mobilization :
• Pre-inspection process, Inspection & Re-inspection process
• New and re-new permit process
• Demobilization process
• To coordinate and arrange transportation for project requirement (Bus & Pool
Car)
• To conduct periodic equipment/vehicle inspection
• To develop audit and inspection program
• To manage and conduct audit and inspection program
➢ Mechanic coordinator
❖ Roles and Responsibilities
• To compile and develop preventive maintenance master schedule
4
Construction
Equipment Page 5 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
•
To monitor preventive maintenance schedule and communicate it to
construction team
• To supervise maintenance activities
• To supervise repair activities
• To manage mechanic work assignment and activities
➢ Mechanic team
❖ Roles and Responsibilities
• To conduct and handle maintenance activities
• To conduct and handle repair activities
➢ CEM admin
❖ Roles and Responsibilities
• To administer all documentation activities within CEM department.
The contractor will assign the standard of qualified technicians to ensure the
maintenance in accordance with the specifications for each unit of equipment and
vehicles. For this case the Contractor will perform:
5
Construction
Equipment Page 6 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
Heavy equipment and contractor vehicles will be operated and maintained in good
condition. Category of maintenance plans are grouped into 3 (three) categories as
follows :
At Field Work
Company’s Area
Emergency
Maintenace At
Safe Point at
Field
• Inspection and regular maintenance (e.g. every 2500KM) and multiplication is done by
a CEM team. minor treatmentssuch as replacement tires, carried out in the work area.
Major maintenance and/or routinely carried out in yard/workshop belonging to the
contractor.
➢ Examination of legal documents and license /certificate (STNK, KEUR) is carried out by a
CEM Team (admin) every week using a vehicle card or alert systems on the
spreadsheet.
7
Construction
Equipment Page 8 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
• Checking the validity period of the Company permit is carried out by the CEM team
(admin) and arrange permit from the Company together with a team of HES
Contractors.
• Checking of the age of the vehicle is carried out by the CEM team (admin). Age of
vehicles used by the Contractor must meet requirements of the Company.
. • Inspection and regular maintenance (e.g. every 200 hours of work excavator) and
• Checking the validity period of the Company permit is carried out by the CEM team
(admin) and arrange permit from the Company together with a HES Team.
• Checking the age of heavy equipment is carried out by a CEM team (admin). Age of
heavy equipment used by the Contractor must meet requirements of the Company.
If the heavy equipment/vehicles used do not give the expected results, CEM
Maintenance Supervisor is responsible to solve the problem or to consult with superiors
before the equipment reuse. CEM Maintenance supervisors are responsible for ensuring the
machine / vehicles are safe to use and meets the applicable regulations, to produce
optimal productivity. The contractor will provide Maintenance Shop area outside the
Company Area, and in this shop there are stock of spare parts. Contractors provide
8
Construction
Equipment Page 9 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
permanent personnel every day, and he is responsible for performi ng the routine
maintenance recommended manufacturers, such as cleaning, lubrication, tuning control
devices, replacing the lamp, and more. Corrective and maintenance action generally also
include finding and isolating the damaged section. When a failure module is found, it must
be reported to the Depot. Depot will provide replacement parts, and after the component
is received, then the mechanic doing the replacement of damaged components and handed
back the failure part to the depot for recorded within 3 days after installation.
• Routine Maintenance
• The maintenance is carried out at the time of heavy equipment/vehicle is still
in the period of work (on service).
• Schedule by day/usage meter. o The maintenance such as Visual Inspection,
hygiene, functional testing, inspection lubricants, and other.
• Maintenance Test o Maintenance using test equipment to check for heavy
equipment / vehicle.
• This treatment is done in conditions of heavy equipment/vehicle were not given
workload.
• This treatment such as check balance, spooring, and more.
• Diagnosis Test
• Testing Is done to heavy equipment / vehicle after something unusual , for
example, after malfunction , after the parts were unloaded and replaced, and
more.
• Diagnosis is done when the heavy equipment be expected to have suffered a
decline in performance, decreased function.
CEM Maintenance Supervisor is responsible to make sure these procedures are applied and
implemented.
9
Construction
Equipment Page 10 of 10
ISSUED BY : HES Dept management Plan
DOC NO : HSE-CEM-PHR-01.00 REV. 0
Area/Dept : Pematang Substation No.Contract : SPHR00534A
DATE. 15 DES 2023
• Every day, the driver must inspect the vehicle shortly after being kicked out of the
garage. If found the interference immediately reported to the CEM team.
• accessibility, or could cause damage to other components, then the vehicle should not
be used.
• Maintenance Card
• The report interference problems from the driver or operator to the CEM
problems that come from PTl or when the operation should be recorded on the
Maintenance Card.
• Maintenance Card contains specific problems and specific time.
• Maintenance Card continued to head of mechanic for the coordination of actions
repair/maintenance.
10